Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 26933
THIRD DIVISION Docket No. MW-26516
88-3-85-3-254
The Third Division consisted of the regular members and in
addition Referee Peter R. Meyers when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Consolidated Rail Corporation
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:
(1) The 10 days of suspension imposed upon Track Foreman J. W. Doerr
for alleged 'Failure to initiate immediate remedial action
...
at M.P. 38.1
...
on February 10, 1984
...
which resulted in the derailment of Train WPCA-30
...
on February 12, 1984' was without just and sufficient cause and on the
basis of unproven charges (System Docket CR-799-D).
(2) The claimant's record shall be cleared of the charges leveled
against him and he shall be compensated for all wage loss suffered."
FINDINGS:
The Third Division of the Adjustment Board upon the whole record
and all the evidence, finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employes within the meaning of the
Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the
dispute involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
Claimant is employed as a track foreman. On February 10, 1984,
Claimant and his two-man crew were assigned to replace ties on the Cape May
Secondary Track at Richland, New Jersey. On February 12, 1984, a derailment
occurred at M.P. 38.1 of the track. Claimant subsequently was instructed to
attend a formal investigation in connection with the following charge:
"Failure to initiate immediate remedial action
on the deteriorated tie condition in the middle
of the curve at M.P. 38.1, Cape May Secondary,
on February 10, 1984 after walking the entire
curve, which resulted in the derailment of Train
WPCA-30 at 4:10 P.M. on February 12, 1984."
Form 1 Award No. 26933
Page 2 Docket No. MW-26516
88-3-85-3-254
The hearing was held as scheduled, and as a result, Claimant was assessed a
ten-day suspension. The Organization thereafter filed a claim on Claimant's
behalf, challenging the suspension.
This Board has reviewed the evidence and testimony in this case, and
we find that there is insufficient evidence in the record to support the
guilty finding. Therefore, the claim must be sustained.
The Carrier has failed to show that the Claimant did not initiate
proper remedial action with respect to ties at M.P. 38.1. The Claimant's
Supervisor testified that the Claimant had discretion to determine which ties
should be replaced; moreover, there were more deteriorated ties needing replacement than Claimant po
the amount of the material available. The Carrier's Assistant Division Engineer concluded that the t
Claimant's work on the day in question. Therefore, there is no probative
evidence that the derailment occurred because of the Claimant's alleged
negligence.
A W A R D
Claim sustained.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest:
ancy J. -Executive Secretary
Dated at Chicago, Illinois, this 30th day of March 1988.