Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 29019
THIRD DIVISION Docket No. MW-28857
91-3-89-3-259
The Third Division consisted of the regular members and in
addition Referee Herbert L. Marx, Jr. when award was rendered.

(Brotherhood of Maintenance of Way Employes PARTIES TO DISPUTE:



STATEMENT OF CLAIM: "Claim of the system Committee of the Brotherhood that:

(1) The Agreement was violated when the Carrier assigned outside forces (Robertson's Machine Shop) to perform routine maintenance on the Marley Bridge in Addis, Louisiana beginning September 21, 1987 (Carrier's File 871029 MPR).

(2) The Carrier also violated Article IV of the May 17, 1968 National Agreement when it did not give the General Chairman advance written notice of its intention to contract said work.

(3) As a consequence of the violations referred to in Parts (1) and/or (2) above, B&B Foreman D. G. Townley, B&B Assistant Foreman R. H. Hutchins, B&B Helper M. L. Durant and First Class Ironworkers D. J. Smith, J. C. Williams and P. L. Ingram shall each be allowed pay at their respective straight time and overtime rates for all straight time and overtime hours expended by the contractor performing the work identified in Part (1) above beginning September 1, 1987 and continuing until the violation was corrected."

FINDINGS:

The Third Division of the Adjustment Board upon the whole record and all the evidence, finds that:

The carrier or carriers and the employe or employes involved in this dispute are respectively carrier and employes within the meaning of the Railway Labor Act as approved June 21, 1934.

This Division of the Adjustment Board has jurisdiction over the dispute involved herein.



On September 21-24, 1987, the Carrier engaged a contractor to make repairs on a bridge in the vicinity of Addis, Louisiana. No notice of such work was provided to the Organization under the provisions of Article IV-Contracting Out of the May Form 1 Award No. 29019
Page 2 Docket No. MW-28857
91-3-89-3-259
"In the event a carrier plans to contract out work within the
scope of the applicable schedule agreement, the carrier shall
notify the General Chairman of the organization involved in
writing as far in advance of the date of the contracting
transaction as is practicable and in any event not less than
15 days prior thereto.





In its defense, the Carrier cited in its Submission 269 instances of contracting bridge, repair work (paralleling similar information provided on the property during the claim handling procedure). This includes many instances before and after the The Carrier contends that such occurrences were not challenged by the Organization. However, there i
The Board does not support the Carrier's view that the Claim must fall based on a failure by the Organization to show that it has performed such work on an exclusive basis. Further, there is little support for the contention that such work must
In view of the extended practice as to contracting work such as here under review, however, the Board is guided by previous Awards under parallel circumstances. As one example, Third Division Award 28610, reviewing closely similar if not identical Rule language, stated as follows:


Form 1 Award No. 29019
Page 3 Docket No. MW-28857
91-3-89-3-259
the notice violation that the Organization could prevail.
Given the long period of time during which the Organization has
acquiesced in the practice of contracting out the disputed work,
however, it is the opinion of the Board that the Organization
cannot now claim a violation of Rule 52 without first putting
Carrier on notice that it believed advance notification was
required in this particular instance. Accordingly, it is our
judgment that the Board herein is limited to directing Carrier
to provide notice in the future, just as in Third Division
Award 26301."
4 W A R D






      Kiz '&V~ 0/

Attest: ,
      Nancy J. er - Executive Secretary


Dated at Chicago, Illinois this 28th day of October 1991.