Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 28590
THIRD DIVISION Docket No. MW-27887
90-3-87-3-411
The Third Division consisted of the regular members and in
addition Referee George S. Roukis when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Union Pacific Railroad Company
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:
(1) The Agreement was violated when the Carrier used on outside
concern to unload crossties on the right-of-way between M. P. 3.9. and M.P. 28
on March 10, 11, 12, 13 and 14, 1986, between M.P. 42 and M.P. 88.50 on March
17, 18, 19, 20, 21, 24, 25 and 26, 1986, between M.P. 547 and M.P. 580 on
March 31 and April 7, 8, 9, 10, 11, 14 and 15, 1986 (System File M-340/013/21052).
(2) Because of the aforesaid violation, Roadway Equipment Operator D.
Morgan shall be allowed one hundred sixty-eight (168) hours of pay at his
straight time rate."
FINDINGS:
The Third Division of the Adjustment Board, upon the whole record
and all the evidence, finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employes within the meaning of the
Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the
dispute involved herein.
Parties to said dispute waived right of appearance at hearing
thereon.
The basic facts in this case are set forth as follows: On November
25, 1985, Carrier served notice on the former General Chairman of its intention to contract out the
notice comported with the requirements of the December 11, 1981 Letter of Understanding.
The subcontracting proposal was later discussed on February 5, 1986,
at which time, Carrier pointedly maintained that the equipment needed for the
venture was not in its inventory and could not be leased.
Form 1 Award No. 28590
Page 2 Docket No. MW-27887
90-3-87-3-411
Carrier implemented its subcontracting proposal by utilizing MidSouth Railroad Service on the da
1986, contesting such action.
In defense of its position the Organization contends that work of the
character involved herein was encompassed within the scope of the Agreement
and consequently was protected work. It also argues that it was indeed possible for Carrier to use o
owned by Carrier and previously used to perform crosstie unloading work.
It observes that none of the exception factors detailed in Rule 52
(contracting) was present here and, as such, Carrier was effectively precluded
from contracting out the work.
Specifically, it points out that Agreement covered employees possessed the special skills needed
task and the work involved was not of such magnitude or of such nature as to
be termed an emergency. It further maintains that Carrier failed to make a
good faith effort to procure said equipment consistent with the clear require-.
ments of the December 11, 1981 Letter of Understanding, wherein to the extent
possible, it was agreed that maintenance of way forces be used. In other
words, by renting equipment, covered employees could perform the work.
In response, Carrier disputes the Organization contention that it had
the needed equipment to perform said work, arguing instead that it did not
have the Koehring 6611 Tie Unloader in its inventory. It maintains the Koehring 6611 was the only ma
Furthermore, since Mid-South Railroad Service did not lease
equipment, and required its own employees to operate equipment, it was not
possible to use Agreement covered employees.
Thus, according to the December 11, 1981, Letter of Understanding and
Rule 52 of the Controlling Agreement, it was operationally permissable to use
the Koehring 6611. It recognized that there was a "Jimbo Crane" at the Grand
Island Shop, but noted that the crane was inoperable and awaiting repairs.
In considering this case the Board concurs with the Organization's
position. The central defining issue herein is whether Carrier could have
used alternate equipment to unload crossties or was compelled by the lack of
such machines to utilize the Koehring 6611. There is no question that said
work accrued to Maintenance of Way forces and hence was protected, subject to
the contracting exceptions delineated in Rule 52 and further implicitly
protected by the December 11, 1981 Letter of Understanding. Since we find
that it was plausible indeed to use the Jimbo Crane or some of the other
equipment identified by the Organization, though it might have been less
efficient, we must conclude that Rule 52 was violated. None of the Rule 52
exceptions was present to justify subcontracting.
Form 1 Award No. 28590
Page 3 Docket No. MW-27887
90-3-87-3-411
On the other hand, we agree with Carrier that the monetary portion of
the Claim is excessive and accordingly, Claimant is to be compensated at the
straight time rate only for the time he was on furloughed status.
A WAR D
Claim sustained in accordance with the Findings.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest:
ncy J. Dev - ecutive Secretary
Dated at Chicago, Illinois, this 16th day of October 1990.