NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket .Number MW-26722
Edward L. Suntrup, Referee
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(National Railroad Passenger Corporation
(Amtrak) - Northeast Corridor
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when, beginning March 5,
1984, it scheduled Mr. A. N. Plant to work ten (10) hours per day, four (4)
days per week without allowing him three (3) consecutive rest days in each
work week (System File NEC-BMWE-SD-941).
(2) As a consequence of the aforesaid violation, Mr. A. N. Plant
shall be allowed ten (10) hours of pay at his respective time and one-half
rate for each rest day lost beginning March 10, 1984 and continuing until the
violation is corrected."
OPINION OF BOARD: On March 25, 1984, a Claim was filed with the Carrier on
the grounds that it was in violation of the AMTRAK-BMWE
Agreement and the Special Construction Gangs Agreement of November 3, 1976,
when it failed to pay the Claimant at overtime rate on various rest days which
he was required to work in March of 1984 and thereafter.
The Rules at bar are the following:
"Rule 40
BEGINNING OF THE WORK WEEK
The term 'work week' for regularly assigned
employes shall mean a week beginning on the
first day on which the assignment is bulletined
to work, and for unassigned employes shall mean
a period of seven consecutive days, starting
with Monday."
"Rule 45
TIME WORKED IN EXCESS OF 40 STRAIGHT TIME HOURS
IN ANY WORK WEEK
Time worked in excess of 40 straight time
hours in any work week, shall be paid at time
and one-half rates, except where such work is
Award Number 26522 Page 3
Docket Number MW-26722
Claim is for time and one-half for March 10, 11 and 23, 1984, and any days
thereafter for which the Claimant was paid pro rata for being required to work
on rest days. After the Claim was filed the Carrier determined, by correspondence dated July 19, 198
a mistake when it paid the Claimant time and one-half on March 10, 1984. The
Carrier stated that it was taking measures to recoup such overpayment.
The record shows that the Carrier is inconsistent, when it handled
this case on property, relative to its understanding of when the new work week
to which the Claimant was assigned, actually began. The Senior Director-Track
informed the Organization by correspondence dated May 24, 1984, that the
change of schedule became effective "...March 10, 1984." The Assistant Chief
Engineer, on the other hand, states that the new work week was to begin on
...March 5, 1984." Despite this anomaly in the record before the Board the
record does show that the Claimant was not given three rest days after his
March 5-8, 1984 work week, and that he was not given three rest days after his
March 17-20, 1984 work week. He was worked on March 10, March 11 and March
23, 1984, and was paid pro rata for those days (if, in fact, his March 10,
1984, overtime rate was rescinded). The Carrier was in error when it paid the
Claimant pro rata on those dates. The reason for this has been clearly outlined by the Board in Thir
used there applies here by reference.
Since the Agreements were violated, the Claimant shall be paid the
difference between the overtime and pro rata rates for March 10-11, and 23,
1984, if, in fact, his overtime rate had been reduced to pro rata for March
10, 1984. The parties are directed to do a joint check of the Carrier's
records after these dates. If there are additional work weeks when the
Claimant worked four, ten hour days followed by any three rest days on which
he was obligated to work, and if he was not paid the overtime rate on these
rest days, the Claimant shall be compensated accordingly at the difference
between the overtime and pro rata rates.
FINDINGS: The Third Division of the Adjustment Board, upon the whole record
and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute are
respectively Carrier and Employes within the meaning of the Railway Labor Act
as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over the
dispute involved herein; and
That the Agreement was violated.
Award Number 26522 Page 4
Docket Number MW-26722
A W A R D
Claim sustained in accordance with the Opinion.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest:
fancy J.
9
v - Executive Secretary
Dated at Chicago, Illinois, this 9th day of September 1987.
CARRIER MEMBERS' DISSENT
TO
AWARDS 26518, 26519, 26522 & 26523
DOCKET NOS. MW-26667, MW-26672, MW-26722 & MW-26724
Referee Suntrup,
In sustaining these claims, the Majority failed to accord sufficient
weight to the fact that the November 3, 1976 Speciai Construction Gangs
Agreement was specifically neg~:iated to grant the Carrier flexibility in
changing workweeks to meet the unique operationa' requirements of its
mechanized gangs and, in consideration for sucn flexibility, an incentive
rate of 25~ per hour over and above the rate provided for the classification
was granted.
We dissent.
M. C. Lesnik
7W
A
d,4
M. W.vFingerhut
&& a - ;,? -
J
R. L. Hicks
. V. Varga
. 4-E . Yost
V