NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number MW-26927
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(The Denver and Rio Grande Western Railroad Company
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood
that:
(1) The dismissal of Work Equipment Operator D. R. Lawyer and the
discipline (sixty demerits) imposed upon Track Liner Operator E. G. Chavez for
alleged responsibility in connection with '...collision between Ballast Equalizer BE-3, Track Liner
...
personal injury to E. G.
Chavez on October 30, 1984
....'
was arbitrary, capricious, without just and
sufficient cause and in violation of the Agreement (System Files D-64-84/MW4-85 and D-65-84/MW-5-85)
(2) Claimant D. R. Lawyer shall be reinstated with all seniority and
rights unimpaired and he shall be compensated for all wage loss suffered in
accordance with Rule 28.
(3) Claimant E. G. Chavez' record shall be cleared of the charge
leveled against him and the sixty (60) demerits imposed upon him shall be removed from his record in
OPINION OF BOARD: At the time of the incident, Claimant Lawyer was an Equip
ment Operator and was in the Carrier's service since May 5,
1981. Claimant Chavez was a Track Liner Operator/Extra Gang Laborer and was
in the Carrier's service since May 19, 1981. Both were assigned to section
forces headquarters at Pinecliff, Colorado. As a result of a collision on
October 30, 1984, charges dated November 1, 1984, Investigation held November
6, 1984, and letters dated November 12, 1984, Claimant Lawyer was dismissed
from service and Claimant Chavez was assessed 60 demerits for their responsibi
lity in connection with that collision.
The record discloses that on October 30, 1984, Claimant Lawyer, while
operating a ballast equalizer, followed Claimant Chavez into a 1000 foot tunnel (Tunnel 16). At the
towing buggies. While in the tunnel, the ballast equalizer collided with the
moving track liner. A motor car operated by Track Patrolman S. P. Schoening
then collided with the ballast equalizer. The collision destroyed the buggies, damaged the track lin
Chavez.
With respect to Claimant Lawyer, we are satisfied that substantial
evidence exists in the record to support the Carrier's determination to impose
Award Number 26532 Page 2
Docket Number MW-26927
discipline. Under the circumstances, and considering the conditions that
existed, we cannot find fault with the Carrier's determination that Claimant
Lawyer should have operated the ballast equalizer at a reduced speed in the
tunnel so as to permit adequate distance for stopping. Claimant Lawyer knew
that Claimant Chavez was ahead of him with the track liner. The tunnel was on
an approximate 12 degree curve and, according to Claimant Lawyer, was "real
steep." Claimant Lawyer testified that he followed Claimant Chavez into the
tunnel but could not see Claimant Chavez ahead of him. Further, by Claimant
Lawyer's own estimate, he was going approximately 15 miles per hour and it
would have taken a distance of five to seven rail lengths to stop his equip
ment while he could only see at a distance of two rail lengths ahead. Thus,
Claimant Lawyer was traveling faster than his ability to see and stop.
The fact that Claimant Chavez was operating the track liner without
headlights does not change the result. The record reflects that Claimant
Chavez thought he informed Claimant Lawyer that the headlights were not working on the track liner.
liner and the record satisfies us that the operation of the headlights on the
track liner had no effect on avoidance of the collision which occurred as a
result of Claimant Lawyer's excess speed for the condition of the terrain.
Nor would the fact that the Track Patrolman was not disciplined even though
his motor car collided with the ballast equalizer after it collided with the
track liner require a different result. The record reflects that the motor
car was proceeding slowly at five miles per hour or less and had more than
adequate stopping distance between it and the ballast equalizer (three to four
rail lengths). The motor car slid and lost friction and was unable to stop
after passing over hydraulic fluid that spilled onto the tracks as a result of
the collision caused by Claimant Lawyer on the ballast equalizer. Therefore,
we can find no disparate treatment in the failure to discipline the Track
Patrolman.
Rule M requires employees to expect the movement of equipment and to
take every precaution to prevent injury. Rule 405 requires employees to expect to find the track in
striking other track cars. Similarly, Rule 415 requires special care be exercised in adverse conditi
speeds for existing conditions. The record thus supports the Carrier's determination that these rule
the above, we do not believe under the circumstances that the Carrier's action
of assessing dismissal was either arbitrary or capricious.
However, we do not find substantial evidence in the record to support
the decision to impose discipline upon Claimant Chavez. He was operating in
the tunnel at a cautious speed when he was struck by Claimant Lawyer. The
Carrier asserts that some fault should be placed upon Claimant Chavez because
he was operating without lights. However, the record shows that he reported
the problem with the lights to his Supervisor prior to the collision and the
record further reflects that he was denied permission to get a part to repair
the lights. In any event, as we have found above, the record satisfies us
that the lack of lights on the track liner was not the cause of the collision,
but the collision was attributable to the speed of the ballast equalizer under
the given conditions. There is no evidence that Claimant Chavez was in any
fashion culpable for the collision. Therefore, we shall require that Claimant
Chavez' record be cleared of the demerits assessed.
Award Number 26532 page 3
Docket Number NW-26927
FINDINGS: The Third Division of the Adjustment Board, upon the whole record
and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute are
respectively Carrier and Employes within the meaning of the Railway Labor Act,
as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over the
dispute involved herein; and
That the Agreement was not violated with respect to Claimant Lawyer
but was violated with respect to Claimant Chavez.
A W A R D
Claim sustained in accordance with the Opinion.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest:
Nancy J. ,Wr - Executive Secretary
Dated at Chicago, Illinois this 30th day of September 1987.