Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 28710
THIRD DIVISION Docket No. MW-26986
91-3-86-3-21
The Third Division consisted of the regular members and in
addition Referee Edwin H. Benn when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Norfolk and Western Railway Company (formerly The
Pittsburgh and West Virginia Railway Company)
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when it assigned outside
forces to perform masonry repair work in the McGugin and Craighead Tunnels on
the Connelsville District November 1 through December 3, 1984, both dates
inclusive (System File MW-ROK-84-14).
(2) As a consequence of the aforesaid violation, furloughed Carpenters J. Anderson, T. Ciesielski, C. Marsili, R. Phillis, M. Digman, P. Uscio,
B. Bryner and J. McKindley shall each be allowed eight (8) hours of pay at
their respective straight time rate and applicable overtime pay for each day
on which the outside concern performed the work mentioned in Part (1) hereof
during the claim period."
FINDINGS:
The Third Division of the Adjustment Board upon the whole record
and all the evidence, finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employes within the meaning of the
Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the
dispute involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
Claimants had seniority in the Bridge and Building Sub-department of
the Maintenance of Way and Structures Department. By letter dated May 29,
1984, the Carrier advised the Organization's General Chairman as follows:
"This is to advise you of Carrier's intent
to engage an outside contractor or contractors
for the purpose of performing tunnel maintenance
on three tunnels on the Pittsburgh Division,
Connellsville district.
Form 1
Page 2
Award
No.
28710
Docket
No.
MW-26986
91-3-86-3-21
This work will consist of the application of
pressurized epoxy and shotcrete to the following
tunnels:
McGugin Tunnel - Hickory, PA
Craighead Tunnel - Ave11a, PA
Greentree Tunnel - Rook, PA
Contractors have been consistently utilized to
perform this type of work on prior occasions.
The Carrier does not possess the necessary
skilled manpower, supervision or equipment to
satisfactorily accomplish a project of this
nature.
If you have any questions regarding this project
or wish to discuss it further, please let us
know."
According to the Carrier, "the work involved the inspection of the tunnel for
cracks and fissures at points of stress and the application of pressurized
epoxy and concrete to make repairs."
By letter dated June 2, 1984, the Organization requested a. meeting to
discuss matters raised in the Carrier's notification. Nevertheless, outside
forces performed the work until December 3, 1984.
In Third Division Award 25860, this Board addressed a dispute between
these parties concerning the use of outside forces to perform similar masonry
repair work in the Hickory Tunnel at Hickory, Pennsylvania. In sustaining the
Claim, this Board stated:
The work included inspection of the tunnel
for cracks and use of pressurized epoxy and concrete to repair them where found.
...
We believe the work involved here is work
reserved to the Bridge and Building Department
by Agreement unless contracting of it can otherwise be justified. As stated in Award 20372,
'Carrier has the burden to justify an exception.' In our view Carrier has not supported
Form 1 Award No. 28710
Page 3 Docket No. MW-26986
91-3-86-3-21
its position that its employes are not qualified
to perform the disputed work. While admitting
its employes pumped grout, etc. Carrier makes no
explanation of how the skills for these jobs
differ, if at all. Rather Carrier merely as
serts the epoxy and shotcrete are new develop
ments, but the facts show at least with refer
ence to the shotcrete, that there has been
disputes between the parties concerning it since
about 1970. While the Carrier now states it has
consistently contracted every project where the
process has been used no evidence in support of
this assertion is offered . ... As we find this
is work of a type reserved by Agreement to the
claiming employes, and as Carrier has presented
no evidence to establish its employes were not
capable of performing the work, or that the work
has consistently been contracted out, there is
no need to reach the question of the extent of
Carrier's responsibility to train.
Award 25860 covers this dispute. While the Carrier disagrees with
the reasoning of that Award, after reviewing that Award, we are unable to find
Award 25860 palpably erroneous. See also, Third Division Award 28339 between
these parties which also involved the use of outside forces to perform tunnel
masonry repair work ("Nonetheless, Award 25860 appears controlling here. It
has been carefully examined and not found to be in palpable error.") To now
hold otherwise would be an invitation to chaos.
Carrier's argument that "If Carrier had had the specialized equipment
and employees skilled in its operation to enable Carrier to perform the work
with its own forces, carpenters would have been used" is not persuasive. The
Carrier recognizes "that claimants held dual seniority as painters and carpenters." Therefore, see Award 25860 where, as here, the claimants therein were
also painters:
...
If, as Carrier contends, no B & B Department carpenters were on furlough and it would
have been carpenters, rather than Claimants who
would have performed the work, no relief would
be afforded Carrier by virtue of that fact. The
seniority roster is departmental and its benefits are available to all within its coverage."
Form 1 Award No. 28710
Page 4 Docket No. MW-26986
91-3-86-3-21
Further, the Carrier has not sufficiently demonstrated to deny this
Claim that "the application of pressurized concrete and epoxy involves the use
of expensive, specialized machinery which Carrier does not own, and with which
its employees have no experience whatever." Again, in accord with Award
25860, "Carrier has the burden to justify an exception." In light of the
prior Award ("Carrier has presented no evidence to establish its employes were
not capable of performing the work") and the fact that we are unable to conclude that the Carrier has sufficiently demonstrated in this matter that the
employees were not capable of performing the work, that argument cannot prevail in this case. Moreover, the Carrier's assertion that "any investment by
the Carrier for the purchase or rental of this equipment
...
would be a wasted
expense" is similarly not supported in this record. See Award 25860 ("The
record is silent on the question of how extensive or expensive the necessary
equipment is, how readily available leased or rented equipment might be and
what efforts in that direction were made by Carrier.").
In light of the missed work opportunity resulting from the Carrier's
use of outside forces and in light of Award 25860, Claimants shall be compensated. In this matter, the Organization seeks compensation for Claimants at
the applicable straight time and overtime rates "while the claimants were on
furlough status." The fact that Claimants were furloughed from the Paint
Gangs on October 31, 1984 and that the work at issue may have commenced in the
summer of 1984 does not change the result. The contracting out of the work
nevertheless amounted to a lost work opportunity during the period set forth
in the Claim. However, the organization's request in the Claim for overtime
is denied. Compensation shall be at the straight time rate as in Award 25860.
A W A R D
Claim sustained in accordance with the Findings.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest: _ s
Nancy J. r - Executive Secretary
41,
Dated at Chicago, Illinois, this 28th day of March 1991.