Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 27175
THIRD DIVISION Docket No. MW-26593
88-3-85-3-514
The Third Division consisted of the regular members and in
addition Referee Robert W. McAllister when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Southern Pacific Transportation Company (Eastern Lines)
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when it assigned outside
forces to perform Maintenance of Way and Structures Department work in
connection with a derailment on the Fort Worth Branch between Mile Post 32 and
Mile Post 34 on September 24, 25 and 26, 1984 (System File MW-84-139/420-66-A).
(2) The Carrier also violated Article 36 of the Agreement when it
did not give the General Chairman advance notice of its intention to contract
said work.
(3) As a consequence of the aforesaid violations, Machine Operator
R. F. Berckenhoff shall be allowed sixteen (16) hours of pay at his straight
time rate and fourteen (14) hours of pay at his time and one-half rate."
FINDINGS:
The Third Division of the Adjustment Board upon the whole record and
all the evidence, finds that:
The carrier or carriers and the employe or employees involved in this
dispute are respectively carrier and employes within the meaning of the
Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the
dispute involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
On September 24, 1984, there was a derailment on the Carrier's Dallas
Division. The Carrier used an outside contractor to furnish a tractor dozer
and operator to assist with the cleanup. The contractor worked sixteen (16)
straight time hours and fourteen (14) overtime at the derailment site. The
Organization argues the performance of tractor dozer work accrues to employees
holding seniority in the Roadway Machine Department, and assignment of the
work to an outside contractor defeats the intent of the controlling Agreement.
Form 1 Award No. 27175
Page 2 Docket No. MW-26593
88-3-85-3-514
The Carrier insists the Claimant was told it could not move the dozer
the Claimant was assigned to because it was not available. The Carrier contends the Claimant said th
work. The on-the-property correspondence indicates the Organization asserted
the Claimant was not offered the derailment work, but if so instructed, he
could not refuse. Notwithstanding, on December 19, 1984, the Claimant wrote
the following letter:
"Reference to your letter dated Nov. 28, 1984. The
foreman came to the trailer and asked me to go help
him run some kind of line. He did not ask me to
run another dozer. The foreman said that they
would have someone else there.
I told him that I didn't want to work if they
didn't need my dozer. I didn't tell him, but I had
a bad tooth ache all that and didn't want to work
unless they needed me to run my machine."
The Board finds the unrebutted statement of the Claimant establishes
that he made himself unavailable. The Organization focuses upon the Claimant's statement he was not
that, once the Claimant said he did not want to work, the foreman had no
obligation to pursue the matter further. He had a right to accept the
Claimant's unavailability at face value. It defies logic to argue that the
foreman should have pursued the issue and ask the Claimant to work on another
dozer.
The Board concludes the Organization has failed to meet its burden of
proof and has not supported its claim with relevant and probative evidence as
opposed to assertions.
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest:
Nancy J. v -Executive Secretary
Dated at Chicago, Illinois, this 23rd day of June 1988.