NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number MW-26283
Herbert L. Marx, Jr. Referee
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Seaboard System Railroad
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when, without an understanding
having been reached between the Carrier and the General Chairman setting forth
the conditions under which the work will be performed as required by Rule 2,
it assigned the work of constructing an agency office building at Pecan, Florida to outside forces b
Div.-15/12-2(83-77) H21.
(2) Because of the violation referred to above, each employe holding
seniority rights on the Jacksonville and Tampa Divisions Seniority District in
B&B Groups, A, G and H in the Water Service Fuel and Air Conditioning Subdepartment and in the M
rates for an equal proportionate share of the total number of man-hours expended by outside forces i
hereof."
OPINION
OF BOARD: By letter of March 27, 1982, the Carrier notified the
General Chairmen as follows:
"At Pecan, Florida, approximately three miles north
of Palatka, we propose to construct an aaency office
building of approximately 2,200 square feet.
The building will be constructed under a permit issued by Putnam County requiring a licensed con
and usual inspections. The building will be one story
with exterior walls and roof of steel, interior will be
finished with steel studs and sheetrock partitions, concrete floors with vinyl asbestos floor tile,
the toilet, where walls and floor will be ceramic tile.
Site work will involve clearing, grading, utilities, sewage disposal, walks, curbs and asphalt pavin
In addition, a deep well will be required with possible
addition of aeration equipment.
Award Number 26220 Page 2
Locket Number MW-26283
Tb meet the County's requirements, we propose to contract the entire project, as our forces are not
nor licensed to perform certain of the work. Your early
concurrence is requested in order that the construction
may be scheduled."
This letter is typical of such correspondence over the years in which
the
Organization is
advised of construction work proposed to be contracted to
outside forces. Such correspondence is clearly and directly related to the
provisions of Rule 2, CONTRACTING, Section 1, which reads as follows:
"This Agreement requires that all maintenance work in
the
Maintenance of
Way and Structures Department is to be
performed by employees subject to this Agreement except
it is recognized that, in specific instances, certain
work that is to be performed requires special skills not
possessed by the employees and the use of special equipment not owned by or available to the Carrier
instances, the Assistant Vice-President, Engineering and
Maintenance of Way, and the General Chairman will confer
and reach an understanding setting forth the conditions
under which the work will be performed.
It is further understood and agreed that although it
is not the intention of the Company to contract construction work in the Maintenance of Way and Stru
available, it is recognized that, under certain circumstances, contracting of such work may be neces
such instances, the Assistant Vice-President, Engineering and Maintenance of Way, and the General Ch
confer and reach an understanding setting forth the conditions under which the work will be performe
instances, consideration will be given by the Assistant
Vice-President, Engineering and Maintenance of Way, and
the General Chairman to performing by contract the grading, drainage and certain other Structures De
work of magnitude or requiring special skills not possessed by the employees, and the use of special
with Company forces."
Pursuant to that portion of Rule 2, Section 1, second paragraph as to
the requirement to "confer", Representatives of the Carrier and organization
met on April 6, 1982, and on several other dates in the ensuing months. No
"understanding" as to the project was reached, and on September 30, 1982, the
Carrier advised the organization in pertinent part as follows:
Award Number 26220 Page 3
Docket Number MW-26283
"We regret that we have been unable to reach a mutual
understanding with you in this instance. In order for
this company to fully and effectively meet its obligations to the shipping public, we believe that t
agency facility should be built without further delay.
Accordingly, it is necessary to proceed with contracting
this project. We hope you will reconsider your position
and concur in our action."
Subsequently the Claim here under review was filed as to whether "the
subject work met the circumstances set forth in Rule 2", and further alleging
that construction of the building "is construction work . . reserved exclusively" to employees in th
There is no question that, in this instance and unlike many previous
instances, the parties did not "reach an understanding setting forth the con
ditions under which the work will be performed." Thus, it is the organiza
tion's principal position that the Carrier has failed to comply with Rule 2,
and the construction work was in consequence improperly contracted to an out
side contractor. In response, the Carrier argues that it fully met the re
quirement to "confer" on the project and that the Rule does not give the or
ganization "veto power" to prevent such contracting simply by failing to
"reach an understanding."
The Hoard was not made aware by the parties of any previous Awards
providing resolution of this precise point. In support of its position, the
organization cites sustaining Third Division Award No. 18287, interpreting the
same Rule. In that Award, however, the facts disclosed that there was no
conference, a necessary preliminary to reaching an understanding. Third
sivioAwards Nos. 13349, 14982 and 16693 are to similar effect.
In support of its view, the Carrier cites a number of Awards (Second
Division Award No. 10964 is an example) involving interpretation of language
such as, "The time and length of the lunch period shall be subject to mutual
agreement with the committee." Where no such Agreement was reached in these
instances, the Awards uniformly permitted the Carriers therein to adjust lunch
periods to changing work conditions. The Hoard finds, however, that this
language, while similar, is clearly not identical to the "confer and reach an
understanding" of Rule 2.
To answer the question posed here, the language in question must be
viewed within the entire context of Rule 2, Section 1. The first paragraph
states that all maintenance work will be performed by employees subject to the
Agreement - with certain specified exceptions. The second paragraph proceeds
fran a different starting point, establishing as to construction work that it
"may be necessary" to contract such work. The paragraph gives guidance as to
when such is "necessary:" the intent not to contract construction work where
Award Number 26220 Page 4
Docket Number MW-26283
"forces and equipment are adequate and available;" the recognition of limitation of doing so, based
and special equipment.
All these factors are clearly intended to be considered in conference
and "understanding" between the parties. The Board does not read the second
sentence of paragraph two simply to mean that the Organization may grant or
withhold its approval of contracting construction work. If this were true, an
organization could effectively prevent any contracting of construction work.
On the other hand, a good faith effort is required of the Carrier; failure to
confer is a Rule violation (see Third Division Award No. 18287 and related
awards). In this instance, the Board perceives that the parties failed to
agree as to whether the work should be contracted or performed by Carrier
employees or a combination of both. The requirement of Rule 2 is not that
strong, however. Is "reach an understanding setting forth the conditions
under which the work will be performed" the same as requiring organization
approval or consent to any contracting of construction work? The Board finds
that it is not, relying on the preceding phrase, which states "under certain
circumstances, contracting, of such work may be necessary."
Thus, the Claim is not sustainable solely on the basis that conferences failed to result in the Orga
This does not mean, however, that the Carrier is free to contract
construction work under any and all circumstances (assuming it has conferred
and sought understanding with the organization). The Rule says it is not the
intent of the Carrier to contract construction work when forces are "adequate
and available" -- except under "certain circumstances." were such "certain
circumstances" present in this instance? It is the Board's conclusion that
they were and that Rule 2 was not violated when the Carrier contracted the construction of the agenc
The "circumstances" include the Carrier's contention, expressed to
the Organization in conference and correspondence, that building construction
for public use of this type requires "certified and licensed tradesmen" under
county regulations. The Carrier argues that its forces do not meet this requirement. The organizatio
the Board is not in a position to dispute this interpretation of local law.
Aside from this, the Carrier claims, in correspondence to the Organization, that its forces lack cer
forces and necessary outside forces. (See Third Division Award No. 20785,
citing numerous other awards.)
Award Number 26220 Page 5
Docket Number MW-26283
There is the further Carrier contention that the time requirements
for construction and use of the new building did not permit it to divert its
already fully occupied forces to undertake the project, even conceding that
much of the work was within the employees' capability.
Rule 2, Section 1, second paragraph places meaningful restrictions on
the Carrier. These include a stated intention not to contract construction
work except under "certain circumstances." There is the basic binding requirement to confer with the
the latter can obviously not be achieved on a unilateral basis. Further,
guidelines are provided in the final sentence as to what factors may provide
for exceptions. Only in the context of all this does the Board find that the
Carrier did not violate Rule 2. Thus, the resolution of this dispute rests on
the particular circumstances reviewed herein and is not of general application.
FINDINGS: The Third Division of the Adjustment Board, upon the whole record
and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute are
respectively Carrier and Employes within the meaning of the Railway Labor Act,
as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over the
dispute involved herein; and
That the Agreement was not violated.
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attes .
Nancy J.~i5~6er - Executive cretary
Dated at Chicago, ~I/llinois this 15th day of January 1987.