For 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 28168
THIRD DIVISION Docket No. MW-27461
89-3-86-3-706
The Third Division consisted of the regular members and in
addition Referee Robert W. McAllister when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(The Kansas City Southern Railway Company
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:
(1) The ten (10) days of suspension imposed upon Roadway Mechanic
J. W. Brown for alleged responsibility in connection with the incident in
which Machine MW 894 was destroyed by fire on January 11, 1985, was arbitrary,
capricious and on the basis of unproven charges (Carrier's File 013.31-328).
(2) The claim as presented by First Vice Chairman G. A. Sackett on
March 25, 1985 to Administrative Manager R. C. John shall be allowed as
presented because said claim was not disallowed by Administrative Manager
R. C. John in accordance with Rule 14-1(a).
(3) Division Engineer T. L. Barker failed to disallow the claim
(appealed to him under date of August 10, 1985) as contractually stipulated
within Rules 14-1(a) and 14-1(b).
(4) As a consequence of either or all (1), (2) and/or (3) above, the
claimant shall be compensated
'...
for all lost time, including any overtime
that was worked by another mechanic on Mr.
Brown's area of responsibility, while Mr. Brown
was off from the period of March 18, 1985 through
March 27, 1985 as a result of investigation held
February 11, 1985.'"
FINDINGS:
The Third Division of the Adjustment Board upon the whole record
and all the evidence, finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employes within the meaning of the
Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the
dispute involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
Form 1 Award No. 28168
Page 2 Docket No. MW-27461
89-3-86-3-706
Essentially, the organization argues this Claim, which arose because
of a ten (10) day suspension issued to the Claimant, must be sustained because
the Carrier twice failed to meet the time limit provisions of Rules 14-1(a)
and (b). Specifically, the organization charges the Carrier did not respond
to its initial Claim letter dated March 25, 1985, and compounded this failure
by not responding to the appeal letter dated August 10, 1985.
The record reveals that on June 18, 1985, the Carrier responded to
the organization's June 10, 1985, letter demanding payment of the Claim
because of the time limit violation. The Carrier therein asserted the organization's Claim letter of
letter was its first notice of any such Claim. The Carrier then addressed the
merits and denied the Claim. On August 10, 1985, the organization appealed
that denial. On November 4, 1985, the Organization wrote to the Carrier stating it had not received
thereby, the Carrier had violated the time limit provisions. On November 10,
the Carrier responded and denied receipt of the August 10 appeal.
Given the above, this Board is required to address the alleged time
limit violations, as well as the Carrier's contentions it had never received
the initial claim or appeal.
Clearly, Rule 14-1(a) requires all claims or grievances to be presented in writing within sixty
which the claim/grievance is based. The Organization contends it "presented"
a Claim to the Carrier on March 25, 1985, which the Carrier, as indicated,
denied receiving. This Board has previously held that in such circumstances
the burden of proof is upon the sender to demonstrate that the letter was
received (See Third Division Awards 22600, 26675, and 21088). In Award 26675,
the Board cited Third Division Award 11505 wherein it stated:
"It is a general principle of the law of agency
that a letter properly addressed, stamped, and
deposited in the United States mail is presumed
to have been received by the addressee. But,
this is a rebuttable presumption. If the
addressee denied receipt of the letter then the
addresser has the burden of proving that the
letter was in fact received. Petitioner herein
has adduced no proof, in the record, to prove
de facto receipt of the letter by the Carrier
.. Upon the record before us we find that
Petitioner has not proven that it presented the
Claim, to Carrier, within the time limitation
agreed to by the parties; and, in the absence of
such proof the claim is barred
...."
Form 1 Award No. 28168
Page 3 Docket No. MW-27461
89-3-86-3-706
In this matter, the Organization has submitted no evidence to support
its allegation that it "presented" the claim to the Carrier. There is no
statement or proof an Organization representative put the letter in the U. S.
mail which placed it in line for timely receipt by the Carrier. If the
parties wish to avoid the expense of tracking each piece of correspondence,
then the burden is on the sender, when receipt is disputed, to offer tangible
proof the letter was, in fact, placed in the regular mail by an identifiable
individual. The existence of a copy of the disputed correspondence is not a
substitute for such proof. Based upon the Organization's failure to meet this
burden, this Claim is hereby dismissed.
A W A R D
Claim dismissed.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
At teat.
L
Nancy J er - Executive Secretary
Dated at Chicago, Illinois, this 16th day of October 1989.