Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 29016
THIRD DIVISION Docket No. MW-27125
91-3-86-3-179
The Third Division consisted of the regular members and in
addition Referee Elliott H. Goldstein when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(St. Louis Southwestern Railway Company
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:
(1) The Agreement was violated when the Carrier assigned outside
forces to perform cleaning and tie handling work in the Texarkana Yards and on
the Eustace Branch in the vicinity of Athens, Texas beginning March 4, 1985
(System File MW-85-17-CB/53-814).
(2) The Carrier also violated Article 33 when it did not give the
General Chairman advance written notice of its intention to contract said work.
(3) As a consequence of the aforesaid violations, furloughed Laborers H. N. Montgomery and R. W.
hours of pay at the laborer's straight time rate for March 4, 5, 6, 7, 8, 11,
12, 13, 14, 18, 19 and 20, 1985 and eight (8) hours of pay for each day, subsequent to March 20, 198
to in Part (1) hereof."
FINDINGS:
The Third Division of the Adjustment Board upon the whole record
and all the evidence, finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employes within the meaning of the
Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the
dispute involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
The instant claim on behalf of two furloughed laborers, is based on
the Organization's contention that outside forces were used to perform Maintenance of Way work in vi
that beginning March 4, and continuing through March 14, 1985, two Spencer
Pilgreen employees were used by the Carrier to clean the right-of-way in the
Texarkana Yards, working in conjunction with the tie gang, and assisting the
tie handler operator in banding ties.
Form 1 Award
No.
29016
Page 2 Docket
No.
MW-27125
91-3-86-3-179
The Organization further contends that similar work was performed by Spencer
Pilgreen employees
on
a continuing basis, beginning March 18, 1985, on the
Carrier's Eustace Branch near Athens, Texas. It is also the Organization's
position that the Carrier violated Article 33 of the current Agreement by
failing to notify the General Chairman.
The Carrier argues that its letter to the Organization dated February
14, 1985, constituted sufficient notice of its intent to subcontract out the
work at issue here. The letter states:
"Under provisions of Article 33 of the
current agreement, this is notice of the Carrier's intent to contract out the following
work:
Clean up debris along tracks and in yards
on Pine Bluff Division. Contractor will utilize
a yard cleaner operated by contractor forces.
It is necessary to utilize a contractor for this
work as Carrier yard cleaners are being fully
utilized.
This work will begin approximately March 1,
1985 and continue for approximately 75 working
days.
The Carrier further asserts that the ties removed by production tie
gangs have been sold to Spencer Pilgreen and other outside companies for many
years, and it has always been their responsibility to remove the old ties.
The banding of ties by Spencer Pilgreen consisted of the banding of the used
ties that had been purchased and was not violative of the Agreement, the Carrier insists.
The first issue in the case turns on whether the Carrier's February
14, 1985 letter constituted sufficient notice of its intent to subcontract.
In reviewing the record in its entirety to make a determination on this question, the Board notes th
parties for the first time before this Board on appeal. Those new contentions
are deemed waived. Confining ourselves to the record on the property, this
Board is of the view that the notice was sufficiently specific so as to inform the Organization <
February 14, 1985 letter is somewhat generic in nature in the sense that no
particular contractor is expressly named, we find that it served its requisite
purpose under Article 33 by giving the Organization advance notice of the
action taken.
The second question is whether outside forces were used to perform
Maintenance of Way work in violation of the Agreement. The Organization
asserted in its Claim that Spencer Pilgreen employees performed cleaning and
tie handling work. The Carrier countered by arguing that Spencer Pilgreen
purchased the material as it was removed from the track structure and was
solely responsible for its disposition.
Form 1 Award No. 29016
Page 3 Docket No. MW-27125
91-3-86-3-179
The Carrier's contention is in the nature of an affirmative defense.
If proven by substantive evidence, we would agree that the work would cease to
be within the scope of the Agreement once title to the material transfers.
However, the evidence necessary to substantiate that critical point is lacking. Significantly, the C
indicate a sale took place, nor was there any probative evidence submitted regarding the practice cl
That being the case, and the Carrier not having advanced any further
arguments refuting the Organization's claim to the work in question, we rule
to sustain Paragraphs 1 and 3 of the claim. Paragraph 2, pertaining to the
notice provision, is denied.
A W A R D
Claim sustained in accordance with the Findings.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest:
Nancy J. D e Executive Secretary
Dated at Chicago, Illinois, this 28th day of October 1991.