NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number MW-2(,264
Herbert L. .Marx, Jr., Referee
(Brotherhood of Maintenance of :Jay Employes
PARTIES TO DISPUTE:
(Seaboard System Railroad
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when it used Mechanical
Department forces instead of Bridge and Building Department forces to construct concrete floors, fou
Tampa, Florida, beginning on or about September 8, 1980 [System File
C-4-(36)-Tampa Div.-9/12-1(83-21)K2].
(2) Because of the aforesaid violation, each Group A B&B employe
holding an assignment on the Jacksonville and Tampa Divisions during the claim
period be allowed pay at their respective straight-time rates for an equal
proportionate share of the total number of man-hours expended by Mechanical
Department forces in performing the work referred to in Part (1) hereof."
OPINION OF BOARD: This is a Claim on behalf of B&B Subdepartment Group A
employes to work performed by Mechanical Department
employes (Carmen) in reference to certain concrete work and relocation and
reconstruction of a building at the Uceta Shops, Tampa.
In its defense, the Organization cites its Scope Rule which reads as
follows:
"RULE 1
SCOPE
These Rules cover the hours of service, wages
and working conditions for all employes of the
Maintenance of Way and Structures Department as
listed by Subdepartments in Rule 5 - Seniority
Groups and Ranks, and other employes who may
subsequently be employed in said Department,
represented by Brotherhood of Maintenance of Way
Employes.
This Agreement shall not apply to:
Supervisory forces above the rank of foremen,
clerical employes and Signal and Communications
Department employes."
Award Number 26551 Page 2
Docket Number "IW-26264
As a Third Party in interest, the Brotherhood Railwav Carmen or t!;e
United States and Canada was notified of the dispute but declined to intervene.
At the outset of its Submission, the Carrier raises objection to the
form of the Claim, in that individual employes are not cited as claimants. As
will be discussed below, previous Awards involving the same parties have been
set forth in similar fashion. Without setting aside the accepted requirement
for specificity in claims, the Board finds it appropriate in this further
instance to resolve the matter on its merits.
The Carrier has presented a substantial record over an extended
period showing that Mechanical Department employes have been engaged in
concrete work. Further, the building in question was originally constructed
by Mechanical Department employes, and they were employed here in its relocation.
There have been a number of Awards addressing the same question as
here. Those cited to the Board by the Carrier have uniformly found that, in
regard to such construction work, the Scope Rule does not require the remedy
which the Organization seeks here. As one example of such Awards, Third
Division Award No. 26208 states:
"The Scope Rule involved in this Claim is
general in nature and this Claim is one of a
series of recent Claims regarding its meaning or
application. Award 25090 states:
'This Board has carefully reviewed the
record of this case and the many citations
submitted by both sides in support of their
respective positions. The results of that
review reveals that Carrier is correct that
both B 6 B Department personnel and Mechanic
Department personnel have performed the
disputed work at various times and various
locations on the property. It also reveals
that the Scope Rule involved here is general
in nature and does not specify that the disputed work belongs only to the B 6 B Department employes.
There is no contention that the work involved is not of the nature
customarily performed by employes represented by the Organization. Rather,
the Carrier argues and the Board finds that there is no contractual sanction
which confines the particular work here at issue to the Claimants. In so
finding, the Board is supported by the cited and other Awards in similar
circumstances to the same effect.
Award Number 26551 Page 3
Docket Number MW-26264
FINDINGS: The Third Division o· tie Adjustment Board, after giving the
parties to this dispute due notice of hearing thereon, -ind upon the
whole record and all the evidence, finds and holds:
That the Carrier and the Employes involved in this dispute are
respectively Carrier and Employes within the meaning of the Railway Labor Act,
as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over the
dispute involved herein; and
That the Agreement was not violated.
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
00,10,
Attest:
Nancy J er - Executive Secretary
Dated at Chicago, Illinois, this 30th day of September 1987.