Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 28730
THIRD DIVISION Docket No. SG-29130
91-3-89-3-556
The Third Division consisted of the regular members and in
addition Referee James E. Mason when award was rendered.
PARTIES TO DISPUTE:
(Brotherhood of Railroad Signalmen
(Burlington Northern Railroad Company
STATEMENT OF CLAIM: "Claim on behalf of the General Committee of the Brotherhood of Railr
Railroad Company (BN):
On behalf of R. C. Nostdahl, for reinstatement to service, account of
Carrier violated the current Signalmen's Agreement, as amended, particularly,
Rule 54, when it assessed him with excessive and harsh discipline." General
Chairman's file D-88-490. Carrier file ESI-89-1-26.
FINDINGS:
The Third Division of the Adjustment Board upon the whole record
and all the evidence, finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employes within the meaning of the
Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the
dispute involved herein.
Parties to said dispute waived
right of appearance at hearing thereon.
Claimant was employed by the Carrier as a Signalman. He entered
Carrier's service on July 22, 1976. He was a fully qualified and experienced
Signalman. On September 21, 1988, Claimant was assigned to work as one-half
of a two-man team to change out track wires at M.P. 55.6 and M.P. 58 south of
Reno, Wyoming. Claimant and the other Signalman completed the work which they
performed at this location at approximately 11:30 A.M. on September 21, 1988.
At approximately 5:00 P.M. that date the Signal Maintainer at Reno Junction
was informed that the signals on which Claoimant and the other Signalman had
previously worked were not functioning properly. The Signal Maintainer -
along with the Signal Supervisor from Gillette, Wyoming - investigated the
reported occurrence and found that the signals on which the two-man team had
worked were displaying "False Clear" aspects. Their further investigation
developed that "- - the east track wires were plugged in on the west side of
the insulated joints and the west track wires were plugged on the east side of
the insulated joints."
Form 1 Award No. 28730
Page 2 Docket No. SG-29130
91-3-89-3-556
By notice dated September 22, 1988, both Claimant and the other Signalman were instructed to att
purpose of ascertaining the facts and determining your responsibility in connection with your failur
Signal 55.6 and 55.7 on September 21, 1988, between East Reno and Nacco Junction, resulting in an Un
The joint Investigation Hearing was held as scheduled. Both Claimant
and the other Signalman were present and represented. Both were permitted to
cross examine witnesses. Both were permitted to - and did - testify on their
own behalf. Both Claimant and the other Signalman were accorded all of the
due process rights to which they were entitled under the terms of the existing
labor contract.
Following the completion of the Investigation Hearing, the other Signalman - who had no prior di
by suspension of thirty (30) days for his involvement in and responsibility
for the incident in question. No appeal was taken from that assessment of
discipline. Claimant, whose prior discipline record contained three disciplinary suspensions plus a
2 1/2 months out of service), was dismissed for his involvement in and responsibility for the incide
An appeal on behalf of the Claimant was initiated and progressed by
the Organization. The on-property handling of the appeal alleged that Claimant was not guilty as cha
created the malfunctioning signal; that the Carrier acted in an arbitrary and
capricious manner in their assessment of dismissal against Claimant; that the
discriminatory dismissal of Claimant should be rescinded and that Claimant
should be returned to service and compensated for all time lost. The Statement of Claim to this Boar
alleged violation of Rule 54 of the Schedule Agreement and because of the
excessive and harsh discipline assessed against Claimant.
The Organization does not specify whic4 ,section of Rule 54 was
allegedly violated in this case. We have read the entire Rule as presented
by the Organization in their Ex Parts Submission and can find nothing in that
Rule which was violated by Carrier in the handling of this case.
We have read and studied the Hearing transcript and find that Claimant readily admitted that
for the work done at the location in quest,lon. He readily admitted that he
made no attempt on his own
or
in conjunction with the other Signalman to test
or otherwise determine the working capability of the signals after the two of
them had completed their work. His response in this regard was "I was sure
that mine were all right - - - I thought he probably checked his." This cavalier attitude is what le
conditions. The Investigation Hearing record contains more than substantial
evidence to support the conclusion that the Claimant contributed to the signal
malfunction which followed the work done by him and the other Signalman on the
date in question.
Form 1 Award No. 28730
Page 3 Docket No. SG-29130
91-3-89-3-556
Once the guilt of the charge had been established by the testimony
and evidence in the Hearing record, Carrier was entirely proper in considering
the employees' past records in determining the amount of discipline which
should be assessed. The fact that the other Signalman involved in this case
was disciplined to a lesser degree than Claimant based upon the absence of
prior derelictions by the other Signalman does not create a discriminatory
situation. On the contrary, the Carrier has not only a right but also an
obligation to consider the absence of prior assessments of discipline when
determining the amount of discipline to assess on a first-time offender.
However, there are factors in the record of this case which cause us
to believe that permanent dismissal from service of Claimant may indeed be
arbitrary, capricious and excessive. The Hearing transcript indicates that
the signal diagram print which the Signalmen were using during the work in
question was not completely correct and that this error on the print could
have been a contributory factor in the malfunction which resulted from the
work performed by the two Signalmen. This alleged incorrect print is referenced at pages 25, 27, 28,
referenced during the on-property appeals of this case. This issue, therefore, is properly before ou
itself was not made a part of the case record submitted to this Board even
though it was identified on the property by Carrier.
While we are fully aware of the function of this Board as an appellate tribunal in deciding disc
is sufficient mitigation of the proven charge against Claimant to justify
permitting him to have one last chance to prove to the Carrier that he can and
will perform his duties in a complete, competent and correct manner in the
future. Toward that end, Claimant should be reinstated to service with seniority unimpaired, but wit
examinations which are normally required of employees of his craft and class.
A W A R D
Claim sustained in accordance with the Findings.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
v
Attest:
--.
Nancy J er - Executive Secretary
Dated at Chicago, Illinois, this 28th day of March 1991.