Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 26864
THIRD DIVISION Docket No. MW-27424
88-3-86-3-665
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Missouri-Kansas-Texas Railroad Company

STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:

(1) The ten (10) days of actual suspension and ten (10) days of deferred suspension imposed upon Section Foreman J. W. Cryer and the five (5) days of actual suspension and ten (10) days of deferred suspension imposed upon Extra Gang Foreman K. D. Ward for alleged failure '*** to follow instructions by your superviso protect the safe passage of trains which caused a backhoe owned by Woods Dirt Contractors to be struck by Extra SP 7541N near mile post 629, pole 29 about 3:55 p.m., Thursday, September 26, 1985.' was without just and sufficient cause and on the basis of unproven charges (System Files 500-72/2579 and 200-130/2579).

(2) The claimants' records shall be cleared of the charges leveled against them and they shall be compensated for all wage loss suffered."

FINDINGS:

The Third Division of the Adjustment Board upon the whole record and all the evidence, finds that:

The carrier or carriers and the employe or employes involved in this dispute are respectively carrier and employes within the meaning of the Railway Labor Act as approved June 21, 1934.

This Division of the Adjustment Board has jurisdiction over the dispute involved herein.



On September 26, 1985, Carrier's roadmaster advised the Section Foreman, Claimant Cryer, to get an operator with a backhoe to MP629 in order to clean out a ditch. Claimant Cryer, in turn, instructed Claimant Ward, the extra gang foreman, to show the backhoe operator how to get to the location. Apparently this was done. Claimant Cryer also had a message issued to Train SP7541N to be aware that a backhoe would be working in the area of MP629, and this information was received by the train crew.

Claimant Ward also instructed the backhoe operator to be clear of the track by 3:30 P.M. before Train SP7541N was due to pass.
Form 1 Award No. 26864
Page 2 Docket No. MW-27424
88-3-86-3-665
Despite all of the foregoing, there was a collision between Train
SP7541N and the backhoe at approximately MP629. Claimants were given notice
of investigation on a number of rule citations including:





Concerning the provision of protection, Claimant Cryer testified as follows:












Form 1 Award No. 26864
Page 3 Docket No. MW-27424
88-3-86-3-665




























Form 1 Award No. 26864
Page 4 Docket No. MW-27424
88-3-86-3-665

























What is clearly evident from the foregoing testimony is that neither of the Claimants fulfilled his responsibility. Each concluded that the other would provide protection. Such failure warrants this Board's conclusion that Claimants were deficient in their responsibilities as supervisors. Whether others were also derelict, does not excuse the responsibility to provide protection. Since Claimants Ward will stand, and Claimant Cryer's discipline is modified to the same. Claimant Cryer shall be allowed five (5) days pay at the applicable rate and his record corrected accordingly.
Form 1 Award No. 26864
Page 5 Docket No. MW-27424
88-3-86-3-665



        Claim sustained in accordance with the Findings.


                          NATIONAL RAILROAD ADJUSTMENT BOARD

                          By Order of Third Division


Attest4 Gy~/
      Nancy J. r - Executive Secretary


Dated at Chicago, Illinois, this 25th day of February 1988.