NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number MW-27003
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(National Railroad Passenger Corporation (Amtrak)
(Northeast Corridor
STATEMENT OP CLAIM: "Claim of the System Committee of the Brotherhood that:
1. The five (5) days of suspension imposed upon EWE 'C' Ballast
Regular Operator J. W. McSorley for alleged violation of Rule 'H' on August 7,
1984, was arbitrary, capricious, on the basis of unproven charges and in violation of the Agreement
2. The claimant's record shall be cleared of the charge leveled
against him and he shall be compensated for all wage loss suffered."
OPINION OF BOARD: The Claimant in this case had been employed by the Carrier
for a period of seven years at the time of the incident
giving rise to the dispute, namely August 7, 1984. On that date, and for some
time prior thereto, the Claimant was assigned as an E.W.E. "C" Machine
Operator. As matters would have it on that date, the Claimant was starting to
"travel" Ballast Regulator #4249, which he regularly operated, from Thorn
Interlocking to Downingtown Yard when he became involved in a collision with
Tamper #0408 (Torsion Beam).
As a consequence of the collision, the Carrier's Track Supervisor
conducted a somewhat formalized Investigation on August 9, 1984, at which testimony was taken and tr
who was substituting for the regular operator of Tamper #0408, and from the
Track Foreman. This testimony was taken individually and separately with no
cross-examination had. Carrier's Equipment Engineer also interviewed the
three above-mentioned employes plus another and submitted a written statement
concerning the collision.
Under date of August 27, 1984, the Claimant was charged as follows:
"Violation of rule 'H' Amtrak Rules of Conduct,
that part which reads, 'Employes must take every
precaution to guard against loss and damage . . .'
Specification a) In that on August 7, 1984 at
approximately 12:01 p.m. you failed to maintain
sufficient distance between equipment while
operating Ballast Regulator #4249 on #2 track at
Thorn Interlocking, resulting in a collision with
Tamper #0408 which caused $8,000 damage to the
Lining Buggy portion of that Tamper."
Award Number 26730 Page 2
Docket Number MW-27003
A Trial was held on September 5, 1984. The Claimant was present and
represented.
Initially, the Organization objects that the Carrier failed to conduct a fair and impartial tria
West Downingtown Yard, were not called as witnesses at the Trial. The record
does not make clear that the two witnesses in question actually witnessed the
collision but it is at least clear that they witnessed the scene after the
collision had occurred. Likewise, there is testimony in the record that these
two potential witnesses had heard the Truck Driver give a horn signal for the
stop he made with Tamper #0408, which he was "traveling" at the time. Neither
the Claimant nor the Organization has suggested any factual testimony which
the so-called "neutral eye-witnesses" could have presented that was not otherwise developed during t
responsibility to conduct a full and fair Trial in which all of the pertinent
facts are developed. On this record, we are confident that has been done.
The Organization offers a second objection in that the Equipment
Engineer interviewed three of the employes directly involved with the collision and obtained written
they would be permitted representation by the Organization if they so desired.
We summarily dismiss this objection on the basis that it has neither been
sufficiently developed nor substantiated to permit the Board to reach a determination.
Turning to the merits of the discipline, we believe a number of
factors are relevant and need be considered. The Carrier takes the position
that the Claimant was negligent while operating the Ballast Regulator in that
he did not keep that equipment at a safe distance behind the Tamper. Principal support for this posi
September 5, 1984.
The Track Supervisor testified that on the basis of his investigation, he felt there was insuffi
Equipment Engineer testified that on the basis of his investigation, he felt
the cause of the collision was the Claimant following too close for conditions. It is noted that nei
Engineer witnessed the collision; their testimony was derived from information
obtained from employes involved in the collision. Additionally, one observed
the site on the following day and the other inspected the machines when they
arrived at Downingtown.
Award Number 26730 Page 3
Docket Number MW-27003
During the Trial, testimony was developed indicating that the Ballast
Regulator was not in good working order. Mention was made by several of the
witnesses that this equipment had numerous leaks in the hydraulic system and
that the brake system was not functioning properly. In this regard, testimony
also indicated that a mechanic was called out to make repairs in the braking
system after the collision. The mechanical deficiencies of the Ballast Regulator are suggested as ha
of the hydraulic fluid may have been on the rails, which, in combination with
the deficiencies in the brakes, caused the Regulator to skid over a distance
sufficient to permit the Claimant to put the Regulator in reverse before the
collision occurred.
From the inception of the collision the Claimant maintained that the
principal cause of the collision was the lack of qualifications on the part of
the employe who was "traveling" the Tamper at the time. It developed that the
employe who was regularly assigned to operate the Tamper had a dental appointment and he was excused
11:30 A.M. Then, the Foreman instructed the gang's Truck Driver to "travel"
the Tamper from the home signal at Thorn to Downingtown West Yard. As a
result of the considerable testimony developed over the Truck Driver's qualifications on the Tamper,
qualifications.
It is not our function to decide the qualifications of the Truck
Driver to properly operate the Tamper; that question is not particularly in
point. Instead, our consideration is given to whether the Claimant received a
recognizable stop signal when the Truck Driver stopped the Tamper in front of
the tower. The Truck Driver testified that he blew the horn on the Tamper two
or three times prior to stopping the machine, but the Claimant insists that he
did not hear the horn. The regular Tamper Operator was called as a witness
during the Trial and was interrogated on the point. He testified that the
procedure used when stopping was:
"To flash the (quartz) lights because they are
visible, you cannot always hear the horn."
It may be added that both the regular Tamper Operator and the Truck Driver,
who was substituting for the regular operator when the collision occurred,
testified that the substitute operator had not previously "traveled" the
involved Tamper. Also, the substitute operator testified that he had never
had to signal for a stop prior to the date of the collision.
Carrier summarizes its position in support of the discipline imposed
by pointing out that the Claimant was experienced, fully qualified and aware
of the Rules governing the movement of track cars. The Claimant was only
60-75 feet behind the Tamper and that distance was inadequate to safely stop
the Ballast Regulator as evidenced by the collision with the Tamper.
Award Number 26730 Page 4
Docket Number NW-27003
While the distance the Claimant maintained in following the Tamper is
certainly a significant and valid consideration in this dispute, there are
other factors present for which the Claimant was not responsible. The
Ballast Regulator was not in good order; both the hydraulic system and the
brake system were faulty to a degree and the Regulator was being taken to the
Downingtown Yard for the specific purpose of having repairs made to it.
Testimony is that some of the hydraulic fluid leaked on the rail. Finally, an
inexperienced substitute operator "traveled" the Tamper but a short distance
when he stopped and the Claimant did not receive the customary signal which he
recognized as indicating a stop. While it may be offered that all of these
other factors should have been taken into consideration by the Claimant in
order to safely stop the Ballast Regulator, the proof should be clear that the
distance maintained was not safe. Negligence on the part of the Claimant is
not demonstrated simply because a collision occurred.
As in all cases of this nature, we are bound by the evidence
presented by opposing factions at the Hearing. We find from a review thereof
that there was insufficient substantial evidence to enable Carrier to conclude
that Claimant was negligent, given the other factors mentioned hereinbefore.
FINDINGS: The Third Division of the Adjustment Board, upon the whole record
and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute are
respectively Carrier and Employes within the meaning of the Railway Labor Act
as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over the
dispute involved herein; and
That the Agreement was violated.
A W A R D
Claim sustained.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
i~
Attest:
Nancy J. Dever - Executive Secretary
Dated at Chicago, Illinois, this 11th day of December 1987.