NATIONAL RAILROAD ADJUSTMENT BOARD
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE: (
(National Railroad Passenger Corporation
(Amtrak) - Northeast Corridor
STATEMENT OF CLAIM: As shown in Docket No. MW-28127 and not repeated
herein.
FINDINGS: The Third Division of the Adjustment Board finds:
That the dispute was certified to the Third Division of the
Adjustment Board ex parte by the petitioning party; and
Under date of January 19, 1989, the petitioning party addressed a
formal communication to the Executive Secretary of the Third Division
requesting withdrawal of this case from further consideration by the Division,
which request is hereby granted.
A W A R D
Claim withdrawn.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest:
6Z
cy J. 8 r -.Executive Secretary
Dated at Chicago, Illinois, this 2nd day of February 1989.