NATIONAL RAILROAD ADJUSTMENT BOARD
(American Train Dispatchers Association
PARTIES TO DISPUTE:
(Missouri Pacific Railroad Company
STATEMENT OF CLAIM: As shown in Docket No. TD-26976 and not repeated
herein.
FINDINGS: The Third Division of the Adjustment Board finds:
That the dispute was certified to the Third Division of the
Adjustment Board ex parte by the complainant party; and
Under date of June 16, 1986 the complainant party addressed a formal
communication to the Executive Secretary of the Third Division requesting
withdrawal of this case from further consideration by the Division, which
request is hereby granted.
A W A R D
Claim dismissed.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest
Nancy J r - Executive Secretary
Dated at Chicago, Illinois this 8th day of July 1986.