Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 27692
THIRD DIVISION Docket No. MW-26954
89-3-85-3-727
The Third Division consisted of the regular members and in
addition Referee Edwin H. Benn when award was rendered.

(Brotherhood of Maintenance of Way Employes PARTIES TO DISPUTE:


STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:

(1) The three (3) claims* as presented by Trackman J. Chapman on December 13, 1983 to Division Engineer D. S. Cargill shall be allowed as presented because the claims were not disallowed by Division Engineer D. S. Cargill in accordance with Rule 26(a) (System Docket CR-1171).

(2) The three (3) claims* as presented by Trackman J. Chapman on December 13, 1983 to Division Engineer D. S. Cargill shall be allowed as presented because the claims were not disallowed by Manager-Labor Relations J. A. Rice (appealed to him on May 18, 1984) in accordance with Rule 26(b).



FINDINGS:

The Third Division of the Adjustment Board upon the whole record and all the evidence, finds that:

The carrier or carriers and the employe or employes involved in this dispute are respectively carrier and employes within the meaning of the Railway Labor Act as approved June 21, 1934.

This Division of the Adjustment Board has jurisdiction over the dispute involved herein.



By three separate claims dated December 13, 1983, completed on preprinted claim forms, Claimant were performing work as a trackman, bus driver and/or foreman on specified dates in October through December, 1983, at different specific locations in Indiana. By letter dated March 22, 1984, the Division Engineer responded that:




Form 1 Award No. 27692
page 2 Docket No. MW-26954
89-3-85-3-727















It is undisputed that by not responding to the December 13, 1983 claims until
March 22, 1984, the Carrier did not "render a decision within sixty (60) days
from the date same is filed" as required by Rule 26(a). The result is dic
tated by the negotiated language of the rule. "When not so notified, _the
claim will be allowed." [Emphasis added].

The Carrier argues, however, that the claims were vague and indefinite and hence invalid and voi required. We disagree. The underlying premise for such an argument is that the claims, as written, were vague and indefinite. Our review of the three claims shows that premise to be faulty in that the claims are quite specific. The three claims all identify Claimant as the individual bringing the claims, the fact that they were time claims, the names of the individuals alleged to have improperly performed the claimed work, the specific locations where the alleged contract violations took place, the exact dates of the alleged violations, the specific type
Thus, by operation of the Agreement and because the claims involved herein are not of a continuing nature, the Carrier's failure to respond within the 60 day period automatically requires that the claims be allowed. In this case, any other interpretation would render the negotiated language found in Rule 26(a) meaningless. See Third Division Award 25309 wherein a time claim was sustained under similar language where the Carrier failed to timely deny the initial claim notwithstanding a rejected allegation that the claim was vague and indefinite.

The line of awards cited to us by the Carrier wherein untimely responses to claims did not resul result in this case. For example, Third Division Award 19766 concerned a damage claim to the employee's automobile which the Board viewed in the nature of a tort and not involving the terms of the parties' agreement. Second Division Award 9321 concerned a safety claim that the Board interpreted as being outside of its jurisdiction. Fourth Division Award 4590 and Third
Form 1 Award No. 27692
Page 3 Docket No. MW-26954
89-3-85-3-727

Division Award 25856 involved duplicate claims that were earlier adjudicated and dismissed under the principle of res udicata. Those awards are factually different from the present case. However, we do find relevant the observation made to the Carrier in Fourth Division Award 4590, supra:





The parties have expended much effort arguing about what occurred after the Carrier untimely denied the claims. Specifically, the parties' arguments address the ramifications of the change of address of the Organization's Vice Chairman and Carrier's August 30, 1984, letter (asserted by the Carrier to have been mailed to his former address) until October 10, 1984. Because of that late receipt, both parties argue each other's further handling of the matter to be untimely under other provisions of Rule 26. We need not address those arguments. Rules 26(b) and (c) both state that in order for the time limit provisions in those rules to operate, the claim or grievance must be "...denied in accordance with [the preceding] ... . Under Rule 26(a), when the Carrier fails to timely respond to claims, as a matter of contract, the claims "... will be allowed." Therefore, in this case, since the claims were "allowed" by operation of Rule 26(a), any denials that occurred after March 22, 1984, under Rules 26(b) or (c) were not "...in accord with [the preceding] paragraph." At the point the Carrier failed to initially deny the claims in this case, the matter was over. In this case, what happened thereafter is immaterial.

Because of our holding, the question presented in paragraph (2) of the claim need not be addressed.



        Claim sustained.


                          NATIONAL RAILROAD ADJUSTMENT BOARD

                          By Order of Third Division


Attest:
        Nancy J ver·- Executive Secretary


Dated at Chicago, Illinois, this 2nd day of February 1989.