Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 28819
THIRD DIVISION Docket No. MW-28588
91-3-88-3-429
The Third Division consisted of the regular members and in
addition Referee Robert W. McAllister when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(CSX Transportation, Inc. (former Seaboard System Railroad)
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when, without a conference
having been held between the General Chairman and the Chief Engineering
Officer as required by Rule 2, it assigned and/or permitted outside forces to
perform track removal, switch work, reconstruction and overall maintenance in
Howell Mill Yard at Atlanta, Georgia beginning August 11, 1987 (System File
HMY-87-88/12(87-1187).
(2) Because of the aforesaid violation, each of the Claimants named
below* shall be allowed pay at his respective pro rata rate of pay for the
number of man-hours consumed to his exclusion by the outside contractor beginning August 11, 1987 an
corrected.
Name ID N0. Position
E. L. Thompson 160252 Foreman
C. Heard 172983 Machine Operator Class 3
C. Daniels 165990 Trackman
E. T. Howell 163222 Crankhand
D. Moon 165989 Trackman
K. J. Turner 149721 Foreman
S. A. Hopper Trackman
M. Alexander 171805 Trackman
D. W. Thompson 168322 Trackman
T. V. Farmer 164415 Trackman"
FINDINGS:
The Third Division of the Adjustment Board upon the whole record
and all the evidence, finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employes within the meaning of the
Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the
dispute involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
Form 1 Award No. 28819
Page 2 Docket No. MW-28588
91-3-88-3-429
Beginning August 11, 1987, certain work, which the Organization avers
is reserved to it under the Agreement, was performed by a contractor at Howell
Mill Yard in Atlanta, Georgia. The Carrier asserts this yard is leased to
Bulk Distribution Centers, Inc., a wholly owned and separate corporate entity.
The Carrier states this work was performed by the contractor for and at the
request of Bulk Distribution Centers, Inc., and not the Carrier.
In support of its position, the Carrier furnished the Organization
with a copy of a short term (interim) license, under which Bulk Distribution
Centers, Inc., received a license, pending formal lease negotiations, entitling it to use of the yar
license, which reads as follows:
"Licensee shall not make, erect or perform construction on the Premises without prior written co
CSXT. Any partitions, structures or other equipment
necessary in connection with the use of the track or
space by Licensee
will
be provided by and at the sole
expense of Licensee. Upon vacating said Premises,
Licensee will remove said partitions, structures and
equipment in a manner satisfactory to CSXT."
We do not agree with the Organization's suggestion that the Carrier
required prior written consent as a means to ensure work was done in accordance with the Agreement.
provisions, which requires the licensee to perform all such work at its own
expense. Provisions requiring a landlord's prior consent to construction are
not uncommon in leases, and are often designed to protect adjacent property or
the landlord's future enjoyment of the land. Such a provision does not, in
and of itself, place the work within the Carrier's direction or control.
Whether the property was leased or licensed to the third party is
a legal distinction which has no bearing on this dispute. By the terms of the
license, the Carrier ceded dominion and control over the disputed work, which
removed the work from the coverage of the Agreement. See Third Division
Awards 21283 and 23575. The work was not performed at the Carrier's
instigation or expense, nor was it for the Carrier's benefit. Therefore,
there has been no violation of the Agreement.
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest:
ancy J. D -Executive Secretary
Dated at Chicago, Illinois, this 25th day of June 1991.