Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 26951
THIRD DIVISION Docket No. MW-26614
88-3-85-3-607
The Third Division consisted of the regular members and in
addition Referee Gil Vernon when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(St. Louis Southwestern Railway Company
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when it assigned outside
forces to weld, strip, grind, crop and load ribbon rail at Illmo, Missouri
beginning August 6, 1984 (System File MW-84-46-CB).
(2) The Carrier also violated Article 33 of the Agreement when it
did not give the General Chairman advance notice of its intention to contract
said work.
(3) As a consequence of the aforesaid violations, Welders D. G.
Hiett and J. F. Rochner and Welder Helpers G. A. Vance and B. D. Doherty shall
each be allowed an equal proportionate share of the man-hours expended by
outside forces in performing the work referred to in Part (1) hereof."
FINDINGS:
The Third Division of the Adjustment Board upon the whole record
and all the evidence, finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employes within the meaning of the
Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the
dispute involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
On September 21, 1984, the Organization filed a claim protesting the
fact that beginning August 6, 1984, four employees of the Holland Welding
Company performed the work of welding, stripping, finish grinding, cropping
and loading of ribbon rails for use on the Pine Bluff Division. The claim
sought an equal proportionate share for the total number of hours expended by
the contractor beginning "August 6, 1984 and on a continuous basis." The
claim was denied and appealed.
Form 1
Page 2
Award No. 26951
Docket No. MW-26614
88-3-85-3-607
In its January 25, 1985, declination the Carrier acknowledged that
the Holland Welding Company had worked on the Pine Bluff Division from August
6, through September 27, 1984. However, it maintained that the lack of notice
was an oversight and that the Claimants were all fully employed during the
relevant period of time.
On May 14, 1985, the General Chairman confirmed the conferencing of
the claim as follows:
"This has reference to claim MW-84-46-CB, your
letter of January 25, 1985, and the conference
held concerning this claim May 2, 1985.
During the conference you were advised that it
was our position that there was not an emergency
at the time the work was performed, the Carrier
clearly violated Article 33, the contractor
worked from August 6, 1984 through September 27,
1984 or a total of 1248 man hours.
You were advised that since this is a continuing
claim it is now for a total of 1248 hours.
You were also advised that the Carrier owned
Holland Welder has completed working on the
North end seniority district and there will be a
force reduction in the Welding Department,
therefore these employees will be adversely
affected and have a loss of earnings account of
this contractor performing their work.
We cannot accept your decision and the claim
will be sent to the Third Division of the
National Railroad Adjustment Board."
From this we are unable to tell if the work of the contractor was limited to
the period of August 6 to September 27, 1984, as the Carrier stated, or if the
Organization is contending the contractor's activities continued past September 27, 1984, into 1985.
cannot determine if there was a true loss of work opportunities for the
Claimants.
Since we cannot conclude, based on this record that the contracting
took place after September 27, 1984, and since the Claimants were fully
employed at least up to that date, no relevant loss of work or work opportunities has been pr
the advance notice provision of Article 33, albeit through an oversight, the
monetary claim is denied.
Form 1 Award No. 26951
Page 3 Docket No. MW-26614
88-3-85-3-607
A W A R D
Claim sustained in accordance with the Findings.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest:
Nancy J.
?--*r
- Executive Secretary
Dated at Chicago, Illinois, this 30th day of March 1988.