NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number MW-26030
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(St. Louis Southwestern Railway Company
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:
1. The Carrier violated the Agreement when it assigned outside
forces to perform grouting work at the Cimarron River Bridge between Liberal
and Bucklin, Kansas from November 17, 1982 through December 22, 1982 (System
File SSW-P-725).
2. As a consequence of the aforesaid violation, furloughed B&B
employes K. C. Sory, H. W. Hogue, G. D. Harrell, R. L. Olson and T. E. Rieson
shall each be allowed two hundred sixty-four (264) hours of pay at their
respective rates."
OPINION OF BOARD: By letter of October 12, 1982, the Carrier notified the
Organization in compliance with Article 33 of the Agreement
of its intent to utilize an outside contractor for bridge repairs. Carrier's
stated reasons included lack of employee expertise and lack of required equipment. A conference was
behalf of furloughed employees.
The instant dispute was initiated by the Organization on January 14,
1983, on behalf of five furloughed B S B employees in conjunction with the
events referred to above. In that letter, the organization pointed to the
fact that outside contractors had worked five (5) employes for thirty-three
(33) days in bridge repair work that came under the scope of the Agreement and
was therefore in violation of the December 11, 1981, Agreement (Article 33 of
the BMWE Agreement on property). Specifically, that Carrier had failed to
"assert good-faith efforts to reduce subcontacting by the procurement of
rental equipment and have Maintenance of Way Employes operate such". It was
asserted by the General Chairman that the contractor had rented the equipment
which the Carrier had made no attempt to secure. Even further, that the
equipment was the "standard air compressor, pneumatic drill and standard
concrete grout machine".
The Carrier on the property asserts that the B 6 B Department lacked
the expertise, that the work would have taken twice the time and in its letter
of September 1, 1983, further states that it lacked the equipment to perform
the work.
Award Number 26072
Docket Number MW-26030
Page 2
This Board has carefully studied the applicable Agreement and the
record that developed on property. The Carrier does not dispute the Agreement
provision which requires "good-faith efforts to reduce the incidence of subcontracting ...including
thereof by carrier employees". The Organization asserts that the Carrier
failed to put forth the effort to rent equipment. A search of the record
finds that the Carrier does not dispute the Organization's allegation. It
stands as fact that the Carrier put forth no effort to rent equipment which
was shown to be standard operating equipment. Even further, the Carrier
failed to rebut the organization's position that the Claimants were recently
hired Rock Island Railroad employees who had the necessary expertise, having
specialized in the work of using epoxy and high pressure grouting while
employed by the Rock Island. As such, the Organization's arguments clearly
prevail and this Board finds the Carrier in violation of the Agreement. This
is consistent with past Board Awards (See Third Division Award 25860).
Having found for the Organization, we now turn to the monetary
portion of the claim and direct the Carrier and Organization to consult the
work records to determine the exact and precise number of days and hours that
contractor's forces were utilized in violation of the Agreement. Such records
should be used to compensate herein named Claimants. Failing to proffer such
records, the Claim is sustained as presented.
FINDINGS: The Third Division of the Adjustment Board, upon the whole record
and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute are
respectively Carrier and Employes within the meaning of the Railway Labor Act
as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over the
dispute involved herein; and
That the Agreement was violated.
A W A R D
Claim sustained in accordance with the Opinion.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest:C~
Nancy J. Dever - Executive Secretary
Dated at Chicago, Illinois, this 8th day of July 1986.