NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number MW-25676
George S. Roukis, Referee
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Peoria and Pekin Union Railway Company
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when it assigned weed mowing
work to outside forces on August 14, 15, 20, 25, September 7 and 9, 1982
(System File PPUT-3496/TC 57-82).
(2) The Carrier also violated Rule 40 when it did not give the
General Chairman advance written notice of its intention to contract said
work.
(3) As a consequence of the aforesaid violations, furloughed
Roadway Equipment Operator R. Meyers shall be allowed thirty-two (32) hours of
pay at the roadway equipment operator's rate."
OPINION OF BOARD; It is the Organization's position that Carrier violated
the controlling Agreement when outside forces were used to
mow grass and weeds along Carrier's right-of-way. Said work was performed on
August 14, 15, 20, 25, September 7 and 9, 1982. The Organization avers that
work of this character is reserved to the Maintenance of Way Structures
Department forces under the provisions of Rules 1, 39 and 51. In particular,
it asserts that Carrier failed to give the General Chairman advance written
notice of its plan to contract out this work as required by Rule 40 and such
failure was a material breach of a definitive obligation. It maintains that
until Carrier complies with the applicable rules, the employer is precluded
from initiating unilateral action. Moreover, it argues that consistent with
the December 11, 1981 National Agreement, signed by both the national
leadership of the Brotherhood of Maintenance of Way Employes and the National
Railway Labor Conference, Carrier was required to make a good faith effort to
procure the necessary equipment through rental or leasing arrangements. It
recognizes that Carrier used outside forces to perform this work for some
twelve (12) years, but notes that it was unaware of this practice. It avers
that the acquiescence of the Local Chairman or for that matter individual
employes to the Carrier's use of outside contractors does not change the
explicit Agreement rules.
Carrier contends that it is virtually unthinkable to believe that
the Local Chairman failed to note that this work was being performed on a
routine and predictable basis by outside forces. It asserts that since the
Scope Rule does not reserve this work to the Organization, it cannot follow
that an Agreement violation occurred. It argues that the Organization as the
Award Number 25930 Page 2
Docket Number MW-25676
moving party has the singular burden of proving a rule violation and
predicated upon the developed record, the Organization has not proven the
Scope Rule or any other rule was violated. It observes that a historical
perspective is needed to understand what in fact occurred and noted that
because of retrenchment decisions made in the early 1950'x, a program of
property disposal was implemented to generate operating and investment funds.
It avers that as a result of these actions the number of acres maintained
decreased and the operating condition of the mowing equipment deteriorated.
It argues that it was more economical to contract out for the reduced mowing
needs and consequently outside forces were used in full view of the Local
Chairman and his constituents for twelve (12) years.
In our review of this case, we concur with the Organization's
position. We are certainly mindful of the long term practice of using outside
forces to mow grass and weeds along Carrier's right-of-way, but this practice
does not negate nor vitiate clear contract language. The Classification of
Work Rule (Rule 39) and the implicit acknowledgment that none but Maintenance
of Way forces performed this work before circa 1970, establishes an Agreement
right to perform the work. The Organization is not barred from insisting on
compliance with the Agreement. (See Third Division Awards 19552, 14599,
22214.) We are indeed surprised by the Organization's nonchalant attitude
during the many years outside forces were used and somewhat perplexed by
Carrier's failure to comply with Rule 40, especially in 1970 when outside
contractors were first used. In the intervening years, there were no changes
in the rules cited in this dispute, and by extension, they were still
operative. In view of the Organization's apparent acquiescence to the use of
outside forces and Carrier's reliance upon this acceptance, it would be unfair
to hold Carrier liable for the compensatory portion of the claim. Both
parties must share responsibility for what had occurred. Accordingly, we find
that the Agreement was violated. The disputed work belongs to the
Organization.
FINDINGS: The Third Division of the Adjustment Board, upon the whole record
and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute are
respectively Carrier and Employes within the meaning of the Railway Labor Act,
as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over the
dispute involved herein; and
That the Agreement was violated.
Award Number 25930 Page 3
Docket Number MW-25676
A W A R D
Claim sustained in accordance with the Opinion.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
r
Attest:
' Nancy J. D er - Executive Secretary
Dated at Chicago, Illinois, this 26th day of February 1986.