NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number MW-26660
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(National Railroad Passenger Corporation - (Amtrak)
( Northeast Corridor
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:
(1) The discipline (three days of suspension and disqualification as
track foreman and assistant track foreman for one year) for alleged violation
of Construction and Maintenance Practice (MW-1000). Paragraph 213.6(a) and
Paragraph 213.9(b) on February 25, 1984 was without just and sufficient cause
(System File NEC-BMWE-SD-894D).
(2) Mr. T. T. Oates' seniority as track foreman and assistant track
foreman shall be restored and unimpaired, his record shall be cleared of the
charges leveled against him, he shall be compensated for all wage loss suffered during his suspensio
he would have received as track foreman and what he was paid during his disqualification period."
OPINION OF BOARD: The Claimant became an Amtrak employee in 1976 and was
working position of Surfacing Foreman on February 25, 1984.
In that position, Claimant shared supervisory responsibility for Gang Z-032
with another Surfacing Foreman, H. Smothers.
On the night of February 24, 1984, Foreman Smothers supervised a portion of the Gang assigned to
and Bush, M.P. 72.5 and 73.8. On that evening, Claimant worked with another
portion of the Gang, hauling ballast. Foreman Smothers took the track out of
service and placed a 30 mph speed restriction between M.P. 72.5 and 73.8,
territory which otherwise was subject to Class 6 operation, i.e., 110 mph.
During his tour of duty on the track resurfacing job, Foreman
Smothers completed only a small section between 72.5 and 72.6, due to malfunction of the tamper.
February 25, 1984. According to Claimant's testimony, he inspected the completed work from 72
for Class 6 operation. Inexplicably, however, Claimant removed the speed
restriction from the entire course, Edgewood to Bush, M.P. 72.5 to 73.8, including the portion not y
A.M. on February 25, 1984.
Later that morning, Track Inspectors assigned to officially review
the work in question found that the speed restriction had already been lifted
by Claimant. Also the Track Inspectors determined that the portion between
72.5 and 73.8 was not fit for Class 6 operation.
Award Number 26667 Page 2
Docket Number MW-26660
After ascertaining that Claimant had lifted the 30 mph speed restriction under the circumstances
"VIOLATION OF CONSTRUCTION AND MAINTENANCE PRACTICE
(MW 1000) Par. 213.6 Protection in part: a) Protection shall be provided for any track that is
considered not satisfactory for the passage of
trains at the maximum speed permitted, including
placing an appropriate temporary speed restriction
and notification of the block station and/or train
dispatcher.
VIOLATION OF CONSTRUCTION AND MAINTENANCE PRACTICE
(MW 1000) Par. 213.9 Classes of Track: Operating
speed limits (in part b) If a segment of track
does not meet all of the requirements for its
intended class, it is reclassified to the next
lowest class of track for which it does meet all of
the requirements of this part . ....
SPECIFICATION: In that on February 25, 1984 at
approximately 3:58 AM you failed to provide proper
protection for the track when you removed the 30
mph speed restriction on S2 track at MP 73.8-72.5
and returned it to the maximum authorized speed of
110 mph (class 6). Subsequent inspection by other
supervision indicated the track condition of that
area to only meet criteria for a maximum speed of
80 mph (class 4)."
Following the Investigation, Carrier concluded that Claimant was guilty as
charged and assessed penalty of three days suspension without pay and disqualification as Supervisor
The record amply demonstrates that Claimant removed a speed restriction placed for the protectio
working. He removed this restriction without personally making sure that the
work had been completed. In fact, the record indicates that Claimant knew, or
should have known, that the job was only partially done when he removed the
restriction for the entire section which had been placed under protection. As
an experienced Maintenance of Way Foreman Claimant is fully responsible for
his failure to follow safety requirements and cannot shift the blame to his
fellow Foreman who placed the protection in the first place.
Based upon the foregoing we find no basis for disturbing Carrier's
determination of Claimant's guilt. Nor can we find the penalty imposed so
unusually harsh or disproportionate to the offense as to warrant modification.
Award Number 26667 Page 3
Docket Number MW-26660
FINDINGS: The Third Division of the Adjustment Board, upon the whole record
and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute are
respectively Carrier
and Employes within the meaning of the Railway Labor Act
as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over the
dispute involved herein; and
That the Agreement was not violated.
A W A R D
Claim denied.
NATIONAL
RAILROAD ADJUSTMENT
BOARD
By Order of Third Division
Attest
Nancy . D9`ver - Executive Secretary
Dated at Chicago, Illinois, this 23rd day of November 1987.