Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 28475
THIRD DIVISION Docket No. MW-28296
90-3-87-3-845
The Third Division consisted of the regular members and in
addition Referee Herbert L. Marx, Jr. when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(The Denver and Rio Grande Western Railroad Company
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when it assigned outside
forces to operate the rail welding plant in the Minneque Yard at Pueblo,
Colorado beginning March 10, 1986 (System File D-86-13 /MW-21-86).
(2) The Carrier also violated Article IV of the May 17, 1968
National Agreement when it did not give the General Chairman advance written
notice of its intention to contract said work.
(3) As a consequence of the violations referred to in Parts (1)
and/or (2) above, Welding Foreman J. J. Rivera, Work Equipment Operator
Meitzler and Trackmen S. D. Maldonado, L. L. Archuleta, J. Roybal, M.
Gutierrez, J. G. Allen, P. Maisel, D. M. Dremel, D. Guillen, R. A. Workman,
W. K. Fleshman, K. D. Nelson, E. D. Tellin, T. B. Diaz, J. R. Garcia, D. M.
Arguello, E. Baca, J. T. Roller, Jr., G. G. Carbajal, A. C. Fogani, F. R.
Garcia, S. B. Espinoza, M. J. Walker, C. L. Orndorff, Jr., D. T. Proud and T.
L. Workman shall each be compensated eight (8) hours at their respective
straight time rates of pay Monday through Friday and they shall be compensated
at the time and one-half rate of pay for all hours worked outside of regular
assigned hours by the outside contractor beginning March 10, 1986 and continuing until the violation
FINDINGS:
The Third Division of the Adjustment Board upon the whole record
and all the evidence, finds that:
The carrier or carriers and the employe or employee involved in this
dispute are respectively carrier and employes within the meaning of the
Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the
dispute involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
Form 1 Award No. 28475
Page 2 Docket No. MW-28296
90-3-87-3-845
Prior to February 28, 1986, the Carrier operated a rail welding
facility at Pueblo, Colorado, located in the Carrier's Minneque Yard. This
facility was operated jointly with the Holland Company, a welded rail supplier, for the purpose of p
assigned four employees (one Foreman-Inspector, one Crane Operator and lo
Trackmen) to this work.
According to the Carrier, the Holland Company sought to expand the
operation to provide welded rail to other Carriers. The Carrier asserts that
if the Holland Company were able to expand the facility and assume the full
operation, this would result in a substantial reduction of the Carrier's cost
of welded rail, based on the Holland Company's ability to purchase rail in
quantity and thus reduce the price.
In March 1986, when the production of welded rail was scheduled to
resume after a period of inactivity, the Carrier assigned Claimant Meitzler to
the crane and bulletined two Trackman's positions. When the Holland Company
determined to use its own forces, rather than Carrier employees for the expanded operation, the bull
Operator was transferred to other equipment.
The Claim herein faults the Carrier in its assignment of other than
Maintenance of Way employees to the work taken over by the Holland Company and
for failure to notify the General Chairman on the change in operations as required by Article IV of
follows:
"ARTICLE IV - CONTRACTING OUT
In the event a carrier plans to contract out
work within the scope of the applicable schedule
agreement, the carrier shall notify the General
Chairman of the organization involved in writing
as far in advance of the date of the contracting
transaction as is practicable and in any event
not less than 15 days prior thereto.
If the General Chairman or his representative, requests a meeting to discuss matters
relating to the said contracting transaction,
the designated representative of the carrier
shall promptly meet with him for that purpose.
Said carrier and organization representatives
shall make a good faith attempt to reach an
understanding concerning said contracting, but
if no understanding is reached the carrier may
nevertheless proceed with said contracting, and
the organization may file and progress claims in
connection therewith."
Form 1 Award No. 28475
Page 3 Docket No. MW-28296
90-3-87-3-845
The Carrier's defense is that there is no contracting out of work,
but rather the Carrier contends that a lease exists between the Carrier and
the Holland Company which, in effect, turns the full operation over to Holland
and out of the control of the Carrier.
Previous Awards have dealt with the establishment of lease arrangements for a Carrier's property
Carrier's position has been sustained as to failure to notify the General
Chairman and to utilize Carrier forces.
In this instance, however, the Organization argues that the Carrier
failed to meet its request to examine the reputed lease. The Carrier asserts
that "In conference, the Carrier showed the Organization a copy of the lease
agreement." Such lease was not shown or given to the Organization at an
earlier and more appropriate time, and the Board is not given a copy of the
lease or a summary of its terms.
Without knowing all the terms of the lease, the Organization understandably presses the issue of
Chairman under the cited portion of Article IV and the insistence on use of
Carrier forces to continue the assignments which were previously theirs.
A similar situation arose in Third Division Award 20895, concerning
an industrial customer which had allegedly leased trackage from the Carrier
and then assigned track construction work to an outside contractor. This
Award stated:
"The Organization stated throughout the
handling of this Claim, without denial, that
the type of work involved in this dispute was
embraced within its Agreement and had historically been performed by Track Department
forces. Since Carrier's defense was based
largely on the assertion that the right-of-way
was leased to the Elevator Company, Petitioner
requested that Carrier submit a copy of the
lease to clarify the issue in dispute. The
Organization argues that Carrier did not furnish
a copy of the lease and by letter dated November
15, 1973 told the Organization that the lease
had not been consummated as of the date of the
conference. In addition, Carrier informed the
Petitioner that it would not be agreeable to
furnishing a copy of the contract. Petitioner
argues that Carrier's omission of the lease was
fatal to its defense, and since a prima facie
case had been established, the Claim must be
sustained.
Form 1 Award No. 28475
Page 4 Docket No. MW-28296
90-3-87-3-845
It is noted that Carrier with its rebuttal
argument before this Board submitted a copy of a
lease agreement with the Elevator Company dated
April 13, 1973. Such evidence cannot be considered since it is well established doctrine
that new evidence which was not presented during
the handling of the dispute on the property may
not be considered by this Board .
...we must find that the work of extending
the trackage was work which should have been
assigned to track forces since it occurred on
Carrier's right-of-way and was work within the
Agreement. Furthermore, Carrier did not give
the notice required under the National Agreement. The question of damages was not raised by
Carrier."
To similar effect is sustaining Third Division Award 19623, concerning the work of cleaning a dr
"While the Carrier asserted on the property
that the work performed by the sub-contractor
was performed on land granted to the State of
Oregon, no probative evidence to sustain that
allegation was introduced. A copy of the actual
easement to the State of Oregon would have
sufficed. Absent such proof this Board must
find that the passing track is on operating
property and the shoulder of the track and the
drainage ditch is an integral part of the track
and therefore the cleaning of spill material was
in fact a necessary operation to the completion
of the passing track, which is work within the
scope of the Agreement. The Carrier's desire to
contract out must conform to Rule 40."
As to the circumstances here under review, the Carrier's undertaking
to follow the advance notice requirement of Article IV might well have avoided
the consequences of this Claim. The Board must necessarily provide a sustaining award. Howeve
remedy is limited to Claimants Rivera, Meitzler, Maldonado, and Archuleta.
A W A R D
Claim sustained in accordance with the Findings.
Form 1 Award No. 28475
Page 5 Docket No. MW-28296
90-3-87-3-845
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest:
y~.
anCy J. ;/er - Executive Secretary
Dated at Chicago, Illinois, this 7th day of August 1990.