Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 28044
THIRD DIVISION Docket No. MW-26847
89-3-85-3-602
The Third Division consisted of the regular members and in
addition Referee Elliott H. Goldstein when award was rendered.

(Brotherhood of Maintenance of Way Employes PARTIES TO DISPUTE:


STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:

(1) The Carrier violated the Agreement when it assigned outside forces to construct a right-of-way fence between Mile Post 109.6 and Mile Post 110.8 on the Connelsville District from August 28, 1984 to September 10, 1984 (Carrier's File MW-ROK-84-11).

(2) The Carrier also violated Article IV of the May 17, 1968 National Agreement when it did not give the General Chairman advance written notice of its intention to contract said work.

(3) B&B Foreman R. Cummings and Carpenters H. Hoeflich, R. Federer, G. Whitaker, J. Kopacko and C. DeBaker shall each be allowed eighty (80) hours of pay at their respective straight time rates because of the aforesaid violations."

FINDINGS:

The Third Division of the Adjustment Board upon the whole record and all the evidence, finds that:

The carrier or carriers and the employe or employes involved in this dispute are respectively carrier and employes within the meaning of the Railway Labor Act as approved June 21, 1934.

This Division of the Adjustment Board has jurisdiction over the dispute involved herein.



Claimants established and hold seniority in their respective classes in the Bridge and Building Sub-Department of the Maintenance of Way and Structures Department.

Beginning on August 28, 1984, and continuing through September 10, 1984, Carrier assigned outside forces to construct a right-of-way fence between Mile Post 109.6 and Hopedal and Pittsburgh Junction, Ohio. There is no dispute that Carrier failed to notify the General construction work in accordance with Article IV of the Agreement, which provides:
Form 1 Award No. 28044
Page 2 Docket No. MW-26847
89-3-85-3-602


































Carrier maintains that it is obligated by law in the State of Ohio to have fencing along property lines where livestock is maintained on the adjacent property. Carrier argues that it needed to take immediate action, and after canvassing its forces, determined that no forces were available to construct the fence within the time frame allowed. The Organization argues that even if that was the case, Carrier was not relieved of its obligations under Article IV.

We agree with the Organization. Carrier has an obligation to assert good faith efforts to reduce the incidence of subcontractng and increase the use of maintenance of way forces. Carrier failed to do so in this case. The fact that Carrier has not met its burden in this regard is a fundamental and overriding concern precedent to reaching any finding as to exclusivity and is a compelling basis on which to sustain the Claim.
Form 1 Award No. 28044
Page 3 Docket No. MW-26847
89-3-85-3-602

While the Board finds that Count I of the Claim must be sustained, the Claimants during the period in question were fully employed and thus were not adversely affected in any monetary sense. The record here discloses no evidence of suffered loss and consequently we will deny the Claim for damages in Count 3.






                              By Order of Third Division


Attest: 01
Nancy J. D - Executive Secretary

Dated at Chicago, Illinois this 10th day of August 1989.