Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 28044
THIRD DIVISION Docket No. MW-26847
89-3-85-3-602
The Third Division consisted of the regular members and in
addition Referee Elliott H. Goldstein when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Norfolk and Western Railway Company
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when it assigned outside
forces to construct a right-of-way fence between Mile Post 109.6 and Mile Post
110.8 on the Connelsville District from August 28, 1984 to September 10, 1984
(Carrier's File MW-ROK-84-11).
(2) The Carrier also violated Article IV of the May 17, 1968 National
Agreement when it did not give the General Chairman advance written notice of
its intention to contract said work.
(3) B&B Foreman R. Cummings and Carpenters H. Hoeflich, R. Federer,
G. Whitaker, J. Kopacko and C. DeBaker shall each be allowed eighty (80) hours
of pay at their respective straight time rates because of the aforesaid
violations."
FINDINGS:
The Third Division of the Adjustment Board upon the whole record and
all the evidence, finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employes within the meaning of the
Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the
dispute involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
Claimants established and hold seniority in their respective classes
in the Bridge and Building Sub-Department of the Maintenance of Way and Structures Department.
Beginning on August 28, 1984, and continuing through September 10,
1984, Carrier assigned outside forces to construct a right-of-way fence between Mile Post 109.6 and
Hopedal and Pittsburgh Junction, Ohio. There is no dispute that Carrier failed to notify the General
construction work in accordance with Article IV of the Agreement, which provides:
Form 1 Award No. 28044
Page 2 Docket No. MW-26847
89-3-85-3-602
"ARTICLE IV - CONTRACTING OUT
In the event a carrier plans to contract out work
within the scope of the applicable schedule agree
ment, the carrier shall notify the General Chairman
of the organization involved in writing as far in
advance of the date of the contracting transacti_on
as is practicable and in any event not less than 15
days prior thereto.
If the General Chairman, or his representative re-
quests a meeting to discuss matters relating to the
said contracting transaction the designated repre-
sentative of the carrier shall promptly meet with
him for that purpose. Said carrier and organization
representatives shall make a good faith attempt to
reach an understanding concerning said contracting,
but if no understanding is reached the carrier may
nevertheless proceed with said contracting, and the
organization may file and progress claims in con
nection therewith.
Nothing in this Article IV shall affect the exist
ing rights of either party in connection with con
tracting out. Its purpose is to require the carrier
to give advance notice and if requested to meet with
the General Chairman or his representative to discuss
and if possible reach an understanding in connection
therewith.
Existing rules with respect to contracting out on
individual properties may be retained in their en
tirety in lieu of this rule by an organization giv
ing written notice to the carrier involved at any
time within 90 days after the date of this agreement."
Carrier maintains that it is obligated by law in the State of Ohio
to have fencing along property lines where livestock is maintained on the
adjacent property. Carrier argues that it needed to take immediate action,
and after canvassing its forces, determined that no forces were available to
construct the fence within the time frame allowed. The Organization argues
that even if that was the case, Carrier was not relieved of its obligations
under Article IV.
We agree with the Organization. Carrier has an obligation to assert
good faith efforts to reduce the incidence of subcontractng and increase the
use of maintenance of way forces. Carrier failed to do so in this case. The
fact that Carrier has not met its burden in this regard is a fundamental and
overriding concern precedent to reaching any finding as to exclusivity and is
a compelling basis on which to sustain the Claim.
Form 1 Award No. 28044
Page 3 Docket No. MW-26847
89-3-85-3-602
While the Board finds that Count I of the Claim must be sustained,
the Claimants during the period in question were fully employed and thus were
not adversely affected in any monetary sense. The record here discloses no
evidence of suffered loss and consequently we will deny the Claim for damages
in Count 3.
A W A R D
Claim sustained in accordance with the Findings.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest:
01
Nancy J. D - Executive Secretary
Dated at Chicago, Illinois this 10th day of August 1989.