NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number MW-26098
Edward L. Suntrup, Referee
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Consolidated Rail Corporation
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:
1. The disciplinary disqualification of Foreman C. W. Hull as Tie
Gang Foreman for alleged violation of 'Rule 3001A' was without just and sufficient cause and on the
MW-3-27).
2. The charge leveled against Mr. C.
w.
Hull shall be removed fran
his record and he shall be listed as qualified for the position of Tie Gang
Foreman."
OPINION OF BOARD: The Claimant was charged with violation of Safety Rule
3001A. He was specifically charged with responsibility for
the derailment and damage to 1 Plateboy and the derailment of 3 Push trucks on
March 16, 1983 at approximately 3:50 P.M. at
JW
Switch, Conemaugh, Pennsylvania. At the time the Claimant held the position of Tie Gang Foreman. Aft
Hearing was held on April 4, 1983, the Claimant was advised that he had been
found guilty as charged and he was disqualified as Tie Gang Foreman.
The record shows that the Claimant and an Acting Foreman were assigned to a Tie Gang working in the
According to testimony at the Hearing the Claimant was Senior or Lead Foreman.
The Racine Plateboy and 3 Push trucks derailed at the point cited above when
they were being moved because clamps on the plateboy hit the heel block at the
switch. This was caused by the loss of a safety pin in the plateboy. The
Assistant Production Foreman to wham the Tie Gang was assigned on March 16,
1983 stated the following at the Hearing with respect to the responsibilities
of the Lead Foreman:
"It is the sole responsibility of the lead foreman
to see that all machinery is safe. No machine
leaves a work site unless it is inspected. It has
always been the procedure in the tie gang or the
raising gang . . . it is the lead foreman's job to
make sure - - - whether he does it or assigns somebody else to do it - - - to inspect the machinery
before movement is made. When we move the lead
foreman takes his back-up foreman and they work
both sides of the machine from front to hack to
make sure everything is secure for movement . . .
that is standard procedure before moving equipment."
Award Number 26192 Page 2
Docket Number MW-26098
It appears from testimony by the Claimant at the Hearing, that he did
not have a proper understanding of his responsibilities relative to the safe
operation of the equipment used by the Tie Gang. He testified that he thought
". . . the operators (were) responsible . . . to check to see if the equipment
(was) safe to move." This apparently was why he did not assign either the
Repairman or the Second Foreman in charge to have the equipment checked. Part
of this confusion with respect to his responsibilities may have been because
the Claimant had just started on the position of Foreman on the day the accident occurred. It was fu
understanding that he was in charge of only the "front end of the tie gang"
which included some 7 pieces of equipment, but not the Racine Plateboy. He
also testified that although he had held the Foreman position at various times
in the past he had no familiarity specifically with the Racine Plateboy. Further, the Claimant had n
those under his charge to ascertain if all were qualified to operate the various pieces of equipment
operate the Plateboy was not qualified to do so.
A complete review of the record shows, therefore, that although the
Claimant stated in Hearing that he was familiar with Rule 3001A he did not,
apparently, fully realize that he was personally responsible, as Lead Foreman,
for the safety of all of the equipment under his charge on March 16, 1983.
The Claimant must bear responsibility for the derailment and damage to the
Plateboy and the Push trucks on that date because safety Rule 3001A clearly
states:
"Immediate supervisor shall be responsible for the
safety instruction and safe performance of all men
under his jurisdiction including employees from
another department or gang."
On the other hand, the Claimant's negligence must be put in the context of
sane extenuating circumstances which were present when the derailment took
place. This includes his lack of familiarity with the specific equipment in
question, which would no doubt have been rectified as the Claimant gained tenure in the Foreman's po
testified at the Hearing, which was not disputed, that he had not received
specific instructions with respect to his Foreman's duties on this gang from
any of the Production Supervisors prior to assuming these duties on March 16,
1983. The Carrier's officers must, therefore, also assume sane of the blame
for the Claimant's failure to have carried out all of his duties according to
"standard procedure."
On the record as a whole, therefore, it is the decision of the Hoard
that the Claimant has already sufficiently paid the price for his negligence
on March 16, 1983. The Claimant shall, therefore, be returned to the list of
employees qualified for the position of Tie Gang Foreman.
Award Number 26192 Page 3
Docket Number MW-26098
FINDINGS: The Third Division of the Adjustment Board, upon the whole record
and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute are
respectively Carrier and Employes within the meaning of the Railway Labor Act
as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over the
dispute involved herein; and
That the discipline was excessive.
A W A R D
Claim sustained in accordance with the opinion.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest: e~
ancy J. r - Executive Secretary
Dated at Chicago, Illinois, this 24th day of November 1986.