Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 28555
THIRD DIVISION Docket No. MW-27180
90-3-86-3-249
The Third Division consisted of the regular members and in
addition Referee Robert W. McAllister when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Spokane International Railroad Company
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when it assigned outside
forces (Sletten Construction Company) to construct Bridges 109.8 and 109.9 at
Bonners Ferry, Idaho beginning March 11, 1985 (System File S-I-119C/013210-SI-1).
(2) The Carrier also violated the Agreement when it assigned outside
forces to perform earth and rock moving work in connection with building a new
roadway at Bridge 109.9 beginning April 9, 1985 (System File S-I-12OC/013210-SI-1).
(3) As a consequence of the violation referred to in Part (1) above,
Foreman G. H. Barfuss, Machine Operator J. D. Yeoumans, Sr., Welder P. W.
Curless, First Class Steel Mechanics A. E. Poelstra and W. E. Kendall shall
each be allowed pay at their respective rates for:
'...
8 hours Straight time and 2 hours Time and Onehalf for every day worked by the Contractor, Slett
Construction Company, starting on March 11, 1985
until April 12, 1985 and then on April 15, 1985 for
8 Hours Straight Time and 8 Hours Time and One-half
until this violation is corrected ***'
and Foreman N. R. Brown, Machine Operator H. E. Hedgecock, Welder K. T. Gors,
First Class Steel Mechanics D. R. Greisen and M. R. Brown shall each be allowed pay at their respect
'*** 8 Hours Straight Time and 2 hours Time and Onehalf for each day worked by the Contractor wh
Second Crew from the Contractor started work on April
15, 1985
....'
(4) As a consequence of the violation referred to in Part (2) above,
furloughed Sectionmen T. S. Couch, G. Chopin and G. Werner shall each be allowed pay at their respec
'...
8 hours straight time plus time and one-half for
each day worked by the Contractor starting on April 29,
1985 until this violation is corrected or the work completed
...."'
Form 1 Award No. 28555
Page 2 Docket No. MW-27180
90-3-86-3-249
FINDINGS:
The Third Division of the Adjustment Board, upon the whole record
and all the evidence, finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employes within the meaning of the
Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the
dispute involved herein.
Parties to said dispute waived right of appearance at hearing
thereon.
On January ?5, 1985, the Carrier, by written no"-°, advised the Organization of its intent t
109.8 and 109.9 at Bonners Ferry, Idaho. The new bridge would replace a wooden structure. The Carrie
"The project will require underwater construction,
barges and over-water cranes, and we neither have
the skills nor the equipment to handle the work."
On February 1, 1985, the Organization advised the Carrier the Organization was not agreeable to
the parties met in conference on February 8, 1985, as well as March 28, 1985.
On May 2, 1985, the Organization filed two Claims contending the work contracted out was covered by
Groups and Classes), 53 (Classification of Work), and 54 (Classification of
Employees), the Organization argues the work of constructing bridges and constructing roadbed approa
scope of the Agreement. For its part, the Carrier argues it did not have the
equipment, supervisory skills, or the manpower to construct the bridge at
Bonnets Ferry given the fact the bridge was 803 feet long. The Carrier also
asserted it was not required to piecemeal portions of the overall project.
In this matter, the Organization adopts the position the parties'
Scope Rule prohibits the Carrier from contracting out any work. In so arguing, the Organization also
Out, of the 1968 National Agreement are not controlling because the "more restrictive provisions" of
Organization additionally attempts to suppress any reference to the 1968 National Agreement because
in compliance with Article IV of the National Agreement.
These arguments overlook significant facts contained in this record.
First, the parties' Agreement contains no language requiring the Carrier to
give notice to the Organization when work that is actually or arguably considered within the scope o
Form 1 Award No. 28555
Page 3 Docket No. MW-27180
90-3-86-3-249
Secondly, the Carrier asserted as early as November 27, 1985, that its employees had never previ
the Carrier specified the bridge was 803 feet long; that two large barge
cranes were necessary for the construction of nine piers in the river; and
that this included cofferdams in water ten to twenty feet deep with spans
weighing between 120,000 pounds and 185,000 pounds. In addition, the Carrier
consistently stated it did not possess the supervisory skills to direct the
construction of the bridge. Aside from mere assertions claiming the employees
did possess the necessary skills, the Organization presented no evidence to
support that Claim. The record further discloses the Carrier recalled three
furloughed carpenters, as well as a furloughed sectionman.
The Organization refers to a letter agreement entered into on
December 11, 1981, between the Organization and the National Railway Labor
Conference Committee. This Agreement refers specifically to the contracting
out provisions of the 1968 National Agreement and jointly reaffirmed the
"intent of Article IV of the May 17, 1968, Agreement that advance notice
requirements be strictly adhered to
...."
Herein, this is precisely what the
Carrier did on January 25, 1985, obviously in compliance with Article IV of
the 1968 National Agreement. In the absence of any language in the parties'
local agreement requiring such notice, the Organization's contention that the
Carrier's failure to specifically cite Article IV nullifies its efficacy is an
exercise in sophistry.
In summation, the Carrier provided the Organization with the requisite notice required by Articl
contention that Organization employees had never previously performed work as
contemplated in the Bonners Ferry project was not refuted nor was the Carrier's contention that its
skills to perform the work. This view is supported by the sheer magnitude and
complexity of the project. Finally, this Board finds no factual support for
the Organization's claim it could perform all the work involved or that some
of the work might have been reserved from the project and assigned to the
Claimants. See Third Division Awards 26504, 24281, 23102, and 20899.
Accordingly, we will deny this Claim.
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest:
Nancy J. r -,Executive Secretary
Dated at Chicago, Illinois, this 27th day of September 1990.