Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 28350
THIRD DIVISION Docket No. MW-28355
90-3-88-3-122
The Third Division consisted of the regular members and in
addition Referee Herbert L. Marx, Jr. when award was rendered.

(Brotherhood of Maintenance of Way Employes PARTIES TO DISPUTE:



STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:

(1) The Agreement was violated when the Carrier assigned outside contractors to repair the roof Pennsylvania on December 17, 18, 19, 20, 21 and 22, 1986 (Carrier's File MW-ROK-87-1).

(2) The Agreement was also violated when the Carrier failed to meet with the General Chairman to discuss matters relating to said contracting transaction in accordance with Article IV of the May 17, 1968 National Agreement.

(3) As a consequence of the violations referred to in Parts (1) and/or (2) above, furloughed Carpenters C. L. Gardner, R. Federer, Jr., J. W. Young and J. A. Anderson shall each be allowed forty-eight (48) hours of pay at the carpenter's straight time rate."

FINDINGS:

The Third Division of the Adjustment Board upon the whole record and all the evidence, finds that:

The carrier or carriers and the employe or employes involved in this dispute are respectively carrier and employes within the meaning of the Railway Labor Act as approved June 21, 1934.

This Division of the Adjustment Board has jurisdiction over the dispute involved herein.



On November 25, L986, the Carrier gave the General Chairman written notice of its intent to contract out roof repair work on Office Building No. 56-2-P at Rook, Pa. The sole reason given for the proposed contracting was that, "The Carrier does not possess the necessary skilled manpower, supervision or equipment to sati On December 1, 1986, the General Chairman wrote the Carrier to advise of the Organization's objection, And requesting a meeting in accordance with Article IV of the National Agrr~nt dated May 17, 1968.
Form 1 Award No. 28350
Page 2 Docket No. MW-28355
90-3-88-3-122

The Carrier in turn advised the General Chairman by letter dated December 15, 1986, that the General Supervisor, Bridges and Buildings "will contact you in the near future to discuss this matter." The record shows, however, that no such meeting was arranged by the Carrier. Further, the roof repair work was performed, as reported by the Organization, immediately thereafter on December 17-22






Whether through inadvertence or otherwise, the facts of record demonstrate that the Carrier viol with the General Chairman to "make a good faith attempt to reach an understanding." On this basis, t had the opportunity to perform the work.

Despite its admitted lapse, the Carrier argues in defense of its position on other bases. These arguments, however, do not have such substantial merit as to obviate in conference as prescribed by Article IV. The alleged lack of skilled manpower and equipment and th lack of exclusive right to such work is beside the point. That work of this nature is generally "within the scope" of the Organization's Agreement cannot be denied. As stated in Third Division Award 27012:
Form 1 Award No. 28350
Page 3 Docket No. MW-28355
90-3-88-3-122





In addition, the Carrier challenges the extent of the monetary Claim made by the Organization. The Board directs the Carrier to furnish promptly proof of the actual number of employees and hours expended in the work. Should the Carrier fail to provide promptly such information, the Claim will be sustained as presented. See Third Division Award 26072 to similar effect.






                          By Order of Third Division


                  0000,


        Attest:. ancy J. e r -Executive Secretary


        Dated at Chicago, Illinois, this 27th day of April 1990.