NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number MW-26299
Rodney E. Dennis, Referee
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Consolidated Rail Corporation
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:
(1) The Agreement was violated when outside forces were used to
construct a fence at Mt. Pleasant, Delaware on August 25, 26 and September 1
and 2, 1983 (System Dockets CR-603, 604, 605 and 606).
(2) The Agreement was further violated when the Carrier did not
give the General Chairman prior written notification of its plan to assign
said work to outside forces.
(3) Because of the aforesaid violations, B&B Foreman B. J. Maylie
and B&B Mechanics D. C. Stanton, F. F. Guzzetti and W. A. Stanowski shall each
be allowed thirty-two (32) hours of pay at their respective straight time
rates."
OPINION OF BOARD: This Board has reviewed the facts of this case and concludes
that since all Claimants were under pay during the perioa
of the Claim, a monetary Award in this instance will be denied. We also take
note that the site involved in the fencing job was property that was leased by
Carrier to another company.
FINDINGS: The Third Division of the Adjustment Board, upon the whole record
and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute are
respectively Carrier and Employes within the meaning of the Railway Labor Act
as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over the
dispute involved herein; and
That the Agreement was not violated.
Award Number 26481 Page 2
Docket Number MW-26299
A W A
R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest:
'Nancy J.
D
v - Executive Secretary
Dated at Chicago, Illinois, this 9th day of September 1987.