Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 27186
THIRD DIVISION Docket No. MW-26633
88-3-85-3-380
The Third Division consisted of the regular members and in
addition Referee George S. Roukis when award was rendered.

(Brotherhood of Maintenance of Way Employes PARTIES TO DISPUTE:


STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:

(1) The Carrier violated the Agreement when it assigned ditching work in the 'big cut' on the Cane Creek Branch, beginning December 19, 1983, to outside forces (System File D-61-83/MW-8-84).

(2) Director of Personnel M. M. Kanderis failed to disallow the claim (appealed to him under date of June 13, 1984) as contractually stipulated within subsections (
(3) As a consequence of either or both (1) and/or (2) above, Messrs. D. L. Drake, T. C. Meitzler, F. D. Ward, L. D. Moore, 0. Ratliff and B. Murray shall each



FINDINGS:

The Third Division of the Adjustment Board upon the whole record and all the evidence, finds that:

The carrier or carriers and the employe or employees involved in this dispute are respectively carrier and employes within the meaning of the Railway Labor Act as approved June 21, 1934.

This Division of the Adjustment Board has jurisdiction over the dispute involved herein.



Claimants hold seniority as equipment operators in the Road Equipment subdepartment of the Maintenance of Way and Structures Department. According to the Organization's petition, beginning on December 19, 1983, Carrier assigned outside forces to perform ditching work in the "big cut" on the Cane Creek Branch near Moab, Utah. The work consisted of removing rock and debris from the ditches along the right-of-way in the cut. In the performance of this work, the outside contractor used one (1) cat backhoe, two (2) dumpaters, one (1) D-3 cut, one (1) motor grader and one (1) D-8 dozer. The Organization contended that work of this character, including work at this same location,
Form 1 Award No. 27186
Page 2 Docket No. MW-26633
88-3-85-3-380

has traditionally and customarily been performed by Carrier's Road Equipment subdepartment forces and consequently, Rules 1, 2, 3, and 4 of the controlling Agreement were violated when said work was performed by these outside forces. It set forth arguments and data to support its position that said work accrued to BMWE forces. Also, it charged that Carrier failed to comply with the explicit terms of the Letter belatedly notified the General Chairman of its intent to contract out said work. On this point, it asserted that Carrier's notice was singularly untimely, since it didn't comp that while the notice was dated December 14, 1983 and received by the General Chairman, Carrier actually commenced the work on December 19, 1983. It further pointed out that Carr Organization that said work would start in approximately two (2) or three (3) weeks and, then begin this work four (4) days after the General Chairman was notified. It cited numerous Third Division Awards on the obligatory and procedural requirements of a 1968 Agreement. Furthermore, and in response to Carrier's arguments that scaling and trimming canyon walls was work not encompassed within the controlling Agreement, the Org breached the controlling Agreement. In effect, said work was covered protected work. In addition, th procedural violation, when it failed to respond in timely fashion to the Organization's appeals letter dated June 13, 1984.

In rebuttal and with respect to the procedural question raised by the Organization, Carrier asserted that the Director of Personnel and Labor Relations denied the Organiz 1984, when said Carrier official mailed his denial letter to the Organization. In this connection, it pointed out that the parties have "long" relied upon the U. S. Postal Service as a means to exchange correspondence without the use of certified or registered mail and implicitly observed that this practice worked to the mutual satisfaction of the parties.

As to the substantive merits of the claim, Carrier denied that maintenance ditching was performe the outside contractor involved the scaling and trimming of the vertical walls of the "big cut" on Cane Creek Branch which included cleaning up the "big cut" after the scaling and trimming. It also argued that Claimants were unqualified to operate the machin fact, unavailable for this work. It took exception to the Organization's contention that it (Carrier) failed to comply with the Letter of Agreement, dated December 11, 1981, (Article IV - Contracting out) arguing that the Organization's December 19, 1983, letter requesting a conference was not received until January 23, 1984. It acknowledged that a conference was held on January 23, 1984, but asserted that such delay was attributed to the Organization's failur Form 1 Award No. 27186
Page 3 Docket No. MW-26633
88-3-85-3-380

In considering this case, the Board rejects the organization's contention that Carrier failed to respond in timely fashion to the General Chairman's June 13, 1984, Letter of Appeal. From the record and in the absence of evidence that the parties traditional reliance upon the U. S. Postal Service to exchange correspondence precipitated conflict or delays, we have to assume a good faith commitment to this normative exchange process. The same is apropos the Organization's December 15, 1983 response letter to Carrier's December 14, 1983 notification to use outside forces. We find no reason predicated upon the parties past history, as established by the record, to conclude that either party was acting in bad faith or under cover of rationalized argument.

On the other hand, and consistent with the intent of the Letter of Agreement dated December 11, 1981 (Article IV - Contracting out) we find Carrier's notification of outside forces on December 9, 1983 somewhat premature and at variance with 11, 1981 Letter of Agreement's implicit spirit, we find that Carrier violated the understanding that it was required to tender notification as far in advance of the date of the c than in fifteen (15) days prior thereto. Beginning the disputed work on December 19, 1983 was not in accordance with this requirement. Conversely, we find no plausible grounds, given our decisional holdings in past cases to award compensation, since all claimants, except one, who was on vacation, were actively employed at the time the work was performed. See Third Division Awards 23402, 18305, 19155, 19399, 19948.






                          By Order of Third Division


Attest:

      Nancy J. r - Executive Secretary


Dated at Chicago, Illinois, this 23rd day of June 1988.