NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number MW-25745
John E. Cloney, Referee
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Norfolk and Western Railway Company
STATEMENT OF CLAIM: 'Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when it assigned outside
forces to perform masonry repair work in the Hickory Tunnel at Hickory,
Pennsylvania November 1 through November 24, 1982, both dates inclusive.
(2) As a consequence of the aforesaid violation, furloughed B&B
employes T. Ciesielski, O. M. Marsili and D. L. Wingard shall each be allowed
one hundred forty-four (144) hours of pay at their respective straight-time
rates."
OPINION OF BOARD: Article 1, the Scope Rule in the Agreement, provides:
"These rules govern the hours of service and working
conditions of all employees in the Maintenance of Way and
Structures Department
...
and all other employees performing work properly recognized as work belonging to
and coming under the jurisdiction of the maintenance
of Way Department
....·
Article II provides that "seniority rights of employees are confined
to the subdepartment in which employed" with some exceptions not applicable
here.
On August 26, 1946 Carrier's predecessor and the Organization
signed the following:
'MEMORANDUM OF NEGOTIATION
PAINT AND MASONRY GANG
'Purpose of meeting is to negotiate rates for a proposed
gang to be known as the Paint and Masonry Gang. The
work of this gang will cover the entire system of
cleaning
and painting of bridges, buildings and other structures.
It will also embrace such work as the repairs, construction and reconstruction of masonry structures
archer bridges, tunnel linings, drains, sewer lines, ash
pits, water station foundation, etc.
Wr »
Award Number 25860 page 2
Locket Number MW-25745
'Journeymen - B 6 B mechanics and painters rate is agreed
at $1.125 per hour. The same rate is now paid on Bridge
Carpenter Gang.'
Article IV of the 1968 National Agreement of the parties states:
'ARTICLE IV - CONTRACTING OUT
'In the event a carrier plans to contract out work within
the scope of the applicable schedule agreement, the
carrier shall notify the General Chairman of the organization involved in writing as far in advance
...
as is
practicable and in any event not less than 15 days prior
thereto.'
The Article further provides for a meeting if requested by the General
Chairman and goes on to state:
'...
but if no understanding is reached the carrier
may nevertheless proceed with said contracting, and the
organization may file and progress claims in connection
therewith.
Nothing in this Article IV shall effect the existing
rights of either party in connection with contracting out
..."
In December, 1981 the parties agreed to establish a LaborManagement Committee to study proble
efficient utilization of the work force. In a letter dated December 11, 1981
it was stated:
'The carriers assure you that they will assert good faith
efforts to reduce the incidence of subcontracting and
increase the use of their maintenance of way forces to
the extent practicable, including the procurement of rental
equipment and operation thereof by carrier employees.'
On August 6, 1982 Carrier wrote the Organization 'to advise that we
intend to make repairs to Hickory Tunnel using a contractor'. The Organization
requested a meeting, it was held on August 31, 1982, and on September 27,
1982 Regional Engineer Beesley advised:
'we are proceeding with the contracting of the work at
Hickory Tunnel was stated in my letter of August 6, 1982
on the basis that the Railway has neither the specialized
equipment, labor, or supervision to perform the work
required.'
The work included inspection of the tunnel for cracks and use of
pressurized epoxy and concrete to repair them where found.
Award Number 25860 Page 3
Docket Number MW-25745
In filing the claim on November 25, 1982,
General Chairman
Gardner
contended that at the
conference the
Organization requested Carrier 'rent
machines needed' but Carrier responded 'what they do with their money is
their business.' Carrier declined the claim on January 28, 1983 on the basis
that the Organization failed to cite a rule; that it was
excessive and
the
cork was 'beyond the training and
expertise of
our employes in that they have
not worked with pressure applied epoxy and shotcrete and we do not have the
equipment to perform this work with our forces.' The claim was advanced and
on February 22, 1983 the Regional Engineer affirmed denial for the reasons
previously stated plus the further reason that Ono B 6 B
Carpenters were
furloughed during the time the contractor worked
....'
and 'Painters cannot
be considered proper claimants for this type of work.' In a May 13, 1982
letter to the
General Chairman,
Carrier stated the 'work involved the use of
pressure - applied epoxy and shotcrete, which must be applied with the aid of
specialized equipment which Carrier does not own. Also, Carrier's employes
have no
experience concerning these
techniques and are not qualified to
perform this specialized work
...."
The Organization responded that
Supervisor C. H. Cummins had been B s B Foreman during a two year period when
certain
tunnel work
was performed including 'Grout was pumped in the
Pittsburgh Tunnel, holes drilled in tunnel wall, and grout pumped in behind
the wall.'
The Organization argues the work involved is clearly reserved to
the Paint and Masonry Gang by the August, 1946 Agreement and cites numerous
Awards including Award 3955 which hold:
'It is a fundamental rule that work of a class covered
by an agreement belongs to those for whose benefit the
contract was made. A delegation of such work to others
not covered by the Agreement is violative
....'
The Organization concedes Carrier did not own the equipment required
to apply epoxy and shotcrete but insists Carrier was required by the December
11, 1981 letter to make a good faith effort to rent or lease such equipment.
The Organization characterizes the assertion that Carrier employes lacked the
necessary expertise as
untrue, but argues even if it were true, it would not
constitute a valid reason for subcontracting. In taking these positions the
Organization relies on Awards which hold that 'the subject of the Carrier's
contract with its employes is work and not equipment" (Award 6905) and 'It
appears well established that mere lack of qualified employes does not
furnish a carrier with grounds for removal of work covered by a Scope Rule'
(Award 5839).
Award Number 25860 Page 4
Locket Number MW-25745
Referring to a Third Division Award issued in September, 1974
(Award 20372) dealing with a dispute between these parties the Organization
notes Carrier in that case argued it was using the shotcrete process. Thus
the organization contends
this
process has been Carrier's standard method of
tunnel repair and if, as argued, the Carrier's forces lacked necessary skills
there was an obligation to train employes.
Carrier contends the work requires use of expensive, specialized
machinery which must be closely monitored. It notes the work on the tunnel
should last 20 years and therefore there is not enough of this work to enable
its employes to become proficient. In this regard Carrier relies upon Awards
holding 'Carrier's right to contract work when special skills, equipment or
material are required
..."
(Award 18046) and 'The Carrier is nor required to
have expensive equipment whose use is only occasionally needed
...'
(Award
13272).
Carrier does not dispute the Organization's claim regarding pumping
grout, etc. in the past but denies that it is comparable to the work at
issue. It states the use of shotcrete and pressurized epoxy are new developments and every project w
contract.
Finally the Carrier argues the purpose of the August, 1946 Agreement
was to formulate rates for a particular gang and this gang was discontinued
years ago.
In considering Carrier's argument that the 1946 Agreement dealt
solely with a gang long since discontinued we immediately note this assertion
is not supported by evidence, nor was it raised during handling on the
property. We believe the work involved here is work reserved to the Bridge
and Building Department by Agreement unless contracting of it can otherwise
be justified. As stated in Award 20372, ·Carrier has the burden to justify
an exception". (In our view Carrier has not supported its position that its
employes are not qualified to perform the disputed work. While admitting its
employes pumped grout, etc. Carrier makes no explanation of how the skills
for these jobs differ, if at all.) Rather Carrier merely asserts the epoxy
and shotcrete are new developments, but the facts show at least with
reference to the shotcrete, that there have been disputes between the parties
concerning it since about 1970. While the Carrier now states it has consistently contracted every pr
evidence in support of this assertion is offered. Neither can we find any
indication of this argument being raised during handling on the property. (As
we find this is work of a type reserved by Agreement to the claiming employes,
and as Carrier has presented no evidence to establish its employes were not
capable of performing the work, or that the work has consistently been
contracted out, there is no need to reach the question of the extent of
Carrier's responsibility to train.)
Award Number 25860 Page 5
Docket Number MW-25745
Carrier has cited Awards which stand for the proposition that
'Carrier is not required to have expensive equipment whose use is only
occasionally needed
...^
(Award 13272) and need not -purchase a substantial
amount of equipment which it might not use again- (Award 11493). We are
again faced with an evidentiary void. The record is silent on the question
of how extensive or expensive the necessary equipment is, how readily
available leased or rented equipment might be and what efforts in that
direction were made by Carrier. The only information of record is the
Organization's undenied statement that when it requested Carrier to rent
needed machines Carrier replied that "what it did with its money is their
business'. Thus there is no showing that machine rental would not have been
feasible.
This Board has repeatedly held:
"...
one of a group entitled to perform the work may
prosecute a claim even if there be others having a
preference to it. The essence of the claim by the Organization is for Rule violation
....
The fact that another
employee may have a better right to make the claim is of
no concern
...
and does not relieve Carrier of the violation
.... " (Award
18557)
We believe the above stated principle applies here. If, as Carrier
contends, no B s B Department carpenters were on furlough and it would have
been carpenters, rather than Claimants who would have performed the work, no
relief would be afforded Carrier by virtue of that fact. The seniority
,roster is departmental and its benefits are available to all within its
coverage.
FINDINGS: The Third Division of the Adjustment Board, upon the whole record
and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute are
respectively Carrier and Employes within the meaning of the Railway Labor
Act, as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over the
dispute involved herein; and
That the Agreement was violated.
Award Number 25860 Page 6
Docket Number MW-25745
A W A R D
Claim sustained.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division:
Nancy .fiver - Executive Secretary
Dated at Chicago, Illinois, this 30th day of January 1986.