Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 27112
THIRD DIVISION Docket No. MW-26432
88-3-85-3-159
The Third Division consisted of the regular members and in
addition Referee Gil Vernon when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(The Chesapeake and Ohio Railway Company
(Southern Region)
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when it failed and refused to
assign a B&B Foreman to work with an outside concern engaged in dismantling
and/or removing the Roundhouse at Peach Creek, West Virginia beginning
November 2, 1983 (System File C-TC-2003/MG-4342).
(2) Because of the aforesaid violation, the senior cut-back B&B
Foreman or the senior B&B Mechanic entitled to the work shall be allowed four
hundred eighty (480) hours of pay at the B&B Foreman's rate."
FINDINGS:
The Third Division of the Adjustment Board upon the whole record
and all the evidence, finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employes within the meaning of the
Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the
dispute involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
On October 21, 1983, the Carrier sent the following notice to the
General Chairman:
"This is to advise you of the Carrier's
intent to contract with Crabtree Demolition
Company to furnish labor and equipment for the
demolition and removal of all debris from the
former Roundhouse at Peach Creek, West Virginia.
Carrier property is to be left in satisfactory
level condition.
Form 1
Page 2
Award
No.
27112
Docket
No.
MW-26432
88-3-85-3-159
It is estimated that this project will take
60 man-days to accomplish. Work is scheduled to
commence November 1, 1983 and to be completed
November 20, L983.
Carrier has iii alternative but to contract
this work as Company forces and equipment are
actively engaged is other equally important
program work and cannot be assigned to do this
work in a timely manner without impeding progress of the established program. Also, Carrier
has no suitable area to dispose of the resulting
debris.
There will be no furloughed B&B Mechanics
on the seniority territory involved during the
period the contractor is working on the property."
On October 27, 1983, the General Chairman took exception with the
portion of the notice indicating that there were no furloughed B&B mechanics
on the seniority roster and he requested, pursuant to Rule 83(b), that a B&B
Foreman be assigned to assist the contractor.
A "B&B" Foreman was not assigned and on November 23, 1983, the
following claim was submitted:
"This office is in receipt of a time claim from
Irvin Wiley, Clifford Hanshaw, Kenneth Brown,
Walter P. Stub, David T. Farnsworth and Ruben E.
Adkins. This claim states that beginning
November 2, 1983 a contractor began demolition
of the Round House at Peach Creek, West
Virginia. Mr. Comiskey's letter of intent to
contract dated October 21, 1983 stated that the
contractor would consume sixty (60) man-days to
accomplish the work. The Carrier did not place
a B&B Foreman Inspector with this contractor and
therefore they are in violation of the rules as
stated above.
I request that the senior cut back B&B Foreman
or the Senior B&B Mechanic who would be entitled
to this work be paid sixty (60) days or four
hundred eighty (480) hours at his respective
rate as the Carrier did not comply with the
Agreement, specifically Rule 83.
Please investigate and advise."
The claim was declined and ultimately appealed to the Board for resolution.
Form 1 Award No. 27112
Page 3 Docket No. MW-26432
88-3-85-3-159
This claim centers around the interpretation and application of Rules
66(c), 83(b) and (c). They are quoted below:
"RULE 66--CLASSIFICATION
* * *
(c) In carrying out the principles of Paragraph (a), bridge and structures forces will
perform the work to which they are entitled
under the rules of this agreement in connection
with the construction, maintenance, and/or removal of bridges, tunnels, culverts, piers,
wharves, turntables, scales, platforms, walks,
right of way fences, signs and similar buildings
or structures ***."
The contracting out of scope covered work is controlled by Rule 83(b)
and (c), which reads:
"(b) It is understood and agreed that
maintenance work coming under the provisions of
this agreement and which has heretofore customarily been performed by employees of the
railway company, will not be let to contract if
the railway company has available the necessary
employees to do the work at the time the project
is started, or can secure the necessary employees for doing the work by recalling cut-off
employees holding seniority under this agreement. Cut-off employees on a seniority district
who will go to other territories to prevent
having to contract work hereunder will be considered upon notification in writing to the
Manager-Engineering or other corresponding
officer of the territory on which the particular
employee holds seniority by that employee. This
shall not preclude letting to contract the
building of new lines, sidings, and yards; the
extension of existing lines, sidings, and yards;
the construction of new buildings or other
facilities which has customarily been handled by
contract in the past; or the doing of maintenance work requiring equipment which the railway
company does not have or skill and tools not
possessed by workmen covered by this agreement;
on the other hand, the railway company will
Form 1 Award No. 27112
Page 4 Docket No. MW-26432
88-3-85-3-159
continue its policy of doing construction work
with employees covered by this agreement when
conditions permit. Where maintenance work
coming under the provisions of this agreement
which has customarily been performed by employees of the railway company is let to contract,
the railway company will place an extra force
foreman in charge of the work if the contracted
work is roadway or track work. If the contracted work is bridges and structures work, a
B&B foreman will be assigned with the contract
force if the job is such as would justify
assignment of a foreman if the railway company
were doing the work with its own forces. If the
contracted bridges and structures work is such
that a carpenter would be used if the work were
being done with railway company forces, a carpenter will be assigned. If painting work is
contracted, a foreman will be used.
(c) See Letter of Agreement of October 24,
1957 in Appendix B."
There is much which is clear about these Rules. First, under Rule 66(c)
employees "will perform" work to which the Rules entitle them in connection
with among other things "removal" of buildings. Obviously this would encompass demolition as involve
Rule 83(b) and (c) entitles the employees to perform work which has
customarily been performed by them. When, at the time the project is started,
there are available employees (active or furloughed), the Rule states clearly
and strongly, with certain exceptions, that contractors will not be used under
such circumstances. One of the exceptions relevant in this case is where the
company does not have the skills or tools available. The last part of Rule
83(b) indicates where contracts are let for work customarily performed by the
employees, a foreman of some type, depending on the type of work will be
assigned.
Thus, there are a number of relevant questions which must be answered
in sequence. The first relevant question is whether the work of demolishing
buildings has customarily been performed by the employees. The Board is
satisfied on the basis of this record that they have.
The next relevant question is whether the Carrier had employees available at the time to perform
that it did not and it is noted there was no particular exception taken to
this by the Organization since they did not request that B&B forces demolish
the building in question. Their response was limited to requesting that a B&B
Foreman be assigned.
Form 1 Award No. 27112
Page 5 Docket No. MW-26432
88-3-85-3-159
Given that the work has been customarily performed by Carrier forces
and that contracting out of the demolition was necessary due to lack of
personnel availability, the last relevant question is whether the Carrier has
fulfilled its obligation under the last portion of Rule 83(b) to assign a
foreman. This obligation is a clear requirement if the Carrier contracts out,
for legitimate reasons, work customarily performed by the employees.
The Carrier makes at least one erroneous argument in defending its
failure to assign a foreman. For instance, it suggests it is not required to
since the Carrier has customarily contracted work such as that herein without
the assigning of a foreman. First of all, there is no evidence of such a
practice, in fact the evidence is to the contrary. Moreover, even if there
was, the language is clear and plainly stipulates that when an outside contractor is required to per
when the contracted work is maintenance work that has been traditionally
performed by those employees covered by the Agreement and where a foreman
would have been assigned had the work been done by Carrier forces. Thus the
fact the Carrier may not have complied with this requirement in the past is
irrelevant.
The Carrier also argues that all the Claimants were fully employed as
foremen or B&B mechanics. However, this does not mean that they weren't available. Certai
not available. However, the burden is on the Carrier to demonstrate this
unavailability. Just because there was full employment and just because the
Carrier couldn't free up enough people from other projects to perform the
entire demolition job doesn't mean necessarily it was impossible or would pose
significant impracticalities to release a B&B mechanic, qualified as a foreman, to be upgraded f
In view of the fact we are not convinced that someone could not be
made available the senior cut back B&B Foreman is entitled to be compensated
for the differences between his earnings and the foreman rate for only the
number of hours the contractor's crew was on the property, not the aggregate
hours extended on this project by contractors.
A W A R D
Claim sustained in accordance with the Findings.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest.
Nancy J r - Executive Secretary
Dated at Chicago, Illinois, this 17th day of May 1988.