Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 28012
THIRD DIVISION Docket No. MW-27186
89-3-86-3-255
The Third Division consisted of the regular members and in
addition Referee Robert W. Me-Allister when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Norfolk and Western Railway Company (former
( Illinois Terminal Railroad Company
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when it assigned outside
forces to install a culvert at Mile Post 143.32 in the vicinity of Renick,
Missouri beginning on or about December 4, 1984 (System File MW-MOB-85-16).
(2)
AS
a consequence of the aforesaid violation, furloughed B&B Employes, R. D. Andrews, M. D. Rile
G. A. Hammons, R. E. Maddox, J. W. Turner, P. Swinford and C. J. Torri shall
each be allowed eight (8) hours of pay, at their respective rates, for each
day on which the outside concern performed the work referred to in Part (1)
hereof and furloughed Backhoe Operator G. J. Arnold shall be allowed fifty-six
(56) hours of pay at the backhoe operator's rate."
FINDINGS:
The Third Division of the Adjustment Board upon the whole record and
all the evidence, finds that:
The carrier or carriers and the employe or employes involved In this
dispute are respectively carrier and employes within the meaning of the
Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the
dispute involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
By letter dated August 15, 1984, the Carrier served notice upon the
Organization that it intended to contract out the work of replacing a stone
box culvert at Renick, Missouri. The Carrier justified its decision by asserting that it did "not po
equipment to satisfactorily accomplish a project of this nature." Following a
conference with the General Chairman to discuss the notice, the Carrier reiterated it did not have t
efficient manner. Over the objection of the organization, the work was performed by a contractor, co
Form i Award No. 28012
Page 2 Docket No. MW-27186
89-3-86-3-255
Article IV of the May 17, 1968, National Agreement and the December
11, 1981, Letter of Agreement between the Organization and the National Carriers' Conference Committ
advance notice of its intention to contract out work within the scope of the
Agreement. This notice must state the Carrier's reasons for contracting out
the work. The intent of the Agreements was to allow the parties an opportunity to explore the possib
available to perform the work and that the Carrier could have leased the large
tractor type backhoe necessary for this project.
The Carrier first asserts it was privileged to contract out the work
because it is work which is not exclusively within the scope of the Agreement.
This argument is based upon its position that the scope rule is general in
nature and the work has been contracted out before. Under these circumstances, the Organization woul
to perform the work. In response, the Organization noted the exclusivity argument was advanced by th
record supports the Organization's objection. Throughout the handling of this
dispute on the property, the Carrier supported its decision solely upon its
position that it lacked the manpower and equipment. The Carrier cannot now be
heard to argue it could have subcontracted the work even if it had the employees and machines.
The Carrier's defense in this case must be based upon its showing
that the project required special equipment and/or employees with special
skills. With respect to the equipment necessary for this job, it appears from
the record that the only machine used by the contractor was a large backhoe.
The Organization asserts the employees have worked with such equipment before
and that it could be readily leased if the Carrier did not have one. We do
not equate the term "special equipment" with any machine which the Carrier
does not own. Rather, the term implies there is something relatively unique
about the machine so that it could not be readily obtained by the Carrier. In
the December 11, 1981 Letter of Agreement, the Carriers undertook a commitment
to increase the procurement of rental equipment to be operated by Carrier employees as a way of redu
have been readily available to the Carrier.
Similarly, there is no evidence in the record to show that the contractor used employees with sp
the plans for this project had been prepared by the Carrier's Maintenance of
Way 6 Structures Department. The Carrier acknowledges its employees have installed culverts, albeit
established it did not have the skilled manpower for this work.
For the reasons stated above, we must find that the Carrier improperly contracted out the work.
were fully employed during the entire time the contractor was working. This
Form 1 Award No. 28012
Page 3 Docket No. MW-27186
89-3-86-3-255
is contrary to the Organization's position that Claimants were furloughed at
the same time the work was begun. There is no documentation in the record to
enable this Board to reach a conclusion one way or the other as to the availability of the Claimants
each have records showing the time worked by Claimants. Accordingly we direct
the Claim be sustained only with respect to those furloughed employees who
actually suffered wage loss as a result of unemployment during the time period
the work was performed by the contractor.
A W A R D
Claim sustained in accordance with the Findings.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest: ,
Nancy J. er - Executive Secretary
Dated at Chicago, Illinois, this 31st day of July 1989.
CARRIER MEMBERS' DISSENT
TO
AWARD 28012, DOCKET MW-27186
(Referee Robert W. McAllister)
The Majority in its Findings, incorrectly sustained the Organization's
claim to work Carrier subcontracted after giving notice and discussing the
proposed subcontracting with the Organization pursuant to requirements of the
May 16, 1968 National Agreement. In so doing, the Majority ignored a legion
of Awards that require the proponent of a claim to support the alleged rule
violation with substantial evidence; the Majority erroneously accepted the
Organization's unsupported allegations as facts.
The Majority rejected, as new argument, Carrier's position that the
claimed work was not reserved to the Organization. Contrary to that finding,
Carrier's denial of the initial claim stressed that the work involved the
"boring and jacking method" and "the work performed [by the contractor] bears
no similarity" to work previously performed by company forces. The
Organization never introduced any evidence to the contrary showing the work
was "within the scope of the applicable schedule agreement." Despite the
lack of evidence, the Majority sustained the claim. Since there was no
evidence to show the work was reserved to the Organization, that finding was
without basis and is erroneous.
The Majority also found that "it appears from the record that the only
machine used by the contractor was a large backhoe" and that "there is no
evidence in the record to show that the contractor used employees with
special skills not had by Claimants." Neither point supports the sustaining
Award.
The project consisted of replacing a stone box culvert with a 10 foot
diameter steel plate culvert; during the handling on the property Carrier
CMs' Dissent to Award 28012
Page 2
repeatedly stated, without contradiction, this installation was accomplished
by the boring and jacking method (to avoid disturbing the roadbed), not by
the cut and cover method. While a large backhoe was used for adjacent
excavation work, it is elementary that such a piece of equipment alone is not
sufficient to do the pipe installation by the method utilized. Therefore,
the Board's conclusion that obtaining a backhoe would have enabled Carrier
forces to perform the work is patently erroneous.
Finally, with regard to the "skilled employee" issue, the Organization
presented absolutely no evidence to prove that Carrier employees ever
performed work of this nature. It was the burden of the organization to
prove that point, and since it did not, the Majority's conclusion improperly
represents the practice on the property.
For the reasons stated, Award 28012 is erroneous and we dissent.
1
·
M. W. Fin
Aa&eA
gerhut
R. L. Hicks
M. C. Lesnik
P. V. Varga