NATIONAL RAILROAD ADJUSTMENT BOARD
Award Number 26182
THIRD DIVISION Docket Number MW-26300
Charlotte Gold, Referee
(Brotherhood of Maintenance of Way Dmployes
PARTIES 7U DISPUTE:
(Consolidated Rail Corporation
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:
1. The Carrier violated the Agreement when it assigned outside
forces to load bridge spans at the South Altoona, Pennsylvania Material Yard
between August 24 and September 2, 1983 (System Dockets CF-584 and CR-585).
2. The Carrier also violated the Agreement when it did not give the
General Chairman advance written notice of its intention to contract said work.
3. As a consequence of the aforesaid violations, Vehicle Operator R.
W. Wilson and Class I Machine Operator J. A. McMahon shall each be allowed
thirty-two (32) hours of pay at their respective straight time rates."
OPINION OF BOARD: Between August 24 and September 2, 1983, bridge spans were
loaded at the South Altoona Material Yard by an outside
Contractor using a thirty-ton Hydraulic Crane and trucks. The Organization
maintains that Carrier violated the Agreement by assigning this work to out
side forces and by failing to give the General Chairman advance written notice
of its intent to contract out. The Organization alleged that Claimants were
fully qualified and available to perform the work.
In support of its position, the Organization argues that the Scope
Rule refers to construction, maintenance, and repair of road beds as Maintenance of Way work. Rule 1
cranes, while vehicle operators will operate highway or rail-highway vehicles.
Further, the organization disputes Carrier's allegation that it supplied a
written Notice and claims that Carrier failed to inform the General Chairman
of its intent in writing fifteen days prior to the contracting transaction.
Carrier believes that the cork was performed in accordance with the March 16,
1977 Agreement concerning the use of Contractors and equipment, but the Organization insists that th
construction equipment, which it did not. Finally, in arguing that the South
Altoona Material Distribution Center is part of Altoona Shops and thereby
exempt fran the provisions of the Scope Rule, Carrier has failed to provide
any evidence to support that contention.
Award Number
26182
Page
2
Docket Number
MW-26300
In its Submission, Carrier argues that the work in question did not
accrue to BMWE represented employes by past practice, custom, tradition, or
Agreement provision and that therefore Carrier was under no contractual obligation to notify the BMW
states that "These rules shall be the agreement between the Consolidated Rail
Corporation (excluding Altoona Shops) and its employees of the classification
herein set forth represented by the Brotherhood of Maintenance of Way Employees . . . " It contends
Altoona Shops seniority district belongs to M of E Shop Craft employes. Carrier further maintains th
Claim, Claimants would not be entitled to compensation, since they were on
duty and under pay.
In reviewing this case, the Bard notes that in the course of discussions and correspondence on the p
loading bridge spans. A copy of that notice, which the organization maintains
it never received, was included in the record. This Bard has no basis for
disputing the validity of that document, despite the fact that the Organization was unable to locate
acknowledgment by Carrier that the loading work did accrue to employes represented by the BMWE.
At the same time, however, we find that the notice was dated August
22, 1983,
two days prior to the time that the subcontracting was to take
place. .The Scope Rule of the parties' Agreement states that:
"In the event the Company plans to contract out
work within the Scope of this Agreement, except in
emergencies, the Company shall notify the General
Chairman involved, in writing, as far in advance of
the date of the contracting transaction as is
practicable and in any event not less than fifteen
(15) days prior thereto. 'Emergencies' applies to
fires, floods, heavy snow and like circumstances."
No mention was made in the record of the existence of an emergency in
this situation that would cause Carrier to be unable to meet the time requirement for notification t
consequence, we must conclude that while Carrier did comply with Agreement in
providing notice to the Organization, it did not do so in a timely manner
(that is more than fifteen days prior to the intended subcontracting).
Carrier has pointed out that Claimants were on duty and under pay and
therefore not entitled to compensation. This Bard must agree. It is a well
accepted principle in the industry that compensation must be denied where all
affected employees are fully employed and suffer no loss. As we noted in
Third Division Award No. 26174, involving the Organization and a different
Award Number 26182 Page 3
Docket Number MA-26300
Carrier, however, there is merit "to the organization's contention that flagrant and continued d
notification should result in the sustaining of a monetary Claim. It is an
argument that warrants attention and we will continue to consider it in the
future."
FINDINGS: The Third Division of the Adjustment Hoard, upon the whole record
and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute are
respectively Carrier and Employes within the mea,iing of the Railway Labor Act
as approved June 21, 1934;
That this Division of the Adjustment Hoard has jurisdiction over the
dispute involved herein; and
That the Agreement was violated.
A W A R D
Claim sustained in accordance with the opinion.
NATIONAL RAILROAD ADJUSTMENT HOARD
By Order of Third Division
Attest:
Nancy J. Lever - Executive Secretary
Dated at Chicago, Illinois, this 24th day of November 1986.