Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 28312
THIRD DIVISION Docket No. MW-28037
90-3-87-3-605
The Third Division consisted of the regular members and in
addition Referee Herbert L. Marx, Jr. when award was rendered.

(Brotherhood of Maintenance of Way Employes PARTIES TO DISPUTE:


STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:

(1) The Agreement was violated when outside forces were used to perform track rehabilitation work on Tracks 9, 10 and 11 in Maidsville Yard from March 17, 1986 through April 7, 1986 (Carrier's File M-3793).

(2) The Agreement was further violated when the Carrier did not give the General Chairman fifteen (15) days advance notification of its plans to assign said work to outside forces in accordance with Addendum No. 9.

(3) Because of the aforesaid violations, furloughed employes M. R. Gallo, K. J. Rock, J. R. Franks, J. E. Myers, T. Garcia, B. K. Johnson and H. T. Moore shall each be allowed one hundred twenty-eight (128) hours of pay at the rate of eleven dollars and forty-two cents ($11.42) per hour for a total of one thousand four hundred sixty-one dollars and seventy-six cents ($1,461.76) each."

FINDINGS:

The Third Division of the Adjustment Board upon the whole record and all the evidence, finds that:

The carrier or carriers and the employe or employes involved in this dispute are respectively carrier and employes within the meaning of the Railway Labor Act as approved June 21, 1934.

This Division of the Adjustment Board has jurisdiction over the dispute involved herein.



Under a Letter Agreement, preliminary to a formal leasing arrangement, the Carrier agreed on Mar Consolidated Coal Company for the purpose of establishing and operating a coal loading facility. The arrangement gave Consolidated the right to enter the designated area "for the purpose of constructing a driveway crossing over No. 2 Track and preparing and using about 5.0 acres of land for the construction of a loading facility and the rehabilitation and maintenance of tracks 9 and 11.
Form 1
Page 2

Award No. 28312
Docket No. MW-28037
90-3-87-3-605

As to the rehabilitation of Tracks 9 and 11, Consolidated engaged another firm to perform the work. This track work was performed from March 17, 1986 through April 17, 1986.

On March 24, 1986 -- while the track rehabilitation work was in progress -- the Superintendent wrote to the General Chairman as follows:

"Please excuse the delay in advising you of a special handling which has developed just recently which affects indirectly the MW&S Department in the Maidsville, W. Va. District.

The Monongahela Railway Company has entered into and will ultimately finalize the leasing of Maidaville Yard tracks Nos. 9-10-11 to Consolidation Coal Company in order to facilitate coal loading by rail at their Humphrey Preparation Plant. Included in lease agreement is proviso for the coal company to perform all necessary rehabilitation of these tracks, as well as ultimate maintenance of same.

In recent years, the MW&S Department has very infrequently performed maintenance of these tracks as the present volume of traffic and business did not warrant same. The costs of labor and material for rehabilitation and maintenance in future is the sole responsibility of Consolidation Coal Company.

In no way will the complement of MW&S track forces at the Maidsville headquarters be affected.

This will result in increased business to the Monongahela Railway Company affording the opportunity to maintain present force in this area of operations.

If you have any further discussion relative to this affair, please feel free to contact me."

The Organization contends that the Carrier was in violation of Addendum No. 9 in failing to advise the Organization at least 15 days in advance concerning the track rehabilitation work. Addendum No. 9 reads as follows:
Form 1 Award No. 28312
Page 3 Docket No. MW-28037
90-3-87-3-605









The Carrier argues that, in this instance, such notice was not required. The Carrier points out it was Consolidated which undertook a subcontracting arrangement to complete work on property leased to it.

Numerous Awards have held a carrier harmless in instances where contracting work is undertaken b the control of and/or for the benefit of the Carrier. As a recent example to this effect, Third Division Award 26103 states:


Form 1 Award No. 28312
Page 4 Docket No. MW-28037
90-3-87-3-605



Nothing herein is intended to dilute the effect of such Awards. Other Awards, however, have exam the work to be performed and where it is apparent that such work could have been performed by carrier forces. To this effect is recent Third Division Award 26212 in a situation closely parallel to that here under review. Award 26212 states in part as follows:










Form 1 Award No. 28312
Page 5 Docket No. MW-28037
90-3-87-3-605
the track is certainly intimately connected with
Carrier's railroad operation. Had Carrier directly
let the work in question to Byler clearly the
Agreement and notice requirements would apply. It
seems equally clear that by leasing the property for
the express purpose of construction of the track an
attempt is made to do by indirection that which can
not be directly done. We conclude the Agreement was
violated when no advance notice of the Lease was
given.
We agree with Carrier that the Organization did
not establish historic exclusivity in the handling
of this Claim. However, without regard to the issue
of whether it would otherwise be necessary to do so,
we have repeatedly held such proof is not necessary
when the question is one of Notice under the Agree
ment and the work is within the Scope of the Agree
ment."

An essential part of the arrangement with Consolidated was preparation of the tracks for use by by a contractor selected by Consolidated is not the central issue. That the work was of a type which could have been performed by Carrier forces is not disputed.

At issue here is the requirement of advance notice under Addendum No. 9. It is not known whether, after conference which may have been requested by the Organization, some alternate arrangement would have been devised. What is certain is that failure to provide the required notice obviated any opportunity by the Organization knew that the track rehabilitation was to be performed as an essential preliminary to establishment
Under these circumstances, the Board finds the reasoning in Third Division Award 26212 persuasive. The Carrier proceeded without sufficient advance notice at its own peril.






                          By Order of Third Division


Attest: -
      'Nancy J. v - Executive Secretary


Dated at Chicago, Illinois, this 29th day of March 1990.