Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 27776
THIRD DIVISION Docket No. MW-27198
89-3-86-3-557
The Third Division consisted of the regular members and in
addition Referee Marty E. Zusman when award was rendered.
(Brotherhood of Maintenance of Way Employee
PARTIES TO DISPUTE:
(Soo Line Railroad Company
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when it disqualified Mr. Kurt
Weber as a tractor operator on June 12, 1985 without just cause (System File
6(d) [13-6(b)]/G-97-5-A-1).
(2) The Carrier further violated the Agreement when it denied Claimant Kurt Weber the right of h
(3) As a consequence of either (1) and/or (2) above, Claimant Kurt
Weber shall be returned to his position as tractor operator with seniority as
such unimpaired and he shall be compensated for all compensation loss suffered
by him."
FINDINGS:
The Third Division of the Adjustment Board upon the whole record
and all the evidence, finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employes within the meaning of the
Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the
dispute involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
The record which this Board reviewed does not contain sufficient probative evidence that it was
by Section 3, First (i) of the Railway Labor Act, as amended.
A review of the correspondence to determine the merits of the Organization's position must be pr
before this Board, does not sufficiently establish that a conference was held
on the property.
Form 1 Award No. 27776
Page 2 Docket No. MW-27198
89-3-86-3-557
While we do not desire to decide on procedural grounds, we have no
choice in the instant Claim. There is a lack of evidence that this case was
conferenced on the property and it must therefore be dismissed by this Board
without considering its merits (Third Division Awards 26867, 26853, 23239).
A W A R D
Claim dismissed.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest:
Nancy J r - Executive Secretary
Dated at Chicago, Illinois, this 2nd day of March 1989.