Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 26779
THIRD DIVISION Docket No. MW-26751
88-3-85-3-505
The Third Division consisted of the regular members and in
addition Referee Edwin H. Benn when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Davenport, Rock Island and North Western Railway Company
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when it assigned outside
forces to perform track work between Mile Posts 169 and 179 from July 24
through August 17, 1984 (System File 31-3).
(2) As a consequence of the aforesaid violation, Extra Gang Foreman
G. Gladfelter, Truck Driver A. Avila, Machine Operator J. Shepard and Track
Laborers D. Steffen, M. Hughes, S. Moss, S. Serrano, L. Andresen, D. Goldsberry, W. Thomas, A. Lieva
Mickle, V. Madison, G. Castel and L. Gomez shall each be allowed one hundred
fifty-two (152) hours of pay at their respective straight time rates."
FINDINGS:
The Third Division of the Adjustment Board upon the whole record
and all the evidence, finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employes within the meaning of the
Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the
dispute involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
Claimants hold seniority within the Track and Roadway Equipment
Sub-Departments of the Carrier's Maintenance of Way and Structures Department.
At the time of the incidents involved in this Claim, one of the Carrier's
parent companies was the Milwaukee Road.
In 1982 and 1983 the Carrier notified the Organization that outside
labor would be used for a welded rail project. By letter dated March 22,
1984, the Carrier's General Manager wrote the General Chairman as follows:
"Please be advised that, in late spring of 1984,
the DRI&NW will be sledding and laying welded
rail for 10 miles between Mile Post 168.85 and
178.85.
Form 1 Award No. 26779
Page 2 Docket No. MW-26751
88-3-85-3-505
Most of this work will be done by Milwaukee road
forces and equipment, as none of our people are
qualified to perform this work, nor do we have
the necessary machinery. As you know, the
Milwaukee is one of our parent companies and has
done this type of work for us in the past.
During this period, all DRI&NW section people
holding seniority will be employed."
During the period July 24 through August 17, 1984, Milwaukee forces
performed track construction and maintenance work between Mile Posts 169 and
179, specifically, laying switches, unloading material and other maintenance.
At the time the Milwaukee forces performed the work at issue, the Carrier did
not have the necessary equipment or employes to perform the work. Further,
Claimants were working and lost no time due to the work attached to the welded
rail project. In the past, Milwaukee extra gangs have performed similar work.
First, contrary to the Organization's argument, we find that the
notice given by the Carrier encompasses the work at issue. The notification
given by the Carrier in 1982 and 1983 along with the letter of March 22, 1984,
amounted to sufficient notice that the work involved in this matter (i.e.,
laying switches, unloading material and other maintenance) would be performed
by non-Carrier forces to satisfy the notice requirements found in Rule 1 for
such work. Cf., Third Division Award 26766 where the March 22, 1984, notice
was held insufficient for picking up scrap rail and other material.
Second, in this case we are unable to agree with the Organization's
argument that a sustaining award is required due to the alleged lack of a
meeting prior to the contracting of work. While the note to Rule 1 mandates a
meeting of the parties concerning contracting of work, the Rule also has a
commensurate requirement that the Organization must first "request
... a
meeting to discuss matters relating to the said contracting transaction
....
Thus, giving the Organization the benefit of the doubt that no meeting
occurred (an assertion which the Carrier disputes), the record fails to disclose if a request for su
Third, upon balance and under the circumstances properly presented by
this record, the lengthy practice of using Milwaukee forces for similar work;
the lack of personnel and equipment for the Carrier to do the work at the
prescribed time (facts not refuted on the property); the fact that no loss of
employment was suffered by Claimants and the lack of any evidence that the
Carrier otherwise sought to avoid its contractual obligations all lead us to
conclude in this case that the Claim is without merit. We shall therefore
deny the Claim.
Form 1 Award
No.
26779
Page 3 Docket
No.
MW-26751
88-3-85-3-505
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest:
Nancy J. D v - Executive Secretary
Dated at Chicago, Illinois, this 28th day of January 1988.