Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 28941
THIRD DIVISION Docket No. MW-28517
91-3-88-3-339
The Third Division consisted of the regular members and in
addition Referee Gil Vernon when award was rendered.
(Brotherhood of Maintenance of Way Employee
PARTIES TO DISPUTE:
(CSX Transportation, Inc. (former Seaboard System
( Railroad)
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when, without a conference
having been held between the Chief Engineering Officer and the General
Chairman, as required by Rule 2, it assigned and/or permitted outside forces
to perform paving work at the Joe McIntosh Road grade crossing located at Mile
Post S-819.8 on the Yeoman Subdivision beginning May 29, 1987 [System File
SF5T36-87-75/12(87-899) Q].
(2) As a consequence of the aforesaid violation, Section Foreman W.
H. Hodges, Apprentice Foreman D. R. Kinards, Machine Operator J. L. Merritt,
Crankhand T. Scott, Jr. and Trackmen R. L. Standifer, E. Sanders and L.
Sanders shall each be allowed eight (8) hours of pay at their respective
straight time rates."
FINDINGS:
The Third Division of the Adjustment Board, upon the whole record
and all the evidence, finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employes within the meaning of the
Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the
dispute involved herein.
Parties to said dispute waived right of appearance at hearing
thereon.
This Claim arose when the Joe McIntosh Road was widened. This road
serviced the plant of Florida Steel Corporation (FSC), and its widening required the reconstruction
with Carrier's track. Carrier deployed its appropriate track gang for all
elements of the reconstruction work except for the finishing work, which
consisted of asphalt paving.
Form 1 Award No. 28941
Page 2 Docket No. MW-28517
91-3-88-3-339
The parties raise a number of issues and contentions in connection
with this work. Among them are whether the disputed work was covered by the
Scope Rule, whether it was covered by the Contracting Rule and whether the
Organization had exclusive rights to perform the work. The Board, however,
based on a careful review of the record, finds these matters to be side issues. We find the determin
There is no basis in the record to conclude that this project was
"Carrier's work." The record shows that the work would not have been done if
it had not been for Florida Steel Corporation's desire to have its service
road widened. FSC initiated the work and absorbed all costs, including those
of Carrier's track gang. In effect, Carrier was hired by FSC to perform work
on the crossing. The record does not show any material benefit to Carrier's
railroad operation, nor does it show Carrier had any control over the decision
to have a contractor do the paving. According to the evidence, that arrangement was handled entirely
Overall, the evidence ldoes not show that Carrier contracted out any
of its work, nor does it show that Carrier was in control of the work. Prior
decisions of this Board hold that no contracting of work violations exist
under these circumstances. See, for example, Third Division Awards 26816,
26082 and 24078.
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest~o
Nancy r - Executive Secretary
Dated at Chicago, Illinois, this 29th day of August 1991.