NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number MW-26724
Edward L. Suntrup, Referee
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(National Railroad Passenger Corporation
(Amtrak) - Northeast Corridor
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood
that:
(1) The Carrier violated the Agreement when, beginning March 12,
1984, it scheduled P.R.S. Unit employes A. Cunha, E. Dickson and C. McIntosh
to work ten (10) hours per day, four (4) days per week without allowing them
three (3) consecutive rest days in each work week (System File NEC-BMWESD-937).
(2) As a consequence of the aforesaid violation, Messrs. Cunha, Dickson and McIntosh shall be co
'the 17th and 18th of March should have been rest
days; therefore, the claimants should be compensated at time and a half for both of these days.
In addition, the claimants were only provided then
with a 20 hour work week, rather than a forty hour
work week; therefore, the claimants and the Organization are requesting an additional 20 hours at th
straight time rate for each of the above-mentioned
claimants.'"
OPINION OF BOARD: On April 2, 1984, the Vice Chairperson of the Organization
filed a Claim with the Carrier on the grounds that it was
in violation of the AMTRAK-BMWE Agreement and the Special Construction Gangs
Agreement of November 3, 1976 when it failed to pay the Claimants at the
overtime rate on various days in March of 1984.
The original Claim filed on April 2, 1984 errs in its calculation of
relief requested under the Agreements at bar. This is later corrected. The
calculation error in the original Claim does not nullify, in the mind of the
Board, the validity of the Claim. See Third Division Awards 20841 and 25061
for resolution of comparable issues.
The Rules at bar are the following:
"Rule 40. BEGINNING OF THE WORK WEEK
The term 'work week' for regularly assigned employes-shall mean a week beginning on the first da
on which the assignment is bulletined to work, and
for unassigned employes shall mean a period of seven
consecutive days, starting with Monday."
Award Number 26523 Page 2
Docket Number MW-26724
"Rule 45. TIME WORKED IN EXCESS OF 40 STRAIGHT TIME
HOURS OF ANY WORK WEEK
Time worked in excess of 40 straight time hours
in any work week, shall be paid at time and one-half
rates, except where such work is performed by an employe due to moving from one assignment to anothe
or where days off are being accumulated in accordance
with the provisions of Rule 39."
RULE 90-A
TRACK UNITS - SOUTHERN DISTRICT
V. WORK WEEK.
The normal work week for employes assigned to
positions in units established pursuant to this
Agreement, will consist of five (5) days of eight
(8) straight time hours each, with two (2) consecutive rest days. An original determination of
whether a unit is to be established for five (5)
or four (4) ten (10) hour work days with three (3)
consecutive rest days shall be made in the notice
given to the General Chairman pursuant to II above.
When it is known in advance that a five (5) day week
will not be practicable and feasible for the duration
of the unit, those times will be specified in such notice. At all other times, the Chief Engineer ma
change the work week from five (5) days to four (4)
days, or vice versa, upon at least five (5) days written notice to the involved employes and the Gen
Chairman, except that such changes may be made in less
than five (5) days upon concurrence of the General
Chairman.
"SPECIAL CONSTRUCTION GANGS AGREEMENT (November
3, 1976) Paragraph 1(d)
"A work week consisting of four ten-hour work
days may be established with any three consecutive days as rest days."
The Claimants were members of the Panel Renewal System which is a District Unit subject to the p
the Special Construction Gangs Agreement of November 3, 1976. The Claim stems
from a memo distributed to the Claimants on February 29, 1984, advising them
of a change in work schedule and of notification of same by the Equipment
Engineer on March 8, 1984. Upon denying the Claim the Assistant Chief Engineer, in correspondence to
following:
Award Number 26523 Page 3
Docket Number MW-26724
"Upon reviewing the aforementioned claim we can
find no basis on which to honor the request for
compensation here, in that the Claimants' tour of
duty was changed in accordance with the applicable
rules of the Agreement and they were properly
compensated for all time worked."
As a result of a change in the work schedule the record shows that the Claimants worked on the f
pro rata rate. March 16, 1984, was a rest day. March 17, 1984 was a work day
on which they were paid overtime. On March 18, 1984 they were paid the pro
rata rate.
This enumeration of the facts of this case must include the qualifier
that two of the Claimants were absent on two days during this time frame as a
result of voluntary absences. This will ultimately affect their relief requested in the instant Clai
be determined from the record, particularly Carrier's June 1, 1984 letter in
combination with the Organization's submission, Claimant Dickson was paid the
proper amount of compensation on the combined dates of March 17-18, 1984, when
he was called to work on his normal rest days but his pro rata and overtime
rates were paid in reverse chronological order. If this Claimant was not paid
at the pro rata rate on March 17, 1984, and at the overtime rate on March 18,
1984, he should have been since he had not completed a forty-hour work week
until the end of the shift on March 17, 1984. Nothing in the Carrier's onproperty correspondence rel
rebuttal to this Board refutes such conclusion.
According to the applicable Agreements the Board notes that March 18,
1984 was a scheduled rest day. If the Claimants were not given that day off
they should have been paid at the overtime rate, under normal conditions, if
called in on assignment, and if they had actually worked that day. The Board
has already ruled on a number of cases between these same parties wherein the
contract provisions are the same but the details of each Claim are different
(See Third Division Awards 26519 and 26522). The reasoning by the Board in
those cases, outlined in detail in Third Division Award 26518, applies here by
reference. The Organization has sufficiently met its burden of proof and the
Claim is sustained on merits.
Claimant A. Cunha shall be paid the difference between the pro rata
and overtime rate for the work he did on March 18, 1984. This amounts to five
hours pro rata. Neither Claimants E. Dickson nor C. McIntosh are entitled to
relief by this Award. Mr. Dickson had not worked a 40-hour week the prior
week since he, was absent from his assignment on March 13, 1984; Mr. McIntosh
did not work on March 18, 1984.
FINDINGS: The Third Division of the Adjustment Board, upon the whole record
and all the evidence, finds and holds:
That thp- parties waived oral hearing;
Award Number 26523 Page 4
Docket Number :".W-26724
That the Carrier and the Employes involved in this dispute are
respectively Carrier and Employes within the meaning of the Railway Labor Act,
as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over the
dispute involved herein; and
That the Agreement was violated.
A W A R D
Claim sustained in accordance with the Opinion.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest:
Nancy J. ev - Executive Secretary
Dated at Chicago, Illinois this 9th day of September 1987.
CARRIER MEMBERS' DISSENT
TO
AWARDS 26518, 26519, 26522 & 26523
DOCKET NOS. MW-26667, MW-26672, M!W-26722 & MW-26724
Referee Suntrup,
In sustaining these claims, the Majority failed to accord sufficient
weight to the fact that the November 3, 1976 Special Construction Gangs
Agreement was specifically nego-.iated to grant the Carrier flexibility in
changing workweeks to meet the unique operationa' requirements of its
mechanized gangs and, in consideration for sucn flexibility, an incentive
rate of 25~ per hour over and above the rate provided for the classification
was granted.
We dissent.
M. C. M. C. Lesnik
M. W. in erhul
R. L. Hicks
.f~ U U ~
F.
V. Varga
. E. Yost CJ