Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 27585
THIRD DIVISION Docket No. :MW-26767
88-3-85-3-516
The Third Division consisted of the regular members and in
addition Referee Edwin H. Benn when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(The Chesapeake and Ohio Railway Company (Southern Railway)
STATEMENT OF CLAIM: "Claim of System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when, without a conference
having been held as required by the October 24, 1957 Letter of Agreement [Rule
84(c)], it assigned outside forces to perform ditching work at Kenova and
Ashland June 25, 1984 through August, 1984 (System File C-TC-2415/MG-4888).
(2) Because of the aforesaid violation, cut back Equipment Operator
L. W. Dillon shall be allowed the difference between what he should have been
paid at the Class A equipment operator's rate and what he was paid at the Trackman's rate during the
FINDINGS:
The Third Division of the Adjustment Board upon the whole record and
all the evidence, finds that:
The carrier or carriers and the employe or employees involved in this
dispute are respectively carrier and employes within the meaning of the
Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the
dispute involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
Claimant is an Equipment Operator who, at the time this dispute arose,
was in a cutback status as a Trackman. On June 25, 1984, the Carrier contracted
with Asplundh Corporation to perform ditching and road bed work at its Kenova and
Ashland Yards. The work performed by the contractor consisted of ditching work
at the yards and was performed through use of a backhoe. The work continued for
approximately two months. The Carrier concedes that the Organization was not
given advance notice of its intent to contract out the work contending that the
failure to do so was through inadvertence. However, on the dates in question,
the Carrier upgraded the senior cut-back Operator on the Huntington Division
working as a Trackman, A. Humphrey, to the Operator's rate. Claimant seeks the
difference between the Trackman's and Equipment Operator's Class A rates for the
time period that the contractor performed services.
Initially, the Carrier's argument that the Organization has presented
a different claim to this Board than it presented on the property thus requiring
dismissal of the Claim must be rejected. Our review of the record does show in
accord with the Carrier's position that the on-property handling specifically
focused upon the lack of notice of contracting out the work at issue, whereas the
Claim before this Board makes reference to the lack of a conference. Further,
Form 1 Award No. 27585
Page 2 Docket No. MW-26767
88-3-85-3-516
our examination of the record shows that there is no substantial variance between
the dispute presented on the property and that which is now before this Board
for decision. Whether the Claim asserts the lack of a conference or the similar
lack of notice will not ultimately affect the outcome of this matter on the facts
presented. Since the basic claim set forth on the property was followed consistently through the pro
See Third Division Awards 26436, 26351, 26210, 25967, 24399.
With respect to the merits, Rule 83(b) states in pertinent part:
"It is understood and agreed that maintenance work coming
under the provisions of this agreement and which has heretofore
customarily been performed by employees of the railway company,
will not be let to contract if the railway company has available the necessary employees to do the w
project is started, or can secure the necessary employees for
doing the work by recalling cut-off employees holding seniority under this agreement."
The letter of agreement of October 24, 1957 found in Appendix B of the
Agreement further addresses the issue:
"...
it has been the policy of this company to perform
all maintenance of way work covered by the Maintenance of
Way Agreement with maintenance of way forces except where
special equipment was needed, special skills were required,
patented processes were used, or when we did not have sufficient qualified forces to perform the wor
where it has been necessary to deviate from this practice in
contracting such work, the Railway Company has discussed the
matter with you as General Chairman before letting any such
work contract.
We expect to continue this practice in the future
...."
The Carrier does not contest that it was required to notify the Organization of its intent to co
did not do so. Therefore, the above-quoted provisions of the Agreement have been
violated.
However, the Carrier seeks to escape the imposition of monetary relief
with the argument that the work involved the use of one operator employed by the
contractor and during the time it contracted out the work, the senior cut-back
Operator on the property was upgraded. We find that position well-taken in this
case. In light of the fact that the senior cut-back Operator was upgraded from
his cut-back Trackman's status during the time that the contractor performed the
work, we cannot say that monetary relief is appropriate in this case. Since the
Claim specifically only seeks relief for the differential in the lost Operator's
wages, the lost work opportunity was remedied by the upgrading of the senior cutback Operator. We vi
Form 1 Award No. 27585
Page 3 Docket No. MW-26767
88-3-85-3-516
remedies have been formulated. For example, in Third Division Award 25967, monetary relief was g
of the rules involved in this case. However, in that case, the Carrier did not
follow the notification requirements and further did not upgrade affected employees as it did herein
Carrier's violation thereby making monetary relief necessary. Similarly, in Third
Division Awards 26351 and 26210 compensation was awarded as claimed to furloughed
employees where non-furloughed employees were upgraded or the upgrade did not
cover the entire period that the work was performed by the outside contractor.
Here, the senior cut-back employee was upgraded for the time that the contractor
performed the work and, most significantly, there is no claim that furloughed
employees are entitled to relief. The only remedy sought is the differential
for Claimant who, admittedly, is not the senior cut-back employee.
But the Organization nevertheless seeks the differential payment to
Claimant. Two further reasons exist to reject that position. First, to sustain
the Organization's argument will result in the Carrier paying two employees for
the loss of one work opportunity and, as such, will amount to an undue penalty
where the Carrier has already complied with a make whole remedy by appropriately
paying the differential to the senior affected cut-back employee Humphrey. Second
(and putting aside the question of whether this issue was raised on the property),
Claimant's hearsay contention that Humphrey told him that "he had no intentions of
bidding on the operators position and therefore did not claim back pay" does not
defeat the fact that this record shows without factual contradiction that Humphrey
was compensated for the differential now also sought by Claimant. While the Organization is correct
relief in order to receive the same. There has been a clear demonstration that
the Agreement was violated. However, in light of the compensation given to the
senior cut-back Operator and the specific relief sought in the Claim, there has
been no demonstration that Claimant is entitled to monetary relief.
A W A R D
Claim sustained in accordance with the Findings.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest:
Z~o
.r - -
Nancy J. - Executive Secretary
Dated at Chicago,/Illinois, this 27th day of October 1988.