Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 28559
THIRD DIVISION Docket No. MW-28601
90-3-88-3-430
The Third Division consisted of the regular members and in
addition Referee Robert W. McAllister when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Union Pacific Railroad Company (former Missouri Pacific
Railroad Company)
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when it assigned outside
forces to perform repair work on Bridge 3125 at Guion, Arkansas beginning July
20, 1987 (Carrier's File 870714).
(2) The Carrier also violated Article IV of the May 17, 1968 National Agreement when it did not
intention to contract said work.
(3) As a consequence of the violations referred in Parts (1) and/or
(2) above, Foreman G. F. Ribbing, Assistant Foreman N. J. Bader, Carpenters
K. D. Lack, C. R. Brown and Hoisting Engineers G. J. Bader and R. L. Hoots
shall each be allowed pay at their respective rates for eight (8) hours per
work day, plus all overtime and holidays lost, beginning July 20, 1987 and
continuing until such time as the violation is corrected."
FINDINGS:
The Third Division of the Adjustment Board upon the whole record
and all the evidence, finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employes within the meaning of the
Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the
dispute involved herein.
Parties to said dispute were given due notice of hearing thereon.
Beginning July 20, 1987, the Carrier used a contractor to perform
work in connection with bridge repair near Guion, Arkansas. The Organization
asserts the Carrier's actions were in violation of the Agreement because (1)
the work is reserved exclusively to employees covered by the Agreement, (2)
Form 1 Award No. 28559
Page 2 Docket No. MW-28601
90-3-88-3-430
the Agreement does not permit such work to be contracted out in the absence of
extenuating circumstances, and (3) the Carrier failed to notify the General
Chairman of its intent to contract out the work. The Carrier has denied the
work in question is reserved exclusively to covered employees and, theref-re,
it was under no obligation to serve a notice upon the Organization. Dur-_
the handling of this dispute on the property, the Carrier did not challenge
the Organization's assertion that no notice was issued.
Article IV of the May 17, 1968, National Agreement requires as follows:
"In the event a carrier plans to contract out
work within the scope of the applicable schedule
agreement, the carrier shall notify the General
Chairman of the organization involved in writing
as far in advance of the date of the contractias
transaction as is practicable and in any event
not less than 15 days prior thereto."
The Carrier bases its defense upon its position the Scope Rule is
general in nature, and, thereby, not the type of rule which, on its face,
grants exclusive jurisdiction of particular work to the covered employees. In
the absence of such an express grant, continues the Carrier, the Organization
must meet its burden of proving that the work has customarily and traditionally been performed by it
all others. The Carrier asserts it is required to serve notice under Article
IV only when there is a showing that the work is within the scope of the Agreement. The Organization
the employees specifically by the Rules of the Agreement as well as past practice. The Organization
because the Carrier is obligated to serve the notice regardless.
The weight of arbitral authority agrees with the Organization. In
Third Division Award 18305, this Board held:
"The first paragraph of said Article IV deals
with the contracting out of work 'within the
scope of the applicable schedule agreement.' It
does not say the contracting out of work reserved exclusively to a craft by history, custom, and tra
to add to, subtract from, or alter an existing
agreement. We therefore conclude that inasmuch
as Maintenance of Way Employes have in the past
performed such work as is in dispute here, then
said work being within the scope of the applicable Agreement before us, Carrier violated the
terms thereof by failing to notify the General
Chairman within 15 days prior to the contracting
out of said work
...."
Form 1 Award No. 28559
Page 3 Docket No. MW-28601
90-3-88-3-430
Award 18305 provided a basis for a long series of Awards of this
Board holding that the provisions of Article IV deal with work which is within
the scope of the Agreement, but that the Organization is not required to show
that the work had been performed exclusively to prove a violation of Article
IV when no notice has been served. It is sufficient in this case that we find
the work performed by the contractor is of the nature which has been assigned
to employees under the Agreement. The Carrier, therefore, violated the Agreement by failing to serve
The Carrier has argued that damages should be limited to any Claimants who were not fully employ
worked. The Organization submits that all Claimants should be entitled to
damages. This Board has not been as consistent with respect to the question
of damages for such a violation. To be sure, several of the Awards relied
upon by the Organization in its argument that notice was required limit damages to furloughed employ
warrant additional compensation to any Claimants for time when they were
already fully employed. Accordingly, we direct the Claim be sustained only
with respect to those Claimants who actually suffered wage loss as a result of
unemployment during the time period the work was performed by the contractor.
A W A R D
Claim sustained in accordance with the Findings.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
000,
Attest:
49
16 ,
Nancy J. Wer - Executive Secretary
Dated at Chicago, Illinois, this 27th day of September 1990.