NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number MW-26238
Edward L. Suntrup, Referee
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(The Atchison, Topeka and Santa Fe Railway Company
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when it assigned machine
operator's work, in connection with a washout, to outside forces beginning
September 28, 1983 (System File 210-A8-8316/11-1940-20-187).
(2) The Carrier also violated Appendix No. 8 (Article IV of the May
17, 1968 National Agreement) when it did not give the General Chairman advance
written notice of its intention to contract said work.
(3) As a consequence of the aforesaid violation, Group 5 Machine
Operators R. Gray, T. Ferguson, V. Hart, S. Moser and M. LaFaye shall each be
allowed pay at their respective rates for an equal proportionate share of the
total number of man-hours expended by outside forces in performing the work
referred to in Part (1) hereof."
OPINION OF BOARD: On September 25, 1983, heavy rainstorms caused extensive
damage to approximately thirty miles of roadbed, banks,
dikes, channels and bridges on the Carrier's right-of-way in the Fourth
District of its Albuquerque Division. The Carrier's operations were inter
rupted and it immediately engaged in emergency reconstruction work. To assist
the Carrier's forces in this attempt to return its operations to normal, the
Carrier contracted with an outside contractor. The Carrier did so in accord
ance with its Letter of Understanding with the Organization which is dated
September 28, 1956. This Letter states the following:
"In connection with the application of the
above, the Carrier may, without conference with
the General Chairman, arrange for the use of
equipment of contractors or others and use other
than Maintenance of Way employes of the Carrier
in the performance of work in emergencies, such
as wrecks, washouts, fires, earthquakes, landslides and, similar disasters."
On September 27, 1983, the trackage in this District of the Albuquerque
Division was returned to service. The Carrier continued to use the outside
contractor after that date. The record shows that from September 27, 1983,
through November 18, 1983, contractor's operators performed approximately
...861 man-hours of service" with two bulldozers and a front-end loader which
belonged to that Company.
Award Number 26708 Page 2
Docket Number MW-26238
On October 19, 1983 the General Chairman of the Organization filed a
Claim on behalf of the Coast Line Group 5 Machine Operators named in the
Statement of Claim. This Claim alleged that the Carrier was in violation of
various Rules of the current Agreement and requested as relief payment "...for
equal and proportionate shares of all hours worked by Herschkowlitz Construction Company since Septe
responses to this Claim the Carrier stated that it had used all Group 5 equipment and operators "...
work involved" after September 27, 1983, and that "...the Claimants and their
machines were used on the Fourth District until the work was completed."
Although the parties appear, in their exchange on property, to want to resolve
this case as one which falls under the correct interpretation of the Agreement's Scope Rule, the foc
...emergency existed" after September 27, 1983. If it did, the Carrier was
correct in continuing to apply the Letter of Understanding of September 28,
1956 (Appendix 8 of the Agreement). If an emergency did not continue to exist
after September 27, 1983, the Claim has merit.
The position of the Organization is as follows. It states that
...Group 5 employes have been force reduced each of the last two winters,
therefore, these contractor's forces (after September 27, 1983) are causing a
loss of work opportunity for Group 5 Coast Line Employees." Even though the
Claimants continued to work throughout the reconstruction this argument points
to future potential loss of work because of the presence of the contractor.
The most specific argument proposed by the Organization is that after the
tracks were opened up on September 27, 1983, the "...emergency ceased to
exist." According to the Organization the restoring of "...dikes, roadbeds,
banks, channels and bridges" was "...routine work" and it should have been
reserved for the members of its craft. Further, the existence of "...slow
orders" after September 27, 1983, were also not sufficient proof, according to
the Organization, to substantiate that an emergency existed.
What exactly was the factual situation on the some thirty miles of
right-of-way after September 27, 1983? There were slow orders issued although
the parties disagree, in the record, on exactly how many. At least the following were issued on Sept
affected territories:
"Speed limit 10 MPH over bridge at Post 84.4
between Kirkland and Skull Valley, Fourth
District.
Speed limit 10 MPH over bridge between Mile
Posts 43.3 and 43.5 between Tucker and Kayfour,
Fourth Division.
*Speed restriction removed October 10, 1984.
Award Number 26708 Page 3
Docket Number MW-26238
Speed limit 10 MPH between Mile Posts 51.3 and
51.9 over shoo-fly between Skull Valley and
Tucker, Fourth District.
Speed limit 10 MPH over bridge between Mile
Posts 54 and 54.1 between Skull Valley and
Tucker, Fourth District.
*Speed limit increased to 30 MPH October 14,
1984.
*Speed restriction removed December 5, 1983.
Speed limit 10 MPH over bridge between Mile
Posts 54.8 and 55 between Skull Valley and
Tucker, Fourth District.
*Speed restriction removed October 10, 1983.
Speed limit 20 MPH over bridge between Mile
Posts 80.2 and 63.3 between Skull Valley and
Tucker, Fourth District.
Speed limit 10 MPH over bridge between Mile
Posts 85.4 and 85.8 between Kirkland and Skull
Valley, Fourth District.
*Speed restriction removed October 18, 1983.
Speed limit 10 MPH over bridge between Mile
Posts 86 and 86.2 between Kirkland and Skull
Valley, Fourth District.
Speed limit 20 MPH over bridge between Mile
Posts 89 and 89.1 between Kirkland and Grand
View, Fourth District.
*20 MPH speed limit over bridge between
Mile Posts 89 and 89.1 was reduced to 10
MPH, effective October 2, 1983."
Thus some nine slow orders were issued on the territory in question with speed
limits, in most cases, reduced to 10 MPH. Several of these orders were not
lifted prior to the departure of the contractor. The Organization cites Third
Division Award 19948 to support its contention that slow orders "...alone do
not lead to the ultimate conclusion of emergency." The Board is in agreement
with the conclusions of this Award given the circumstances under consideration. In that case a fire
the Carrier decided to replace it with a steel structure. B&B forces installed
the structure and an outside contractor did the fill work. In the interim, a
Award Number 26708 Page 4
Docket Number MW-26238
slow order of 10 MPH was in effect. It took the contractor some ten days to
finish the work although it only worked five of those days. The Board reasoned in that case that the
not reflect a policy of immediate action by the Carrier" and it ruled that no
emergency existed and sustained the Claim. Such facts are in considerable
contrast to those of this case both because of the large number of slow orders
here under consideration and because of the "...pace of the work" required of
the contractor by the Carrier. That pace is best underlined by correspondence
by the Organization itself to the Carrier wherein it states, in its original
October 19, 1983, Claim letter, that "...contractor's forces have worked 10
hours per day, 7 days per week since September 28, 1983
...."
Such pace does
not suggest "...routine work." In view of this, Award 19948 cannot reasonably
be considered to have precedential value for this Claim. There is no dispute
that parts of the right-of-way along the thirty miles sustained major damage.
For example, the Carrier states in its correspondence of June 6, 1984, to the
Organization that:
"several bridges between Mile Posts 43 and 89 on
the Fourth District did sustain major damage.
For instance, at Bridge 51.6, a 200 ton section
of the concrete drainage box broke off and
washed 35 feet downstream together with most of
a 100 yard embankment 50 feet high (see attachment). At this location, it was necessary to
construct a shoo-fly on the upstream side of
this bridge in order to affect repairs. At
Bridge 84.4, some of the supporting timbers were
completely destroyed."
The record before the Board in this case paints one of fairly widespread destruction by the rain
for slow orders for up to six weeks after that date in some sections of the
Carrier's track in the Fourth District of its Albuquerque Division. The
Carrier states that it did not have sufficient manpower among its own employees to bring the situati
the pace of the work performed by the contractor while it was on property.
In Claims such as this one the burden of proof lies with the Organization as moving party (Secon
Award 15670). A study of the record warrants the reasonable conclusion that
such burden has not been met in this case. The Carrier was not in violation
of the Agreement when it continued to use the contractor after September 27,
1983, under the provisions of Appendix 8 of the Agreement. The record reasonably establishes that an
merits, the Claim must be denied.
FINDINGS: The Third Division of the Adjustment Board, upon the whole record
and all the evidence, finds and holds:
Award Number 26708 Page 5
Docket Number MW-26238
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute are
respectively Carrier and Employes within the meaning of the Railway Labor Act
as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over the
dispute involved herein; and
That the Agreement was not violated.
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest.
Nancy J r - Executive Secretary
Dated at Chicago, Illinois, this 23rd day of November 1987.
LABOR MEMBER DISSENT
TO
AWARD 26708 - DOCKET MW-26238
(Referee Suntrup)
The Majority erred when it held that:
"The record before the Board in this case paints one of
fairly widespread destruction by the rains on September 25,
1983. Such implied the need for slow orders for up to six weeks
after that date in some sections of the Carrier's track in the
Fourth District of its Albuquerque Division. The Carrier states
that it did not have sufficient manpower among its own employees
to bring the situation back to normal in several days. The
record reasonably supports this contention, both by the number
of slow orders issued and by the pace of the work performed by
the contractor while it was on property."
The Majority found that the record in this dispute supports the Carrier's position that an emerg
review of the entire Award discloses at least two (2) inconsistencies in the
reasoning relied upon in arriving at such a finding.
First, the majority points to a picture of fairly widespread destruction caused by the rains of
Albuquerque Division. However, this dispute involved only a small portion
of the Albuquerque Division. This is important because the slow order
listed by the Majority involved bridges which were located within the cl.3im
area, but were not affected by the work performed by the contractor's
forces. The fact is that it was undenied by the Carrier that such was the
case. This was clearly established in the record of the handling of this
dispute on the property and was pointed out to this Board. If the contra,~-
tor's forces were nut performing work which materially affected the slow
orders, then the fact that those
moment insofar as the disposition
Second, the Majority found i that it did not have sufficient ma
the pace of the work performed by
slow orders existed should have been of no
of the instant claim was concerned.
t
significant that the Carrier asserted
n power and in support thereof, pointed to
the contractor's forces. However, it was
undenied in the record and pointed out to the Majority that the Carrier's
forces were not working any overtime hours during the claim period. This is
particularly striking when consideration is given to the fact that prior to
September 27, 1983, the date on which the Carrier's train traffic was
restored in the claim area, the Carrier's forces were performing significant
amounts of overtime service. It was pointed out by the Organization that
when the Carrier's train traffic was restored, albeit with the aforementioned slow orders, the Carri
overtime would be authorized. In other words, the Carrier's employes were
at home while the contractors employes were working in their place. Hence,
it could hardly be argued that such a circumstance supported the Carrier's
contention that an emergency existed.
We submit that the Majority ignored the Organization's undenied arguments concerning the emergen
Organization had not met its burden of proof. Therefore, I dissent.
D. D. B rtholomay
Labor Member