Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 27025
THIRD DIVISION Docket No. MW-26248
88-3-84-3-669
The Third Division consisted of the regular members and in
addition Referee Eckehard Muessig when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Southern Pacific Transportation Company (Western Lines)
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when it assigned Purchasing
and Materials Department forces instead of Bridge and Building Department
forces to dismantle the wooden floor, anchored to a cement slab, at the South
end of the 'Old Sawmill' in the Locomotive Works Facility at Sacramento,
California, on February 10 and 11, 1983 (Carrier's File MofW 152-974).
(2) Because of the aforesaid violation, Foremen N. F. Shull and B.
H. Mollart, Assistant Foreman P. Osiow, Welder T. A. Freeman, Carpenters J. E.
Lee and S. R. Griffith and Steelman L. F. Childs shall each be allowed pay at
their respective.straight time rates for an equal proportionate share of the
ninety-six (96) man-hours expended by Purchasing and Materials Department
employes in performing the work referred to in Part (1) hereof."
FINDINGS:
The Third Division of the Adjustment Board upon the whole record and
all the evidence, finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employes within the meaning of the
Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the
dispute involved herein.
Parties to said dispute were given due notice of hearing thereon.
In this dispute, both parties have raised issues and arguments in
their Submissions to the Board that were not advanced on the property. Accordingly, this Board is pr
were not raised on the property.
With respect to the questions properly before us, the significant
events are as follows:
Form 1 Award
No.
27025
Page 2 Docket
No.
MW-26248
88-3-84-3-669
(a) February 25, 1983: The Organization submitted its initial claim
to the Carrier's Regional Engineer. It mainly asserted that, on
the dates claimed, the Carrier assigned employees of the P 5 M
Department to perform Bridge and Building Sub-Department work.
It then described the work consisting of "...dismantling a floor
54 feet by 60 feet which was anchored to a concrete slab in a
building located on the southeast end of the old sawmill, now
called the Track Distribution Center within the Sacramento Loco
motive Works Facility." The claim also included the names of
the employees of the P 5 M Department who allegedly did the
disputed work and asked for 96 hours compensation for the
Claimants.
(b) April 7, 1983: The Carrier's Regional Engineer denied the claim
stating in pertinent part: "Have investigated above claim and
find that the wooden floor referred to in said claim was not
anchored to the concrete underneath, it was considered scrap
lumber."
(c) May 9, 1983: The General Chairman appealed the decision of the
Regional Engineer. The appeal letter: (1) listed the names,
service date, occupation, and assignment of the Claimants;
(2) listed the names and title of the personnel who allegedly
did the disputed work as well as the number of hours each
worked; (3) cited the various Rules relied upon for support
of the claim; (4) described the claimed work by, in part,
stating "...commenced the stripping of inside wooden floor
which was anchored to cement slab and walls of a building
located at ...Sacramento, California," noting that the material
removed was permanently anchored and secured to the cement slab
foundation and consisted of 1"x4"x8' plywood sheeting which had
been cut to various dimensions and thereafter nailed to 2"x4"
boards covering an area approximately 54' wide x 60' long,
equivalent to 3,240 square feet; (5) stated that the Carrier's
Material Handling Foreman did not believe such work was that
of his department, but he was only following instruction; (6)
stated that "thereafter, Bridge and Building Sub-department
employees" (the Claimants) were called to complete the pro
ject; (7) quoted that part of Rule 1 - Scope on which it relied
as follows:
"These rules govern rates of pay, hours of service, and
working conditions of employes in all sub-departments of
the Maintenance of Way and Structures Department (not
including supervisor employes above the rank of foreman)
represented by the Brotherhood of Maintenance of Way
Employes, such as: foreman and assistant foremen of
bridges, buildings, tunnel, painter, construction concrete,
mason, water supply, plumbing, paving, fence gang, pile
driver, and all employes coming under the supervision of
such foreman."
Form 1 Award No. 27025
Page 3 Docket No. MW-26248
88-3-84-3-669
(d) December 15, 1983: The Carrier again rejected the claim.
It stated that because the initial claim of February 25, 1983,
did not specify any Rules that allegedly had been violated and
because the appeal letter of May 9, 1983, amended the claim, the
claim was not the same and, therefore, was improperly before
the Carrier, Moreover, it contended that:
"The removal of a scrap wooden floor by employes of the
Purchasing and Materials Department consisted of removal of
a wooden floor layed over a concrete slab and was not
anchored to cement as alleged. The removal of the floor was
not a job which necessitated any knowledge or finesse. The
floor was just ripped up by a fork lift and scrapped.
In support of our position, we were handed three written
statements dated May 10, May 24 and June 7, 1983, from
Purchasing and Materials Department Supervisors in support
of our contentions.
In addition, Rule 1, Scope Rule of the current agreement,
which simply lists categories and does not describe or
define work to be performed, is general in nature. See
Third Division, National Railroad Adjustment Board, Awards
12929, 12927, 12694, 10389, 11129, 15538, 19190, 19306,
19761, 20421, 21768 and 21898. Claimants were fully
employed at the time and dates indicated and therefore lost
no earnings as a result of the alleged violation."
The three statements obtained by the Carrier included one which
essentially asserted that the wooden floor was not anchored to
the concrete, that it was scrap lumber, and that it took approximately three (3) hours to remove. An
that the floor was stripped, the lumber scrapped and "there
had been been no work done to the concrete foundation." The
remaining statement was from the Foreman who allegedly had
stated that the work did not belong to his Department. This
person wrote that he did not make a statement to the Organization's B68 Supervisors and that his cre
on the "tearing up of flooring" for approximately four (4) hours.
(e) March 5, 1984: The Organization addressed the prior Awards the
Carrier had relied upon when it rejected its claim. It again
asserted its Scope Rule contentions and provided statements from
the Claimants that the floor was attached and anchored to the
concrete floor.
Form 1 Award No. 27025
Page 4 Docket No. MW-26248
88-3-84-3-669
(f) June 22, 1984: The Carrier rejected the claim, contending that
nothing new had been brought forward to warrant a change in the
decision rendered on December 15, 1983.
Pursuant to Section 3, First (j) of the Railway Labor Act, as
amended, notice was given to B.R.A.C. of this claim as a possible party of
interest. B.R.A.C. has filed a submission, claiming that the work at issue is
covered by its Scope Rule.
The Board has carefully reviewed the record. We find that the considerable exchange between the
and conflicting statements and that these are without sufficient evidence of
probative value to consider in reaching a decision of this claim. Accordingly, while we would prefer
dispute, we are constrained to dismiss the claim despite our reluctance to do
so.
A W A R D
Claim dismissed.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest:
Nancy J.
f
- Executive Secretary
Dated at Chicago, Illinois, this 25th day of April 1988.