NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number MW-25776
Herbert J. Marx, Jr., Referee
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(The Chesapeake and Ohio Railway Company (Southern Region)
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when, without a conference
having been held as required by the October 24, 1957 Letter of Agreement, it
assigned outside forces to perform ditching and grading work and to unload and
spread stone and/or gravel at Camp Morrison on the Peninsula Sub-division of
the Richmond Division (System File C-C-1556/MG-3901).
(2) Because of the aforesaid violation, cut-back Machine Operator J.
Coff shall be allowed two hundred eighty-eight (288) hours of pay at the
machine operator's rate and furloughed Trackman J. L. Silver shall be allowed
two hundred twenty-six (226) hours of pay at trackman's rate plus six cents
(6E) per hour differential."
OPINION OF BOARD: In this dispute, the Organization argues that the Carrier
violated the applicable Rules by assigning, without
conference with the Organization, certain work to outside forces. This work
involved ditching and roadbed work at Camp Morrison on the Peninsula Sub
division of the Richmond Division. This type of work is specifically covered
in Rule 66, Classification.
As to the restrictions on the Carrier in assignment of such work to
outside forces, the Organization cites Rules 83(b), which reads in pertinent
part as follows:
"(b) It is understood and agreed that
maintenance work coming under the provisions of
this agreement and which has heretofore customarily
been performed by employees of the railway company,
will not be let to contract if the railway company
has available the necessary employees to do the
work at the time the project is started, or can
secure the necessary employees for doing the work
by recalling cut-off employees holding seniority
under this agreement."
In addition, the Organization cites Appendix B, a letter from the
Carrier to the General Chairman dated October 24, 1957, which reads in
pertinent part as follows:
Award Number 25967 Page 2
Docket Number MW-25776
"As explained to you during our conference at
Huntington, W. Va., and as you are well aware, it
has been the policy of this company to perform all
maintenance of way work covered by the Maintenance
of Way Agreements with maintenance of way forces
except where special equipment was needed, special
skills were required, patented processes were used,
or when we did not have sufficient qualified forces
to perform the work. In each instance where it has
been necessary to deviate from this practice in
contracting such work, the Railway Company has
discussed the matter with you as General Chairman
before letting any such work to contract.
We expect to continue this practice in the
future . . . .
As to the work involved, the parties are in sharp dispute. The
Organization, throughout extensive on-property written correspondence, argued
that the Carrier had the necessary equipment and personnel to perform the work
and had utilized its own employees to do similar work in the past. The
Carrier argued that the "magnitude" of the work (involving extensive road
construction) precluded the use of its own forces and also that the equipment
employed by the outside contractor to perform the work expeditiously was not
available to the Carrier.
The Board need not resolve this factual conflict, however, since the
dispute turns, as the Board sees it, on the contractual ground as to whether
or not the Carrier was required to arrange for advance discussion with the
General Chairman, as provided in Appendix B.
In this particular connection, the Carrier raises a procedural
objection, based on which it urges the Board to dismiss the case. The Carrier
notes that in the original Claim letter, the Organization stated its argument
that "Labor Relations has not furnished this office with a letter showing the
intent of the Carrier to contract this work". The appeal to this Board,
however, states as follows:
"(1) The Carrier violated the Agreement when,
without a conference having been held as required
by the October 24, 1957 Letter of Agreement, it
assigned outside forces to perform . . . .
The Carrier contends that this is not the same Claim as argued on the
property. The Board does not agree. A review of the original Claim letter
leaves no doubt that the Organization's concern is with the performance of the
work itself by outside forces, as well as a notification failure. The
furnishing of a "letter" or some other form of communication is, as the
Organization notes, a necessary preliminary to the discussions specified in
Appendix B. The Claim is in valid form for processing to this Board.
Award Number 25967 Page 3
Docket Number MW-25776
Rule 83(b) states that work "customarily being performed by
employees" will not be contracted out if the Carrier has or can secure by
recall the necessary employees. The Carrier maintains and the Organization
denies, as suggested above, that this particular project does not fall within
the Scope of customary work. Appendix B, however, goes further and adds to
the exceptions under which work will not be assigned to Maintenance of Way
employees; namely, the need for special equipment or special skills, use of
patented processes, or in the absence of sufficient qualified forces. In
Appendix B, the Carrier undertakes to continue the practice of discussing the
matter in advance with the General Chairman "in each instance where it has
been necessary to deviate from this practice in contracting such work".
The Carrier argues that this must be read to mean it is required to
give advance notice only when work is to be contracted out for reason other
than the exceptions noted. The Board finds this too narrow a view.
Classification Rules and Rule B3(b) prohibit the contracting of work when
employees are available. In such circumstances, no "discussion" is called
for. Appendix B spells out other circumstances under which contracting may
be done (special equipment needs, etc.) but balances this with the undertaking
to discuss first.
In this particular circumstance, the difference between the parties
as to the work itself appears to center on its "magnitude" and not the unusual
nature of the work itself. Of relevance here is Award No. 24399 (Sickles)
involving the same parties and sustaining the Organization's position, which
states in part as follows:
"
OPINION OF
BOARD: The pertinent Agreement
reserves certain, work to the Employes and the
October 24, 1957 Letter of Agreement between the
parties specifies that the Carrier will perform all
' maintenance of work with classified employes except
where special equipment is needed. But it was
agreed that the Carrier would discuss any asserted
necessity to deviate from that practice prior to
contracting work out.
The Employes assert that no such conference
was held even though work which could have been
performed by the Employes was contracted to another
firm .
Here, as in the situation in Award
No.
24399, it appears the work
"could have been performed by the Employes". Whether it was practical to do
so, whether special equipment was needed, etc., would have formed the content
of the specified advance discussion with the General Chairmen. In the absence
of such discussion, the Board concludes that the Carrier is in violation of
its undertaking in Appendix B.
As to the appropriate remedy, the Board is not persuaded by the
Carrier's argument as to no lost work opportunity for the Claimants. This is
Award Number 25967 Page 4
Docket Number MW-25776
based on innumerable previous Awards on this subject. As to the amount of
time utilized by the contractor in use of a truck, which work is claimed by
one of the Claimants, the Carrier and the Organization are directed to consult
the work records to determine the appropriate amount of hours. Failing the
proffer of such records, the Claim must stand as presented.
FINDINGS: The Third Division of the Adjustment Board, upon the whole record
and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute are
respectively Carrier and Employes within the meaning of the Railway Labor Act,
as approved June 21, 1934;
That this Division of the Adjustment Board had jurisdiction over the
dispute involved herein; and
That the Agreement was violated.
A W A R D
Claim sustained in accordance with the Opinion.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest:
Nancy J. Dever - Executive Secretary
Dated at Chicago, Illinois, this 14th day of March 1986.