NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number MW-26097
Edward L. Suntrup, Referee
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Southern Pacific Transportation Company
(Western Lines)
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when it assigned End
Loader-Backhoe Operator T. J. Miller instead of Water Service Mechanic T.
L. Walsh to perform Water Service Mechanic's work from August 11, 1982 through
September 17, 1982, for a total of seventy-six (76) man-hours (Carrier's File
MofW 152-960).
(2) Claimant T. J. Walsh shall be paid at the Water Service
Mechanic's rate for seventy-two (72) hours at the pro-rata rate and four (4)
hours at the time and one-half (1 1/2) rate."
OPINION OF BOARD: The Organization submitted a Claim to the Carrier on
October 2, 1982, on behalf of the Claimant for seventy (72)
hours at straight-time pay and four (4) hours at overtime rate. The contention of the Claim is that
the Carrier's Oregon Division, should have worked the hours in question from
August 11, 1982 through September 17, 1982, in lieu of a fellow employee, Mr.
T. J. Miller, who had less seniority. Although the Claimant cites various
Rules from the operant Agreement which the Carrier allegedly violated on the
dates in question the Rule provision which the Claimant specifically references is the following, in
"Rule 13(a) - When force is reduced, the
senior employee in the class or
classes affected in the gang, or
in case of employees not assigned
to gangs, having headquarters at the
location where reduction is to he
made, shall be retained."
In its denial of the Claim the Carrier states that the Claimant was a Water
Service Mechanic whereas Mr. Miller was an End Loader-Backhoe Operator and as
such was needed on the days in question in that capacity. The Carrier officer
states, in its correspondence to the District Chairman of the Organization on
November 30, 1982, that since "...there were no senior qualified end loaderbackhoe operators among t
Award Number 26257 Page 2
Docket Number MW-26097
in question), (Mr. Miller) remained on his assigned position." The Board can
find no evidence in the record to the effect that the Claimant was a qualified
End Loader-Backhoe Operator. Further, in his original correspondence to the
Organization which is dated September 10, 1982, and which was the information
supplied by the Claimant to the Organization which became basis for the Claim
filed on October 2, 1982, the Claimant included a plain sheet of paper on
which he listed each workday from August 11, 1982 through September 17, 1982,
and the specific work allegedly performed by Mr. Miller on each of these days.
Although it is unclear from the record exactly how the Claimant obtained this
information since he was on furlough on the days in question, the information
states that Mr. Miller did work the Backhoe on some of the days for which pay
is claimed but that on other days he performed yard work or did something
other than operate a Backhoe. The General Chairman of the Organization was
advised by the Carrier, however, in correspondence dated June 30, 1983 that:
"J. T. Miller, incumbent of end loader-backhoe
operator (position), B&B Gang No. 35, Eugene,
performed service on that position on the dates
of claim as indicated by a joint check of our
records.
In regard to the copy of the work schedule
provided by the Claimant (which is the one
referenced by this Board above) alleging that
this schedule represented end loader-backhoe
operator T. J. Miller's work schedule on the
dates involved, you were advised that the company
rejects his alleged work schedule as self-serving
evidence which is not substantiated by a review
of our records during our conference which
records indicate that T. J. Miller as performing
service on his regular assigned position each
day." (Emphasis added.)
As moving party in the instant dispute the burden of proof lies with the
Organization to provide substantial evidence that the Claim be sustained
(Second Division Awards 5526, 6954; Fourth Division Awards 3379, 3482).
Assertions by the Organization are no substitute for proof according to
substantial evidence criteria (Third Division Award 25575). Substantial
evidence has been defined as such "relevant evidence as a reasonable mind
might accept as adequate to support a conclusion" (Consol. Ed. Co. vs Labor
Board 305 U.S. 197, 229). A search of the record fails to produce evidence by
the Organization that Mr. Miller did, in fact, do other than cover the
assignment for which he and not the Claimant was qualified. On merits, the
instant Claim cannot he sustained.
The Board observes that there is considerable information contained
in the Submissions which was not part of the exchange on the property. The
Board has ruled that materials and arguments used in Submissions to the Board
which have not been exchanged by the parties on the property are untimely and
inadmissible (Third Division Awards 21463, 22054, 25575; Fourth Division
Awards 4112, 4136, 4137).
Award Number 26257 Page 3
Docket Number MW-26097
FINDINGS: The Third Division of the Adjustment Board, upon the whole record
and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute are
respectively Carrier and Employes within the meaning of the Railway Labor Act
as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over the
dispute involved herein; and
That the Agreement was not violated.
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest:
_ P~-
Ile
Nancy ever - Executive Secretary
Dated at Chicago, Illinois, this 2nth day of March 1987.