91-3-89-3-205


(Brotherhood of Maintenance of Way Employes PARTIES TO DISPUTE: (Union Pacific Railroad Company

                STATEMENT OF CLAIM: As shown in Docket No. MW-28808 and not repeated herein.


                FINDINGS: The Third Division of the Adjustment Board finds:


That the dispute was certified to the Third Division of the Adjustment Board ex parte by the petitioning party; and

Under date of March 7, 1991, the petitioning party addressed a formal communication to the Executive Secretary of the Third Division requesting withdrawal of this case from further consideration by the Division which request is hereby granted.

                        A W A R D


        Claim withdrawn.


                            NATIONAL RAILROAD ADJUSTMENT BOARD

                            By Order of Third Division


Attest:

      Nancy J. De -.Executive Secretary


Dated at Chicago, Illinois this 28th day of March 1991.