Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 28328
THIRD DIVISION Docket No. MW-28114
90-3-87-3-695
The Third Division consisted of the regular members and in
addition Referee Marty E. Zusman when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Union Pacific Railroad Company
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:
(1) The sixty (60) day suspension imposed on Foreman D. T. Towler
for alleged responsibility for the derailment which occurred on May 19, 1986
was without just and sufficient cause, arbitrary, on the basis of unproven
charges and in violation of the Agreement (System File D-80/860064).
(2) Claimant Towler's record shall be cleared of the charges leveled
against him and he shall be compensated for all wage loss suffered."
FINDINGS:
The Third Division of the Adjustment Board upon the whole record
and all the evidence, finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employes within the meaning of the
Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the
dispute involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
On May 19, 1986, at approximately 1:40 P.M., Claimant was Section
Foreman in charge of installing ties when a train derailed at his work site.
Claimant was removed from service on May 20, and thereafter was notified by
letter dated May 29, 1986, to attend a Hearing to consider his alleged
responsibility for the derailment in violation of various Rules. Following
the Hearing, Claimant was notified by letter of June 11, 1986, that he had
been found guilty and was assessed a sixty (60) days suspension.
The Organization argues that Claimant's removal from service was a
violation of Rule 48(o) in that no evidence was produced to find Claimant
guilty of a "serious" violation of the Rules. It further argues that the
charges were expanded beyond the Rules cited in the Notice of Hearing and the
Carrier failed to meet its required burden of proof.
Form 1 Award No. 28328
Page 2 Docket No. MW-28114
90-3-87-3-695
It is the Carrier's position that its action and charges were fully
supported with sufficient probative evidence. The Carrier holds that Claimant's actions were the cau
A review of the record finds no procedural violations of the Agreement. The charge letter indica
CE Bulletin 85-387-T which states that "installation of ties must be handled
in accordance with the CE Bulletin covering Tie Renewals." The variance
between explicit referral to tie renewals in the statement of charges and its
embedded mention is not in these circumstances fatal. Claimant was aware of
the temperature issue as indicated in the transcript and a procedural error
fatal to a finding of guilt did not occur. We also find that the Tie Renewal
Bulletin was read to the Claimant and he had knowledge thereof.
With respect to the merits of the case, the Board finds substantial
evidence present to warrant a conclusion of guilt. The transcript contains
the testimony of two Carrier witnesses that the ties were improperly installed
specifically with regard to instructions pertaining to rail temperature. The
record indicates that Claimant began installing ties at approximately 10:00
A.M. when the temperature was cool. Although Claimant admits he had a rail
thermometer with him and would have tested the rails at Noon, he testified
that he did not test the temperature as he was called away. The derailment
occurred at around 1:40 P.M. Evidence of record confirms that the rail temperature was 100 degrees a
P.M. Since the Rules required a slow order at 100 degrees or above, and
Claimant neither measured rail temperature, nor issued such an order, the
Board finds Carrier's conclusions to have been supported.
In view of the record before this Board, notwithstanding all other
probable contributing causes, there is sufficient probative evidence to
support Carrier's conclusions that Claimant was responsible for the condition
of the track which led to the derailment. Since such is the case, this Board
will not disturb the Carrier's determination in this matter.
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest:
' Nancy J
r0-
Executive Secretary
Dated at Chicago, Illinois, this 29th day of March 1990.