Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 28312
THIRD DIVISION Docket No. MW-28037
90-3-87-3-605
The Third Division consisted of the regular members and in
addition Referee Herbert L. Marx, Jr. when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(The Monongahela Railway Company
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:
(1) The Agreement was violated when outside forces were used to
perform track rehabilitation work on Tracks 9, 10 and 11 in Maidsville Yard
from March 17, 1986 through April 7, 1986 (Carrier's File M-3793).
(2) The Agreement was further violated when the Carrier did not give
the General Chairman fifteen (15) days advance notification of its plans to
assign said work to outside forces in accordance with Addendum No. 9.
(3) Because of the aforesaid violations, furloughed employes M. R.
Gallo, K. J. Rock, J. R. Franks, J. E. Myers, T. Garcia, B. K. Johnson and
H. T. Moore shall each be allowed one hundred twenty-eight (128) hours of pay
at the rate of eleven dollars and forty-two cents ($11.42) per hour for a
total of one thousand four hundred sixty-one dollars and seventy-six cents
($1,461.76) each."
FINDINGS:
The Third Division of the Adjustment Board upon the whole record
and all the evidence, finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employes within the meaning of the
Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the
dispute involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
Under a Letter Agreement, preliminary to a formal leasing arrangement, the Carrier agreed on Mar
Consolidated Coal Company for the purpose of establishing and operating a coal
loading facility. The arrangement gave Consolidated the right to enter the
designated area "for the purpose of constructing a driveway crossing over No.
2 Track and preparing and using about 5.0 acres of land for the construction
of a loading facility and the rehabilitation and maintenance of tracks 9 and
11.
Form 1
Page 2
Award No. 28312
Docket No. MW-28037
90-3-87-3-605
As to the rehabilitation of Tracks 9 and 11, Consolidated engaged
another firm to perform the work. This track work was performed from March
17, 1986 through April 17, 1986.
On March 24, 1986 -- while the track rehabilitation work was in
progress -- the Superintendent wrote to the General Chairman as follows:
"Please excuse the delay in advising you of
a special handling which has developed just
recently which affects indirectly the MW&S
Department in the Maidsville, W. Va. District.
The Monongahela Railway Company has entered
into and will ultimately finalize the leasing of
Maidaville Yard tracks Nos. 9-10-11 to Consolidation Coal Company in order to facilitate coal
loading by rail at their Humphrey Preparation
Plant. Included in lease agreement is proviso
for the coal company to perform all necessary
rehabilitation of these tracks, as well as
ultimate maintenance of same.
In recent years, the MW&S Department has very
infrequently performed maintenance of these
tracks as the present volume of traffic and business did not warrant same. The costs of labor
and material for rehabilitation and maintenance
in future is the sole responsibility of Consolidation Coal Company.
In no way will the complement of MW&S track
forces at the Maidsville headquarters be affected.
This will result in increased business to
the Monongahela Railway Company affording the
opportunity to maintain present force in this
area of operations.
If you have any further discussion relative
to this affair, please feel free to contact me."
The Organization contends that the Carrier was in violation of
Addendum No. 9 in failing to advise the Organization at least 15 days in
advance concerning the track rehabilitation work. Addendum No. 9 reads as
follows:
Form 1 Award
No.
28312
Page 3 Docket
No.
MW-28037
90-3-87-3-605
"Contracting out of Maintenance of Way Work
In the event a carrier plans to contract out
work within the scope of the applicable schedule
agreement, the carrier shall notify the General
Chairman of the organization involved in writing
as far in advance of the date of the contracting
transaction as is practicable and in any event
not less than 15 days prior thereto.
If the General Chairman, or his representative, requests a meeting to discuss matters
relating to the said contracting transaction,
the designated representative of the carrier
shall promptly meet with him for that purpose.
Said carrier and organization representatives
shall make a good faith attempt to reach an
understanding concerning said contracting, but
if no understanding is reached the carrier may
nevertheless proceed with said contracting, and
the organization may file and progress claims in
connection therewith.
Nothing in this Article IV shall affect the
existing rights of either party in connection
with contracting out. Its purpose is to require
the carrier to give advance notice and, if requested, to meet with the General Chairman or
his representative to discuss and if possible
reach an understanding in connection therewith."
The Carrier argues that, in this instance, such notice was not required. The Carrier points out
it was Consolidated which undertook a subcontracting arrangement to complete
work on property leased to it.
Numerous Awards have held a carrier harmless in instances where contracting work is undertaken b
the control of and/or for the benefit of the Carrier. As a recent example to
this effect, Third Division Award 26103 states:
"In this case at bar (unlike PLB 2203, Award
No.
21) there is no showing that the Carrier was
involved in the contract or had any knowledge
whatsoever of the contract by its subsidiary.
Nowhere on property does this Board find any
probative evidence to go beyond mere inference
Form 1 Award No. 28312
Page 4 Docket No. MW-28037
90-3-87-3-605
that Carrier violated the Scope of the Agreement. This Board finds from the record on
property that the Carrier had no control over
the work herein contested on leased property of
its subsidiary or knowledge thereof, and that
such subcontracting has been no violation of the
Agreement."
Nothing herein is intended to dilute the effect of such Awards. Other Awards, however, have exam
the work to be performed and where it is apparent that such work could have
been performed by carrier forces. To this effect is recent Third Division
Award 26212 in a situation closely parallel to that here under review. Award
26212 states in part as follows:
"Thus it appears this Board has defined several
categories of cases in which the Agreement will not
be violated by use of outside forces. These, at a
minimum include situations:
(1) Where the work, while perhaps within
control of Carrier, is totally unrelated to
railroad operations.
(2) Where the work is for the ultimate
benefit of others, is made necessary by the
impact of the operations of others on Carrier's
property and is undertaken at the sole expense
of that other party.
(3) Where Carrier has no control over the
work for reasons unrelated to having itself
contracted out the work.
Applying these criteria, and recognizing there
may well be others which would apply in different
circumstances we conclude the work at issue here was
within the Scope Rule of the Agreement. The very
instrument by which the property was leased to
Coastal includes the parties' Agreement 'with respect to the construction maintenance
of industrial track.' This constitutes an agreement
by Carrier to have track built by the Lessee and is
fairly within the Notice requirement of the Agreement as well as the December 11, 1981 letter. Furth
the track is to be constructed, maintained and
operated is reserved to Carrier and the operation of
Form 1 Award No. 28312
Page 5 Docket No. MW-28037
90-3-87-3-605
the track is certainly intimately connected with
Carrier's railroad operation. Had Carrier directly
let the work in question to Byler clearly the
Agreement and notice requirements would apply. It
seems equally clear that by leasing the property for
the express purpose of construction of the track an
attempt is made to do by indirection that which can
not be directly done. We conclude the Agreement was
violated when no advance notice of the Lease was
given.
We agree with Carrier that the Organization did
not establish historic exclusivity in the handling
of this Claim. However, without regard to the issue
of whether it would otherwise be necessary to do so,
we have repeatedly held such proof is not necessary
when the question is one of Notice under the Agree
ment and the work is within the Scope of the Agree
ment."
An essential part of the arrangement with Consolidated was preparation of the tracks for use by
by a contractor selected by Consolidated is not the central issue. That the
work was of a type which could have been performed by Carrier forces is not
disputed.
At issue here is the requirement of advance notice under Addendum No.
9. It is not known whether, after conference which may have been requested by
the Organization, some alternate arrangement would have been devised. What is
certain is that failure to provide the required notice obviated any opportunity by the Organization
knew that the track rehabilitation was to be performed as an essential preliminary to establishment
Under these circumstances, the Board finds the reasoning in Third
Division Award 26212 persuasive. The Carrier proceeded without sufficient
advance notice at its own peril.
A W A R D
Claim sustained.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest: -
'Nancy J. v - Executive Secretary
Dated at Chicago, Illinois, this 29th day of March 1990.