Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 28337
THIRD DIVISION Docket No. MW-27214
89-3-86-3-288
The Third Division consisted of the regular members and in
addition Referee John C. Fletcher when award was rendered.



PARTIES TO DISPUTE:


STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:

(1) The Carrier violated the Agreement when it assigned outside forces to perform yard cleaning 1985 (System File MW-85-35-CB/53-838).

(2) As a consequence of the aforesaid violation, Foreman I. C. Spears and Machine Operator L. H. Loggins shall each be allowed pay at their respective rates for an equal
FINDINGS:

The Third Division of the Adjustment Board upon the whole record and all the evidence, finds that:

The carrier or carriers and the employe or employes involved in this dispute are respectively carrier and employes within the meaning of the Railway Labor Act as approved June 21, 1934.

This Division of the Adjustment Board has jurisdiction over the dispute involved herein.



On February 14, 1985, Carrier notified the General Chairman, under the provisions of Article 33 of the Agreement, of its intent to contract out work of cleaning up debris along tracks and in yards on the Pine Bluff Division. The notice indicate which it would operate with its own forces. The notice further stated that all of Carrier's yard cleaners were fully utilized and that the work would begin on March 1, 1985, and continue for approximately 75 working days.

On February 19, 1985, the Organization responded with a contention that the intended contracting out was "totally ridiculous" and that the work was not emergency work and could be performed at a later date when Carrier cleaners became available. Additionally, the organization contended that large force reductions were being made in all Maintenance of Way Departments and that the use of a contractor was in direct violation of the December 11, 1981 Agreement. The February 19, 1985 letter indicated that Claims would be filed if Carrier allowed contractors to do the work, but it did not request a meeting to discuss the matter.
Form 1 Award No. 28337
Page 2 Docket No. MW-27214
89-3-86-3-288

On May 14, 1985, Claims were filed on behalf of the individuals named in the Statement of Claim for an equal proportionate share of the total man hours worked by the contractor's forces. As these Claims were progressed on the property the organization preserved its initial basis of objection to the contracting and also contended that Carrier had not made a good faith effort to reduce contracting or increase the use of Maintenance of Way forces as contemplated by the December 11, 1981 Letter of Understanding.

In response to the Claims, Carrier contended that it had given proper notice to the Organization and that it had valid reasons for contracting the work out. Before this Board it also contended that neither Claimant lost any work as a result of the contract, both being fully employed during its duration.

In support of their arguments before this Board both parties rely upon a large number of Awards involving contracting out issues in the Maintenance of Way Craft. On r not on point because they deal with cases in which the Carrier did not initially give the Organizati cases in which incomplete or generalized blanket notices were given, a defect which the Organization has not alleged is present here. One dealt with a case where the wrong General Chairman was given the notice; something else which is not present here. Still other Awards cited to us deal with the issue of whether a notice was require contracted was not exclusively within the scope of the Agreement; something else absent in this case. None of the remainder of the citations, to our knowledge, cover a situation where a timely notice was given, but the Organization did not seek a me





Form 1 Award No. 28337
Page 3 Docket No. MW-27214
89-3-86-3-288
Nothing in this Article shall affect the existing rights
of either party in connection with contracting out. Its
purpose is to require the carrier to give advance notice
and, if requested, to meet with the General Chairman or
his representative to discuss and if possible reach an
understanding in connection therewith."














Form 1 Award No. 28337
Page 4 Docket No. MW-27214
89-3-86-3-288
The Committee shall retain authority to continue discus
sions on these subjects for the purpose of developing
mutually acceptable recommendations that would permit
greater work opportunities for maintenance of way em
ployees as well as improve the carriers' productivity by
providing more flexibility in the utilization of such em
ployees.
The carriers assure you that they will assert good-faith
efforts to reduce the incidence of subcontracting and in
crease the use of their maintenance of way forces to the
extent practicable, including the procurement of rental
equipment and operation thereof by carrier employees.
The parties jointly reaffirm the intent of Article IV of
the May 17, 1968 Agreement that advance notice require
ments be strictly adhered to and encourage the parties
locally to take advantage of the good faith discussions
provided for to reconcile any differences. In the in
terests of improving communications between the parties
on subcontracting, the advance notices shall identify the
work to be contracted and the reasons therefor.
Notwithstanding any other provisions of the December 11,
1981 National Agreement, the parties shall be free to
serve notices concerning the matters herein at any time
after January 1, 1984. However, such notices shall not
become effective before July 1, 1984.
Please indicate your concurrence by affixing your signa
ture in the space provided below."

In this case it is clear that Carrier did give the notice required by Article 33. Additionally, the notice identified the work to be contracted and offered reasons therefor, as required by the pen-penultimate paragraph of the December 11, 1981 Letter of Understanding. However the Organization did not request a meeting to discuss the matter. Thus, the opportunity to meet and make a good faith attempt to reach an understanding concerning the subject of the notice was not taken advantage of by the Organization in spite of a strong admonition to do so. (We are aware that the Organizaton sent a letter of protest and what was stated in this letter may well have been its position in a face-to-face meeting, but we do not think that this action is an appropriate substitute for a meeting, especially since the Chief Negotiator for the Organization and the Chief N take advantage of meetings and discussions.)
Form 1 Award No. 28337
Page 5 Docket No. MW-27214
89-3-86-3-288

As we read Article 33 and the December 11, 1981 Letter of Understanding, the Carrier must give n within the scope of the applicable schedule agreement." When this notice is given, the Organization, at its sole option, may request a meeting to discuss matters relating to said contracting. Such discussions, once requested, are obligatory and are to be conducted in good faith in an attempt to reconcile any differences between the parties. If the Organization fails, for whatever reason, to take advantage of its contractual right to have such a meeting and passes up an attempt to engage in contemplated good faith discussions, it misses its opportunity to demonstrate "that work within the scope of the applicable schedule agreement is contracted out unnecessarily."

Without such a meeting and discussion, which by the language of the Agreement must be originated by the Organization, we doubt that we have license to explore further the merits of the transaction. Accordingly, after careful review of the entire record in this case, the explicit provisions of Article 33, the lengthy provisions of the December 11, 1981 Letter of Understanding and the Awards r basis on which the Organization's Claim can be sustained.






                              By Order of Third Division


Attest:
      Nancy J er·- Executive Secretary


Dated at Chicago, Illinois, this 27th day of April 1990.