Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 28559
THIRD DIVISION Docket No. MW-28601
90-3-88-3-430
The Third Division consisted of the regular members and in
addition Referee Robert W. McAllister when award was rendered.

(Brotherhood of Maintenance of Way Employes PARTIES TO DISPUTE:



STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:

(1) The Carrier violated the Agreement when it assigned outside forces to perform repair work on Bridge 3125 at Guion, Arkansas beginning July 20, 1987 (Carrier's File 870714).

(2) The Carrier also violated Article IV of the May 17, 1968 National Agreement when it did not intention to contract said work.

(3) As a consequence of the violations referred in Parts (1) and/or (2) above, Foreman G. F. Ribbing, Assistant Foreman N. J. Bader, Carpenters K. D. Lack, C. R. Brown and Hoisting Engineers G. J. Bader and R. L. Hoots shall each be allowed pay at their respective rates for eight (8) hours per work day, plus all overtime and holidays lost, beginning July 20, 1987 and continuing until such time as the violation is corrected."

FINDINGS:

The Third Division of the Adjustment Board upon the whole record and all the evidence, finds that:

The carrier or carriers and the employe or employes involved in this dispute are respectively carrier and employes within the meaning of the Railway Labor Act as approved June 21, 1934.

This Division of the Adjustment Board has jurisdiction over the dispute involved herein.



Beginning July 20, 1987, the Carrier used a contractor to perform work in connection with bridge repair near Guion, Arkansas. The Organization asserts the Carrier's actions were in violation of the Agreement because (1) the work is reserved exclusively to employees covered by the Agreement, (2)
Form 1 Award No. 28559
Page 2 Docket No. MW-28601
90-3-88-3-430

the Agreement does not permit such work to be contracted out in the absence of extenuating circumstances, and (3) the Carrier failed to notify the General Chairman of its intent to contract out the work. The Carrier has denied the work in question is reserved exclusively to covered employees and, theref-re, it was under no obligation to serve a notice upon the Organization. Dur-_ the handling of this dispute on the property, the Carrier did not challenge the Organization's assertion that no notice was issued.

Article IV of the May 17, 1968, National Agreement requires as follows:



The Carrier bases its defense upon its position the Scope Rule is general in nature, and, thereby, not the type of rule which, on its face, grants exclusive jurisdiction of particular work to the covered employees. In the absence of such an express grant, continues the Carrier, the Organization must meet its burden of proving that the work has customarily and traditionally been performed by it all others. The Carrier asserts it is required to serve notice under Article IV only when there is a showing that the work is within the scope of the Agreement. The Organization the employees specifically by the Rules of the Agreement as well as past practice. The Organization because the Carrier is obligated to serve the notice regardless.

The weight of arbitral authority agrees with the Organization. In Third Division Award 18305, this Board held:


Form 1 Award No. 28559
Page 3 Docket No. MW-28601
90-3-88-3-430

Award 18305 provided a basis for a long series of Awards of this Board holding that the provisions of Article IV deal with work which is within the scope of the Agreement, but that the Organization is not required to show that the work had been performed exclusively to prove a violation of Article IV when no notice has been served. It is sufficient in this case that we find the work performed by the contractor is of the nature which has been assigned to employees under the Agreement. The Carrier, therefore, violated the Agreement by failing to serve
The Carrier has argued that damages should be limited to any Claimants who were not fully employ worked. The Organization submits that all Claimants should be entitled to damages. This Board has not been as consistent with respect to the question of damages for such a violation. To be sure, several of the Awards relied upon by the Organization in its argument that notice was required limit damages to furloughed employ warrant additional compensation to any Claimants for time when they were already fully employed. Accordingly, we direct the Claim be sustained only with respect to those Claimants who actually suffered wage loss as a result of unemployment during the time period the work was performed by the contractor.






                          By Order of Third Division


                  000,


Attest:
        49 16 ,

        Nancy J. Wer - Executive Secretary


Dated at Chicago, Illinois, this 27th day of September 1990.