NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number MW-26166
Martin F. Scheinman,
Referee
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE: (
(Southern Pacific Transportation Company
(Eastern Lines)
STATEMENT OF CLAIM: "Claim of the System
Committee of
the Brotherhood that:
(1) The Carrier violated the
Agreement when
it assigned Car Department forces instead of Roadway Track
Department forces
to perform track work
at Lufkin, Texas on April 13, 1983 (System File MW-83-66/391-91-A).
(2)
Because of
the aforesaid violation, furloughed Track Laborers
E. J.
Baggett, T
. Zackery and R. D. Eaglin shall each be allowed four (4)
hours of pay at their straight time rate."
OPINION OF BOARD: As Third Party in
interest, the
Brotherhood Railway Carmen
of the United States and Canada was advised of the
pendency
of this case, but chose not to file a Submission with the Division.
During the
week of
April 4, 1983, a number of cars derailed on
Carrier's Houston Division at Lufkin, Texas.
Three Carmen
performed certain
work necessary to rerail the cars. According to the Organization, such work
involved repair to the rails which should have been done by its
members.
As a result, the Organization filed this Claim. Carrier
rejected
it. Upon the parties' failure to
resolve the
dispute on the property, the
matter was advanced to this Board for adjudication.
The Organization contends that Carmen
repaired the
track at the
derailment site. In support of this position, it cites a
letter by
a Carman
in which he states, "We
...
did perform said Maintenance of Way work." Thus,
the Organization insists that the disputed work does belong to
members of
its
craft. Accordingly, it asks that the Claim be sustained and that each Claimant be
compensated four
hours' pay at the straight time rate.
Carrier,
however, argues
that the disputed work involved simply the
rerailing of cars which does not belong to the Organization pursuant to the
Scope Rule.
Therefore, it
asks that the Claim be rejected.
A
review of
the record evidence convinces
us that the Claim must
fail. The
letter cited
by the Organization reveals only that the Carman performed duties he considered Maintenance of W
did what was necessary to rerail the cars. In so doing, they worked with the
rails, not to repair them, but
to
permit the cars
to
be placed back on them.
Award Number 26459 Page 2
Docket Number MW-26166
Clearly, such work does not constitute repair of rails as suggested
by the Organization. In this context, it is significant that the tracks were
subsequently torn out and repaired by Maintenance of Way Employe.
Under these circumstances, we are convinced that work done to the
rails by Carmen did not constitute repair work so as to fall under the
Organization's Scope Rule. Accordingly, and for these reasons, the Claim must
be denied.
FINDINGS: The Third Division of the Adjustment Board, after giving the
parties to this dispute due notice of hearing thereon, and upon the
whole record and all the evidence, finds and holds:
That the Carrier and the Employes involved in this dispute are
respectively Carrier and Employes within the meaning of the Railway Labor Act,
as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over the
dispute involved herein; and
That the Agreement was not violated.
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest i
Nancy ,Y.go_ver - Executive Secretary
Dated at Chicago, Illinois, this 24th day of August 1987.