Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 28126
THIRD DIVISION Docket No. MW-27560
89-3-86-3-825
The Third Division consisted of the regular members and in
addition Referee Robert W. McAllister when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(CSX Transportation, Inc. (formerly Seaboard
(System Railroad)
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when it furloughed Bridge and
Building Department forces during the construction of an Agency Building at
Fernandina Beach, Florida [System File 12-2(86-15) I/B&B-85-85].
(2) As a consequence of the aforesaid violation 'the B&B Employees
involved in the recent cut off' and 'the B&B Employees furloughed in the prior
abolishments protected by this Agreement' shall each be allowed eight (8)
hours of pay, at their respective straight time rates, for each day of continual violation."
FINDINGS:
The Third Division of the Adjustment Board upon the whole record and
all the evidence, finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employes within the meaning of the
Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the
dispute involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
On July 23, 1985, the organization and Carrier reached an understanding concerning construction
Florida. This understanding provided that Carrier could use an outside contractor for construction o
furloughed during the course of the project. During November 1985, while the
building was still under construction, Carrier furloughed employees in all
Crafts, including B&B forces. At the same time, the contractor was notified
he would not be able to continue work on the project.
On December 6, 1985, a Claim was filed on behalf of unnamed, furloughed B&B forces. This Cla
readily identifiable and that it was for an uncertain period and for no specific amount. On the meri
Form 1 Award No. 28126
Page 2 Docket No. MW-27560
89-3-86-3-825
after the date the November furloughs were effective and that
B&B
forces were
thereafter used to complete the structure. Carrier also argued the Claim was
"vague, indefinite and uncertain" and was based on a theory that:
...Carrier was required to continue having
B&B work
performed by the Contractor and prohibited from furloughing
B&B
forces because (the organization) consented to contracting
B&B
work in this lock and key
project."
This Board agrees with the Carrier's position that the Claim is
vague, indefinite, and uncertain. We also find the Organization has not demonstrated that the unders
the Carrier. The Agreement provided that no
B&B forces
would be furloughed
"during the course of this project." Clearly, this commitment was linked to
the use of an outside contractor. As of November 22, 1985, that contractor
ceased all work that could be performed by Carrier employees.
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest:
.ancy J. /D r - Executive Secretary
Dated at Chicago, Illinois this 25th day of September 1989.