NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number MW-26983
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(The Chesapeake and Ohio Railway Company (Northen Region)
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood
that:
(1) The ten (10) days of suspension imposed upon Track Foreman R. E.
Brown for alleged insubordination for failure to comply with Assistant Track
Supervisor B. L. Jewel's instructions on November 15, 1984, was arbitrary and
on the basis of unproven charges (System File C-D-2670/MG-5086).
(2) The claimant's record shall be cleared of the charges leveled
against him and he shall be compensated for all wage loss suffered."
OPINION OF BOARD: The Carrier's Track Supervisor intended to be absent on
November 15, 1984, and his plans were that the surfacing
unit be operated that day to surface the last mile and one half of Carrier's
Chicago Subdivision. The procedure to be followed contemplated that intervening roadway crossings be
unit to surface thru the crossing. If a crossing was not pulled, the surfacing unit skipped that cro
Crossings are pulled by the removal of certain materials within the crossing
in advance of the surfacing unit and then restoration is made to the crossing
following passage of the surfacing unit.
In anticipation of his one day absence, the Track Supervisor conferred with his Assistant Track
wanted done on November 15, 1984. Arrangements were thereafter made to augment the Claimant's gang w
work began on November 15, 1984, the Assistant Track Supervisor instructed the
Claimant to meet with the Foreman of the surfacing unit and to remove road
crossings ahead of that unit.
The Claimant was assigned as a Track Foreman with supervision of a
gang of five other employes. His total service with the Carrier exceeded 13
years and all of it was in the Track Department. He had served as a Foreman
for six years. With this experience, the Claimant knew or should have known
what was required in the instructions he received from the Assistant Track
Supervisor as well as what was necessary to comply with those instructions.
Award Number 26571 Page 2
Docket Number MW-26983
When work was concluded on November 15, 1984, the surfacing unit had
surfaced to a point approximately one half mile beyond 76th Street. The unit
skipped the road crossing at 76th Street because that crossing had not been
pulled by the Claimant and his gang. It is not disputed that the track line
and surface were left in an inferior condition to that which would have resulted had the surfacing u
On November 20, 1984, the Carrier charged the Claimant with responsibility for insubordination f
ahead of surfacing unit SU-261 on that date. Hearing was scheduled and held
on November 30, 1984. Under date of December 11, 1984, the Claimant was notified that he had been fo
had been charged and that an actual suspension of ten-working days was administered as discipline. S
behalf of the Claimant by the Organization and those appeals were denied by
designated Officers of the Carrier. The dispute has been submitted to this
Board and it is properly before us.
It is clear and undisputed on the record that the Claimant was given
a fair and impartial Hearing and that the Carrier has complied with all prerequisites of the Agreeme
we find the instructions given to the Claimant by the Assistant Track Supervisor before the Claimant
clear and concise. The Claimant, himself, testified he was to "pull crossings" in front of the Forem
At the Hearing on November 30, 1984, the Claimant was given full
opportunity to explain his part in the events of November 15, 1984, as well as
that of others involved. In short, it was the Claimant's testimony that there
was not sufficient time for him and his gang to pull the 76th Street crossing
without incurring overtime, which had not been authorized. In support of this
overall explanation, the Claimant detailed seven incidents or non-incidents
preventing his completion of the work within authorized time. In his testimony, however, he did not
attempt to overcome the obstacles he felt prevented fulfillment of his instructions.
In addition to the Claimant, four other witnesses appeared and gave
testimony at the Hearing on November 30, 1984. The particulars involved in
the charge were adequately developed. While there are conflicts in certain
testimony, most is free from dispute. As stated in prior awards, this Board
functions in an appellant capacity and we do not resolve conflicting testimony.
While we concur in the position of the organization that there is no
evidence of the Claimant having displayed a rebellious attitude, taken as a
Award Number 26571 Page 3
Docket Number MW-26983
whole, the evidence is clear and convincing that the Claimant was responsible
for insubordination, as charged, albeit not openly displayed. Hence, we do
not disturb the Carrier's determination.
We have a similar view with respect to the sanction of an actual suspension of ten working days
serious and a ten day suspension is not excessive in the circumstances herein.
FINDINGS: The Third Division of the Adjustment Board, upon the whole record
and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute are
respectively Carrier and Employes within the meaning of the Railway Labor Act,
as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over the
dispute involved herein; and
That the Agreement was not violated.
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest:
Nancy J. v - Executive Secretary
Dated at Chicago, Illinois this 30th day of September 1987.